United States
Gemini Program
Quarterly
Review
of
The Gemini Near
Infrared Spectrograph
(GNIRS)
Held
October 5, 2001
at
Tucson, Arizona
Distribution
AURA President
NOAO
Director
Gemini
Head of Instrumentation
US
Project Scientist
US
Project Manager
Instrument
Team Manager
USGP Report of
the Quarterly Review for GNIRS
1.
Meeting Background
A
USGP Quarterly Review (QR) of GNIRS was held on October 5, 2001. The meeting was
attended by Taft Armandroff (US Project Manager) and Mark Trueblood (Work
Package Manager) from the USGP, Mark Hunten (Gemini observer), and members of
the GNIRS team including Neil Gaughan (GNIRS Project Manager), Jay Elias
(Instrument Scientist), and Peter Ruckle (GNIRS Software Engineer). Others
attending by telecon were Dan Weedman (NSF) and Jeremy Mould (Director, NOAO).
The
goal of the QR’s is to evaluate each instrument project's overall status with
respect to the entire project lifetime and to review and assess recent progress
in a number of different areas on a periodic basis, with emphasis on management
and high-level concerns. Specifically, the USGP uses a formal mechanism to
determine whether a project is on track with respect to budget and schedule, and
to identify potential problems before they significantly impact progress.
2.
Major Findings
Previous
schedule slips amounting to about 2 months, coupled with additional slips in
delivery by an outside vendor of the bulkhead assembly and in the design and
fabrication of the radiation shields forced the integration phase of the project
to be re-planned to preserve the original delivery date. The result is that the
Pre-Ship Acceptance Test continues to be scheduled to be complete in late summer
of 2002, but with a consequence that the Project Manager now reports schedule
contingency down to 6 weeks. This effectively removes contingency from the
schedule when one considers how unstructured the effort of system integration
is, and how dynamic the redefinition of the ordering of tasks is on a daily
basis during this project phase. The work on the critical path will be performed
by a few people in this loosely structured, dynamic task environment. This will
require very close monitoring and supervision by the Project Manager throughout
the remainder of the project to prevent an evenly-paced march to the finish line
from degenerating into a slow crawl or worse yet, a haphazard random walk.
The
main area behind schedule remains mechanical design, for the reasons noted in
previous QR reports, but the focus of both attention and the source of new
problems has shifted to fabrication, as would be expected of a project at this
mature stage. We expect both design to be complete, and fabrication to be
completed or nearly so by the next QR, so the focus of attention should be
shifting at that point to the integration effort and the challenges that that
activity poses.
The
projected delivery date has not changed significantly in the last two years,
despite considerable refinement of the design, updates to the schedule based on
the details of the current design, and shifting of management focus from design
to fabrication, and now to integration and testing.
The
Project Manager made a special effort at this QR to address several areas of
concern expressed by the USGP in the previous QR report. We commend the Project
Manager for taking our comments seriously and addressing them in a detailed,
forthright, and responsive manner.
The
GNIRS overall status is that the instrument is in the final design and
fabrication phase:
More
work needs to be done in mechanical design and fabrication, but these items
should be complete by the end of the calendar year. Electronics and software
fabrication are nearly complete, with subsystem integration under way in both
areas.
In
the previous QR, the USGP estimated that the GNIRS team could meet their then
current schedule despite their being slightly behind schedule at that point in
time, provided:
(a)
The GNIRS
team is able to schedule around the inability of IGPO to deliver the OIWFS
components by the end of CY2000.
(b)
The final
BaF2 lens is delivered on schedule in August, and
(c)
IGPO
delivers the NOAO flexure rig no later than December 31, 2001 (assuming a month
for installation and test before first use in February).
Regarding
these points:
(a)
Gemini
delivered the OIWFS components, but many were not as expected, did not meet the
ICD, or the ICD proved to be poorly written. Consequently, NOAO has had to
perform a large amount of rework, which has delayed the project and reduced the
contingency.
(b)
The final
BaF2 lens will be delivered in November, which is consistent with the
revised integration plan.
(c)
Gemini
awarded the flexure rig contract, with delivery expected in March. This would
permit first use of the flexure rig with GNIRS in April, consistent with the
revised integration schedule.
The
Work Package Manager (WPM) still believes that it is possible for the Team to
meet its schedule, but due to the reduced contingency, this is increasingly
unlikely. Therefore, the WPM now estimates that GNIRS will pass its Pre-Ship A/T
in late October 2002 and arrive at Cerro Pachón in November 2002. That is, the
WPM believes the project will be delivered 2 months late with respect to the
current schedule.
3.
Project Summary
3.1
Project Overview and Key Accomplishments
The
key accomplishments since the last QR have been:
·
Completed
design of 17 of 19 fixed assemblies, with the remaining assemblies expected to
be complete by the end of November
·
Completed
fabrication of all but one mechanism, the Focus Assembly, which should be
complete by the end of October
·
Completed
fabrication and fit check of all optical benches
·
Awarded
contract for the fabrication of the Bulkhead Assembly, which should be complete
and leak tested with the dewar shell by the end of November
·
Began
mechanism and optical subassembly testing, which should be complete by
mid-December
·
Received
all optics except for one BaF2 camera lens and some flats
·
Completed
electronics thermal enclosure fabrication and checkout
·
Completed
initial coding of Components Controller software and began initial testing
·
Received
OIWFS components from Gemini’s contractor, the University of Hawaii
3.2 Project Status and Plans
The GNIRS project is on schedule according to the recently revised schedule. However, the WPM believes the instrument will be delivered about 2 months late, since the revised schedule leaves only 6 weeks of contingency after the beginning of February and the flexure rig will not be ready until April. If major problems with flexure are not detected until then (drawing a parallel with NIRI) the integration and testing phase could be drawn out significantly longer than currently planned.
The following goals for this October 2001 QR that were
met are (some of these are from previous QR’s):
·
Complete fabrication of all benches
· Complete electronics thermal enclosure fabrication and checkout
· Complete initial software coding of the Components Controller
·
Start final testing of the Component Controller software
The following goals for this October 2001 QR that were not
met are (some of these are from previous QR’s; goals have been combined for
clarity):
· OIWFS integration. Gemini did not deliver the OIWFS components per Amendment 4 of the GNIRS Work Scope by September 5, 2000 and finally delivered the parts late during this past summer. The revised integration plan presented at the QR takes this late delivery into account.
·
Release rotary prototype report. Writing the report was
placed at a lower priority than other work, but the results were incorporated
into the design. The Project Manager indicated that given the quantity of work
remaining on the project, the prototype testing SDN on this topic will have to
suffice as a prototype test report. This goal will be removed from the goals for
the next QR.
· Release linear prototype report. Writing the report was placed at a lower priority than other work, but the results were incorporated into the design. The Project Manager indicated that given the quantity of work remaining on the project, the prototype testing SDN on this topic will have to suffice as a prototype test report. This goal will be removed from the goals for the next QR.
· Complete lens delivery and acceptance testing. The remaining camera lens has been delivered, but has a flaw. It will be used until Janos can make a replacement. Acceptance testing at the vendor plant is scheduled for November, then the lens must be coated before shipping to NOAO, with delivery expected sometime in December 2001.
·
Complete fabrication of all mechanisms. Of the 9
mechanisms, only the Focus Assembly remains, and this should be complete by the
end of October.
·
Complete 3D design of all fixed assemblies. 17 of 19 fixed
assemblies have 3D design complete, with the rest complete by the end of
November.
·
Complete 2D design of all fixed assemblies. This should be
complete by the next QR.
· Complete dewar to electronics thermal enclosure cabling fabrication. The design is complete, and fabrication is waiting for final dimensions. This should be complete by the next QR.
· Complete fabrication of the Bulkhead Assembly. After delays in generating and releasing drawings to the vendor, and subsequent changes to the drawings, this is now scheduled for delivery by Bechdon in mid-November after leak testing, which was not part of the original work allocated to this vendor.
· Complete fabrication of most dewar components (radiation shields and shells but not mounting trusses or cryo head hardware). Radiation shield design was delayed by analysis work done on other parts. This is now on the Critical Path, and is expected to be completed in mid-December.
· Complete 75% of mechanism and optical subassembly testing. Mechanism testing was delayed by a lack of complete mechanisms to test. This situation is being rectified, and mechanism testing was beginning about the time of the QR.
· Receive all optics. The remaining items were the replica flats and the BaF2 camera lens replacement. These are now expected in November.
· Plans for documentation. The Project Manager discussed how he would address missed milestones, such as the A/T Plan, but not the overall documentation approach, which is scheduled in the future. The USGP recommends that this important set of tasks not be overlooked, as they can consume valuable skilled resources near the end of the project when there is considerable pressure to release such resources to other projects prematurely.
By the next review, nominally scheduled for January 2002, the Project Manager plans to:
· Complete 3D design of all fixed assemblies
· Complete 2D design of all fixed assemblies
· Complete fabrication of all mechanisms
· Complete fabrication of the bulkhead assembly
· Complete mechanical fabrication, except for:
o rework items
o shipping container
o items associated with flexure testing
· Complete mechanism and optical subassembly testing
· Receive all optics
· Complete dewar to electronics thermal enclosure cabling fabrication
· Complete OIWFS components integration onto the OIWFS bench
· Complete electronics fabrication and checkout, except for:
o some cables may remain to be fabricated
o some rework items identified in system integration may remain
· Complete testing of the Components Controller software with the electronics
· Complete and deliver the Acceptance Test Plan
· Complete and deliver the Change Order for delivery of GNIRS to Chile
· Complete and deliver the Change Order revision for the Differential Pressure Switch
· Complete and deliver manual outlines
The project is 82% complete from the Restart Review to the completion of the Pre-Ship Acceptance Test, now scheduled for late August 2002.
3.3
Project Problems and Concerns
At
the previous QR the following were identified as concerns:
At the October QR, the Project Manager listed problems that he had dealt with during the previous quarter, but not ongoing problems that he would need to watch during the coming quarter. However, as noted above, the WPM believes that, despite the current status depicted by the latest MS Project schedule update on the recently revised schedule, the project is now 2 months behind schedule in a way that cannot be recovered, and that this will result in late delivery of the instrument by that amount. This conclusion is supported by the fact that contingency in the schedule is reduced to 6 weeks, which for the dynamic, fluid activity that is system integration, is uncomfortably small, given the experience of other Gemini instruments. It might even be quite generous to limit the overrun prediction at this stage to 2 months, given all this past history. Also as noted above, the integration phase will require the constant attention, involvement, and vigilance of the Project Manager on a daily basis to keep it on track and moving forward at a reasonable pace.
3.4 Project Schedule
The
summary-level project schedule is available on the GNIRS Web site (a copy is
attached to this report). An analysis of the schedule performance of each major
engineering discipline appears below. In past phases of the project, the
Critical Path was deliberately designed so that no single mechanism could delay
the instrument until System Integration. Instead, it included various steps in
most of the mechanisms. Now that the project is entering the System Integration
phase, this no longer applies, and the Critical Path is occupied by a limited
number of sequential tasks performed by a very limited number of people,
increasing the need for the Project Manager’s close scrutiny.
3.5 Project Milestones, Cost, and Manpower Charts
A
summary-level Microsoft Project schedule is attached as an appendix. This
reporting category is not repeated for each work area below, since all work
areas are represented in the project schedule and manpower charts. The manpower
charts were presented in the handouts and will not be repeated in this report,
except at a summary level.
3.6
Project Budget and Expenditures to Date
The
estimated cost (from January 1999 forward) decreased slightly ($90k) from the
June QR value of almost $4.2 million to just below $4.1 million, the latter
value being below the original estimate in January 1999. At no point since the
Restart Review has the estimated cost at completion exceeded $4.3 million.
The
cost of the entire project continues to be estimated to be $6.3M, including the
$2.4M spent between the project start in October, 1995 and December 31, 1998. As
of the end of August 2001, the project had spent a total of $5,552,477 against a
planned value of $5,730,878 yielding an underrun of $178,401. Most of the
underrun is in labor, primarily in Mechanics in the area of fabrication.
Increased capital costs for sending parts to outside machine shops did not
completely offset the lack of instrument makers available to the project, in
part because the project is slightly late with having drawings ready for
fabrication. USGP expects this underrun to be spent in accordance with the
Project Manager’s current projections. The estimated cost of the project has
not exceeded $6.5M since early 1999.
3.7
Organization
The
project appears to be staffed with a sufficient number of competent staff.
Design drafting, which was an area of concern in previous phases of the project,
is no longer of concern because design is almost done and the demand for
designers is greatly reduced from previous levels. As mentioned in the previous
QR report, some of the instrument makers have been used for mechanism assembly
and fit checks, so more parts than originally planned had to be sent outside for
fabrication. This increased the burden on procurement as well as the engineering
staff for oversight. Due to delays in beginning the design of the radiation
shields and other work, the Project Manager delayed the previously scheduled
departure of Ed Hileman from the project until the radiation shields are
designed, and of Dale Circle until the end of the calendar year.
Furthermore,
each key engineering position is only one deep, so when a person leaves the
project, no immediate replacement is usually available to fill the gap. At this
late stage of the project, loss of an engineer would ensure a delay in the
delivery date, perhaps of several months.
4.
Project Management
4.1
Project Management Overview and Key Accomplishments
The
Project Manager continues to exert proper management control over the project.
4.2 Project Management Status and Plans
The
project continues to be effectively managed. The fact that the projected
delivery date and Estimated Cost At Completion have not changed significantly in
almost three years since the current Project Manager was assigned to the project
reflects the pressure the Project Manager is applying to the staff to maintain
the schedule, and his skill in reworking the schedule when problems do arise.
The
major issue now facing the Project Manager is keeping the system integration
effort on track. This will require:
The
USGP also reminds the Project Manager of the huge documentation task that lies
ahead, and of the resources and time required to address this task. Although
some personnel have been assigned to begin writing manuals, the enormity of the
undertaking should not be underestimated. The USGP recommends that the Project
Manager direct a fair portion of his energy and time to reviewing this task now
and determining whether the plan now in place is adequate and fits well with the
current schedule and staffing plan.
4.4
Project Management Schedule
The
Project Manager usually delivers reports on schedule and meets his other
schedule obligations. Project Management is a level of effort activity that is
71% complete.
4.5
Project Management Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
4.6
Project Management Organization
The
GNIRS Project Management organization consists of Neil Gaughan (Project
Manager), Dan Eklund (assigned half time as Project Assistant), and Melissa
Bowersock (Administrative Assistant to the Project Manager).
5.
Systems Engineering
5.1
Systems Engineering Overview and Key Accomplishments
None
– this activity is complete.
5.2
Systems Engineering Status and Plans
From
this point on, systems engineering activity will consist of sustaining
engineering support to the other engineering staff.
5.3
Systems Engineering Problems and Concerns
None
5.4
Systems Engineering Schedule
No
further systems engineering work is scheduled.
5.5
Systems Engineering Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
5.6
Systems Engineering Organization
The
GNIRS systems engineering group consists of Jay Elias (GNIRS Instrument
Scientist and lead systems engineer), Dick Joyce (KPNO IR spectroscopist) , and
Brook Gregory (CTIO instrument scientist).
6.
Optics Design
The
optics design is complete. All further optical work is in the area of
procurement, installation, alignment, and integration.
7.
Optics Fabrication
All optics fabrication is being performed by outside
contractors. Optical procurement is 86% complete.
8.
Mechanical Design
8.1
Mechanical Design Overview and Key Accomplishments
The
Team completed design for 7 fixed assemblies during the last quarter, bringing
the total to 17 of 19 fixed assemblies designed. Work on the design of the
Bulkhead Assembly was completed and the contract for its fabrication was
awarded. This led to an even greater understanding of the overall instrument
envelope, and a request for a second waiver from Gemini for a small amount of
space for a hose/wiring distribution/breakout panel and for crossover cabling
and hoses under the dewar shell. Gemini granted this waiver, which permitted the
design to go forward.
8.2
Mechanical Design Status and Plans
Mechanical
design and fabrication (which are reported together) are 87% complete overall
with benches 100% complete, mechanisms 92%, and fixed assemblies 62%. The
current status (as of the QR date) of the design of fixed assemblies is that 17
of 19 are complete.
Plans for the next QR are to have all 3D and 2D designs complete. The major pacing item on the Critical Path for the entire project is the design of the radiation shields.
8.3
Mechanical Design Problems and Concerns
Staffing
of design drafting is no longer of concern. There are no other mechanical design
problems or concerns, other than completing the design of the radiation shields
as quickly as possible.
8.4
Mechanical Design Schedule
The
fixed assemblies are about 2 months behind schedule, showing a marked
improvement from the 5.5 months behind schedule at the previous QR. This is an
indication that the mechanical design work is drawing to a close, though there
is still work remaining to be completed.
The
Bulkhead Assembly, identified at the previous QR as being on the Critical Path,
has been designed and the contract was awarded in September for its fabrication.
A subsequent update to the contract to add mounting bosses for counterweights
and to require the contractor to perform the leak check delayed delivery until
the end of November, but it must be remembered that this shifts work and risk to
the contractor to deliver a fully tested dewar assembly with vacuum integrity.
The
design item now on the Critical Path is the radiation shields. The Project
Manager expects the 3-D model to be done by late October, and the 2-D
fabrication drawings to be done by mid-November. Fabrication is expected to be
complete by mid-December. Additional design staff would not accelerate this
item.
8.5 Mechanical Design Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
8.6
Mechanical Design Organization
The
GNIRS mechanical engineering group consists of Ed Hileman (benches and fixed
assemblies) and Gary Muller (mechanisms and engineering management systems). The
mechanical design group consists of John Andrew (lead), Dave Rosin, Eric Downey,
and Dale Circle. Dale was scheduled to leave the project on October 1, but will
be retained until the end of the calendar year.
9.1
Mechanical Fabrication Overview and Key Accomplishments
Fabrication
is complete on all but 1 mechanism (focus assembly). All bench fabrication is
complete, and the benches have undergone a fit check. Of the 19 fixed
assemblies, 17 had completed design, 4 had completed fabrication, and 9 were in
fabrication at the time of the QR.
9.2
Mechanical Fabrication Status and Plans
Fabrication status is not reported separately from design (see above). By the next QR, all mechanical fabrication should be complete, except for:
· rework items,
· the shipping container, and
·
items associated with flexure testing.
9.3
Mechanical Fabrication Problems and Concerns
In
the previous QR report, the USGP raised a concern about the slow ramp-up of
assigning instrument makers to GNIRS versus the plan. Since most of the parts
have now been fabricated, this is no longer a concern.
The
major concerns raised at this QR are:
These
are discussed in greater detail in the next section.
9.4
Mechanical Fabrication Schedule
Most
of the parts fabrication delays reported in the previous QR are no longer of
concern, with the exception of the Bulkhead Assembly. This critical and complex
assembly, if it fails its vacuum test and is delayed for rework, could easily
move past the radiation shields onto the Critical Path. The vendor is mature and
experienced, having performed well on NASA space mission hardware contracts, and
should be able to diagnose and cure any problems detected in preliminary vacuum
leak checks.
Once
the radiation shields are designed, since they appear to be relatively
straightforward, their fabrication should go quickly and smoothly. However, the
USGP recommends that the design engineers work with the instrument makers to
arrive at a final design that simplifies fabrication, shortens the fabrication
schedule, and reduces risk.
9.5
Mechanical Fabrication Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
9.6
Mechanical Fabrication Organization
Mechanical parts fabrication is performed by a
combination of outside machine shops and the NOAO instrument shop. NOAO
instrument makers assemble and check out each subassembly. The NOAO instrument
makers assigned to GNIRS include John Stein, Randy Bennett, Lou Lederer, and Ron
Harris.
10.
Electronics Design
10.1 Electronics Design Overview and Key
Accomplishments
Electronics
design is complete.
10.2 Electronics Design Status and Plans
Electronics
design is complete.
10.3 Electronics Design Problems and Concerns
None.
10.4 Electronics Design Schedule
Electronics
design is complete.
10.5 Electronics Design Budget and Expenditures to
Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
10.6
Electronics Design Organization
The
GNIRS electrical engineer is Jerry Penegor. He is assisted by electronics
technician Ron George.
11.
Electronics Fabrication
11.1 Electronics Fabrication Overview and Key
Accomplishments
Fabrication
and checkout of the components controller thermal enclosure is complete.
11.2 Electronics Fabrication Status and Plans
The overall electronics effort for design and fabrication stands at 86% complete. The only remaining electronics fabrication work is:
· wiring the dewar
· fabricating cables
·
fabricating the dewar warm-up controller
By the next QR, these items will be complete.
11.3 Electronics Fabrication Problems and Concerns
None.
11.4 Electronics Fabrication Schedule
Electronics
fabrication is approximately on schedule. The only item on the detailed schedule
shown behind schedule is the software test fixture, but since the Instrument
Components Controller is now wired and checked out, it is available for software
checkout and the software test fixture is no longer needed.
11.5 Electronics Fabrication Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
11.6
Electronics Fabrication Organization
The GNIRS electrical engineer is Jerry Penegor, assisted by electronics technician Ron George.
12.
Software Design
12.1
Software Design Overview and Key Accomplishments
The
software design is essentially complete.
12.2
Software Design Status and Plans
Overall
the software design is quite similar to that used by GMOS, with the exception
that actual component control is performed in ordinary C software instead of
EPICS software written in C.
The
design is mature and well-understood.
12.3
Software Design Problems and Concerns
None
12.4
Software Design Schedule
The
software design is essentially complete.
12.5 Software Design Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
12.6
Software Design Organization
The
GNIRS software engineer is Richard Wolff with EPICS software provided by Peter
Ruckle. This will change upon Dr. Wolff’s retirement on October 31.
13.
Software Fabrication
13.1
Software Fabrication Overview and Key Accomplishments
Since
the previous QR, the OCSwish simulator was delivered and coding was completed on
the Components Controller, Lab Support software, and Detector Interface
software.
13.2
Software Fabrication Status and Plans
Overall,
the software is 85% complete and is approximately on schedule according to the
GNIRS Project Summary Schedule. The coding for the Component Controller, Lab
Support, and Detector Interface software are complete. The EPICS code is 82%
complete.
13.3
Software Fabrication Problems and Concerns
The
USGP expressed a concern in the previous QR report regarding the impending
retirement of Richard Wolff and the prospect of losing his expertise. Peter
Ruckle, who has worked for most of the current project’s lifetime with Dr.
Wolff on the GNIRS software, will be assuming Dr. Wolff’s duties as lead
software engineer. Mr. Ruckle made a detailed presentation at the QR that
indicated he was knowledgeable in the entire scope of GNIRS software and firmly
in control of the entire effort. The USGP believes the remaining software work
on GNIRS can be performed by Mr. Ruckle without further assistance from Dr.
Wolff, though apparently the latter will be available part-time for
consultation, if needed.
The
outstanding issues remaining from previous reviews were addressed to the
USGP’s satisfaction. These were:
13.4
Software Fabrication Schedule
The
software fabrication is approximately on schedule.
13.5 Software Fabrication Budget and Expenditures to
Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
13.6
Software Fabrication Organization
The
GNIRS software engineer is Richard Wolff with EPICS software provided by Peter
Ruckle. This will change, as noted above, upon Dr. Wolff’s retirement on
October 31.
14.
Subsystem Integration
14.1
Subsystem Integration Overview and Key Accomplishments
Due to the late delivery of the OIWFS, delays in the
Bulkhead Assembly and the radiation shields, and a late start in beginning cold
tests of the mechanisms (due to their not being available as early as originally
planned), subsystem integration was re-planned as part of the overall
integration phase re-planning.
14.2 Subsystem Integration Status and Plans
The
benches were assembled with a couple of the mechanisms for a fit check, which
revealed a minor vignetting problem. This required minimal machining of some
support structures that was completed before sending the post-slit bench out for
painting. Cold testing of mechanisms was about to begin at the time of the QR
meeting.
Electronics
checkout of the Components Controller rack was completed just before the QR
meeting.
Software
testing and debugging at the module and subsystem level was 74% complete at the
time of the QR meeting.
The
Team plans to have all subsystem integration completed by the next QR.
14.3
Subsystem Integration Problems and Concerns
See above.
14.4
Subsystem Integration Schedule
See above. Alignment and integration were due to begin April 1, but due to the delays mentioned above, these activities are several months late, and have been rescheduled.
14.5
Subsystem Integration Budget and Expenditures
to Date
The GNIRS Statement of Work does not require this WBS
element to be reported separately to the USGP.
14.6
Subsystem Integration Organization
Various engineers and technicians perform subsystem
integration, depending on which subsystem it is.
15.
System Integration
15.1
System Integration Overview and Key Accomplishments
System
integration begins in October.
15.2 System Integration Status and Plans
System
integration will begin with opto-mechanical integration, starting with the
benches in October. Mechanism cold testing will proceed in parallel with this
activity.
15.3
System Integration Problems and Concerns
Other
Gemini instruments have endured protracted integration periods that have delayed
instrument delivery, despite mechanism cold testing and other precautions.
Although the GNIRS team has endeavored to avoid the mistakes of other teams to
date, and has scheduled several months for system integration, the compacted
schedule and the virtual elimination of schedule contingency have made it
unlikely that the instrument will be delivered on schedule. It remains to be
seen if the GNIRS team will fare better than others in terms of problems they
encounter during the system integration and test and checkout phases of the
project. A well-planned and coordinated approach to system integration is
essential to maintaining control of the schedule.
With
respect to integrating the OIWFS, the agreement with Gemini is that if
significant problems are encountered, the team will consult with Gemini (through
the USGP) for direction on whether to proceed, how much effort to expend, and to
request assistance from Gemini or the IfA. The USGP congratulates the team for
its adherence to this agreement in the past, and encourages it to continue this
trend in the future. This is important to keeping staff working on Critical Path
tasks from being diverted to diagnosing problems that are not NOAO’s concern.
15.4
System Integration Schedule
The
project is moving in accordance with the recently-revised schedule.
15.5
System Integration Budget and Expenditures to Date
The GNIRS Statement of Work does not require this WBS
element to be reported separately to the USGP.
15.6
System Integration Organization
Various engineers and technicians perform system
integration, depending on the subsystem being integrated into the instrument.
The primary personnel performing system integration are Jay Elias and Dick
Joyce.
16.
Test and Checkout
No test and checkout tasks were scheduled to begin before
the Quarterly Review. The previous QR report contained a note indicating it was
Gemini’s responsibility to deliver a flexure rig in time for NOAO to install
it by the GNIRS need date of February, 2002. Due to the rescheduling of
integration, the need date is now April, which is consistent with both the
contract that Gemini awarded and the availability of the new facility NOAO has
planned.
17.
Documentation and Training
17.1
Documentation and Training Overview and Key Accomplishments
The Team delivered a Test Plan outline and approach, and
circulated a preliminary draft of an Acceptance Test Plan.
17.2 Documentation and Training Status and Plans
Documentation is several months behind schedule. The Test
Plans document was due March 2001 and was 6 months late at the time of the QR
meeting.
17.3
Documentation and Training Problems and Concerns
As noted in the previous QR report, the Acceptance Test
Plan (ATP) is late. The Team began work on this important document and is making
progress. However, the author, the Instrument Scientist, is also behind schedule
on mechanism cold tests and will soon be working on system integration, so it is
not clear that he will have the time to complete this document when it is
needed. Experience with other US Gemini instrument teams has shown that several
iterations of the document are required for Gemini and USGP approval of the
format and content of the document.
Besides the ATP, the team is responsible for producing
two Change Orders (change of venue to Chile/Commissioning, and the Differential
Pressure Switch) and the Manual Outlines. These tasks are important, given the
time needed to develop manual outlines and the usual iteration with Gemini.
17.4
Documentation and Training Schedule
The documentation task completion status is:
· electronics -- 95% complete
· test plans – 81%
· manuals – 0%
·
as-built fabrication drawings – 0%.
Although
the percent complete claimed for as-built fabrication drawings is 0%, the
process for drawing update and release, and parts fabrication is to update the
drawings first before parts are fabricated, instead of redlining drawings on the
instrument makers desk. This should speed up the task of generating and
delivering as-built fabrication drawings.
17.5
Documentation and Training Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
17.6
Documentation and Training Organization
For
electronics documentation, the responsible parties are the GNIRS electrical
engineer, Jerry Penegor, assisted by electronics technician Ron George. Jay
Elias is writing the Test Plans. Manual outlines are being prepared by Jay Elias
and Peter Ruckle.
18.
Other Activities
No
tasks for other activities were scheduled to begin before the Quarterly Review.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
NOAO
Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360