United States
Gemini Program
Quarterly
Review
of
The
Gemini Near Infrared Spectrograph
(GNIRS)
Held
August
15, 2000
at
Tucson,
Arizona
1.
Meeting Background
A
USGP Quarterly Review (QR) of GNIRS was held on August 15, 2000. The meeting was
attended by Taft Armandroff (US Project Manager) and Mark Trueblood (Work
Package Manager) from the USGP, and Neil Gaughan (GNIRS Project Manager), Jay
Elias (Instrument Scientist), and Dan Eklund (GNIRS Project Assistant) from
NOAO/GNIRS. Others attending included Dan Weedman (NSF) and Sidney Wolff (NOAO).
The
goal of the QRs is to evaluate each instrument project's progress in a number of
different areas, with emphasis on management and high-level concerns.
Specifically, the USGP uses a formal mechanism to determine whether a project is
on track with respect to budget and schedule, and to identify potential problems
before they significantly impact progress.
2.
Major Findings
Overall,
the project is approximately 1.7 months behind the current schedule, an increase
from being 1 month behind schedule at the previous QR three months ago. The main
area behind schedule is mechanical design. This occurred even after the Project
Manager asked both mechanical engineers to work a considerable amount of
overtime after the Pre-Fabrication Review (PFR) in May. The problem was in the
transition that occurred from the previous lead mechanical engineer to the
current engineer. The previous engineer delayed the project by several months,
and did not leave the drawings in a state ready for analysis. Consequently,
considerable effort was required after the PFR just to determine which drawings
were the latest versions, and to get them ready for structural analysis. Further
problems were encountered in submitting AutoDesk Mechanical Desktop drawings to
MSC NASTRAN that required help from MSC programming staff.
The
estimated cost and projected delivery date have not changed significantly in the
last year, despite considerable refinement of the design and updates to the
schedule and budget based on the details of the current design. Since the last
QR/PFR, the team has completed the basic design and analysis of the optical
benches, with only a few details remaining to be completed (e.g., location of
screw holes) before awarding contracts for their fabrication.
The
USGP estimates that the GNIRS team can meet their current schedule despite their
being slightly behind schedule at this point in time, provided they take steps
(a) to achieve milestones on their due dates, and (b) to move on to the next
task when each milestone is completed. The Project Manager identified this as
partly a cultural problem that he understands and is addressing. The USGP is
pleased to see that the Project Manager understands the situation and is taking
steps to bring it under control. This is a very serious issue that will be
reviewed at the next QR.
The
USGP was pleased to see in the handout at the QR an official response from the
team to the PFR committee. This will be sent to the Gemini review committee
chair for further distribution at his discretion. We also note that the Project
Manager has addressed several requests made by Dr. Weedman and the USGP at the
last review, such as including a milestone chart showing milestones scheduled
and achieved by quarter, and rationalizing the budget and actual dollars by
removing the scientists’ time from the budget figures. This demonstrates a
continuing responsiveness to customer requests by the GNIRS team.
3.
Project Summary
3.1
Project Overview and Key Accomplishments
The
key accomplishments since the last QR have been:
·
Completed
structural analysis of the main optical benches
·
Continued
refinement of the mechanism designs
·
Fabricated
parts for environmental cover assembly
·
Laid out
the electronics schedule and integrated it into the overall project schedule
·
Built the
software prototype hardware
·
Completed
the overall software design, and continued software fabrication
·
Obtained
results from the rotary and linear prototypes
·
Master
gratings ruled; met specifications
·
Revised
the detailed schedule of all tasks needed to complete the design and to
fabricate, test, and deliver the instrument
3.2 Project Status and Plans
The GNIRS project is about 1.7 months behind the current
schedule. All goals for this August, 2000 QR were met, which included:
· Review the recommendations of the PFR committee report and the team’s responses, and how they will be integrated into the project plan
· Review the status of structural analysis of the optical benches and other analysis that should have been completed before the PFR
· Review the status of the rotary, linear, and bearing prototypes; what was learned, and how that was folded into the mechanism designs
· Review the status of the 3D engineering model of the instrument, and the plan for producing 2D fabrication drawings
·
Given the lessons learned from NIRI (that the majority of flexure
appears to originate from mechanisms in an unpredictable way), explore with the
team how they intend to meet the stringent Gemini flexure requirement
It appears that the team is close to meeting the flexure requirement, but how close the bench is to meeting its budgeted flexure will not be known for about 2-3 weeks while the optical engineer completes his analysis using inputs from the mechanical engineer’s analysis of the optical bench flexures. Originally, this was supposed to have been completed before the PFR, and the USGP had hoped this would have been completed by this QR. Mechanism flexure will not be analyzed, and will not be known until tested to first order in the test dewar. The full cumulative effect of mechanism flexures will not be known until system integration is well along. A backup plan is in place to add active flexure compensation at the collimator mirror, but as the Instrument Scientist noted, this has its limits, and as the US Project Manager noted, it can also have undesired side effects. The team appears to be making good progress in its 3-D modeling of the instrument and in producing 2-D fabrication drawings, but to date, drawing production per se is not pacing fabrication. This situation could change very soon, as analysis of benches is completed.
The project is 29% complete from the Restart Review to the delivery of the instrument in July, 2002, compared to 35% complete if it were on schedule.
By the next review, nominally scheduled for
mid-November, the Project Manager plans to:
· Award contracts for fabrication of all optical benches
· Award contracts for fabrication of 3 of the remaining 6 mechanisms
· Complete 3-D designs of all remaining mechanisms
· Complete lens delivery and acceptance testing
· All optics on order or delivered
· Begin 3-D design of 5 of the 16 fixed assemblies
· Begin electronics fabrication
· Begin OIWFS components integration
In addition, the USGP expects to see the following
milestones completed:
· Rotary prototype report
· Linear prototype report
·
Grating master ruling test report
3.3
Project Problems and Concerns
The
USGP could find no major problems that require the attention of management
outside NOAO. The Project Manager noted the following items that he is watching
closely:
The
USGP considers the Project Manager capable of dealing with these situations
within NOAO.
3.4 Project Schedule
The
summary-level project schedule is available on the GNIRS
Web site. An analysis of the schedule performance of each major engineering
discipline appears below. The Critical Path was deliberately designed so that no
single mechanism could delay the instrument. Instead, it includes various steps
in most of the mechanisms.
3.5 Project Milestones, Cost, and Manpower Charts
A
summary-level Microsoft Project schedule is available on the GNIRS
Web site. This reporting category is not repeated for each work area below,
since all work areas are represented in the project schedule and manpower
charts.
3.6
Project Budget and Expenditures to Date
The
cost of the project is estimated to be $6.6M, including the $2.4M spent between
the project start in October, 1995 and December 31, 1998. As of June, the
project had spent a total of $3,650,212 against a planned value of $4,359,120
yielding an underrun of $709k. Most of the underrun is in labor ($537k), and
given the slip of the PFR from February to May, USGP expects this underrun to be
used by the end of the project. Some of it may be used in increased capital
costs in an attempt to shorten the fabrication schedule through increased use of
outside machine shops.
3.7
Organization
The
project appears to be staffed with a sufficient number of competent staff.
However, each position is only one deep, so when a person leaves the project, no
immediate replacement is usually available to fill the gap. An organization
chart is included in the Quarterly
Review Presentation.
4. Project Management
4.1
Project Management Overview and Key Accomplishments
The
Project Manager continues to exert proper management control over the project.
Since the last QR, the Project Manager and his assistant revised the schedule to
include more details about the software and to permit the new electronics
engineer, Jerry Penegor, to replan the electronics design and fabrication effort
according to his understanding of the requirements, the needs of other parts of
the projects, and his way of working.
4.2 Project Management Status and Plans
The
project continues to be effectively managed. The Fabrication Review Board
mentioned in the previous QR report was established to formalize the process of
deciding whether to make an assembly in the NOAO machine shop or to use an
outside shop.
4.3
Project Management Problems and Concerns
At
the last QR, it was noted that the lead mechanical engineer responsible for
structural design was replaced with one more attuned to analysis and to
performing to a schedule. The new engineer, Ed Hileman, has accepted full
responsibility for his portion of the design and analysis effort, has been
willing to work extra hours over a sustained period to help keep the project on
schedule, and has demonstrated his competence in structural analysis and other
engineering expertise at a depth often lacking on this project in the past. The
USGP congratulates the Project Manager for successfully dealing with a problem
that threatened to delay the project to the point of possibly making the
instrument no longer interesting to Gemini.
There
are no other project management problems or concerns.
4.4
Project Management Schedule
The
Project Manager usually delivers reports on schedule and meets his other
schedule obligations.
4.5
Project Management Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
4.6
Project Management Organization
The
GNIRS Project Management organization consists of Neil Gaughan (Project
Manager), Dan Eklund (assigned half time as Project Assistant), and Melissa
Bowersock (Administrative Assistant to the Project Manager).
5. Systems Engineering
5.1
Systems Engineering Overview and Key Accomplishments
As
recommended by the PFR committee, the thermal analysis is considered completed
as of the PFR. The mechanical structural analysis of the benches was completed
August 15, and the results were given to the optical engineer for calculation of
the image motion. All prototyping is complete except for final reports.
5.2 Systems Engineering Status and Plans
Systems
engineering is 97% complete. Knowledge gained from the prototypes was fed into
the designs for the rotary and linear mechanisms. Plans include writing the
final reports for the rotary and linear prototypes.
5.3
Systems Engineering Problems and Concerns
None
5.4
Systems Engineering Schedule
Complete
systems engineering activities this summer before mechanism fabrication begins.
5.5
Systems Engineering Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
5.6
Systems Engineering Organization
The
GNIRS systems engineering group consists of Jay Elias (GNIRS Instrument
Scientist and lead systems engineer), Dick Joyce (KPNO IR spectroscopist), and
Brook Gregory (CTIO instrument scientist).
6.
Optics Design
The
optics design is complete. All further optical work is in the area of
procurement, installation, alignment, and integration.
7.
Optics Fabrication
All optics
fabrication will be performed by outside contractors. Optical procurement is 34%
complete.
8.
Mechanical Design
8.1
Mechanical Design Overview and Key Accomplishments
The
pre-slit, post-slit, and OIWFS optical benches have been designed and the
structural analysis has been completed. The slit/decker and filter wheel
assemblies have been 3-D modeled. To enable the engineering and drafting teams
to maintain the schedule, the team changed its drafting software package from
AutoDesk Mechanical Desktop to SolidWorks.
8.2
Mechanical Design Status and Plans
Mechanical
design and fabrication (which are reported together) are 16% complete overall
(versus a calendar value of 35%) with benches 16% complete, mechanisms 24%, and
fixed assemblies 1%. Effort will focus on mechanism 3-D design definition to
finalize mechanism/bench interfaces in time to release bench drawings to
fabrication vendors on schedule in September.
8.3
Mechanical Design Problems and Concerns
The
new senior mechanical engineer, Ed Hileman, who was hired to replace Larry
Goble, has accepted responsibility for the bench design and analysis and has
performed well, as noted earlier. However, problems in the drawings left behind
by Mr. Goble and in the interface between Mechanical Desktop and NASTRAN have
caused further schedule slips, despite many hours of overtime worked by both
mechanical engineers. These interface problems have been solved, but further
overtime will be required to get the project back on schedule.
Once
the 3-D modeling is complete, designers will be needed to extract 2-D
fabrication drawings from the 3-D models. These fab drawings must be properly
dimensioned, toleranced, annotated for production processes and finishes, and
checked. The Project Manager noted that some designers are more productive than
others. This could become an issue by the next QR.
8.4
Mechanical Design Schedule
The
post-slit optical bench design and analysis activities are about two months
behind schedule,
8.5
Mechanical Design Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
8.6
Mechanical Design Organization
The
GNIRS mechanical engineering group consists of Ed Hileman (benches and fixed
assemblies) and Gary Muller (mechanisms and engineering management systems). The
mechanical design group consists of John Andrew (lead), Dave Rosin, Eric Downey,
and Rick Robles.
9.
Mechanical Fabrication
9.1
Mechanical Fabrication Overview and Key Accomplishments
The
environmental cover mechanical parts have been fabricated on schedule. The
assembly itself is slightly behind schedule, awaiting connectors and minor
assembly for completion. Fabrication of the motor drive units was begun but has
not been completed.
9.2
Mechanical Fabrication Status and Plans
Mechanical
fabrication was scheduled to have begun, but has not begun, on the Camera
Turret. This was deferred to concentrate effort on preparing drawings needed to
award fabrication contracts for the Post-slit Optical Bench and the OIWFS Bench.
9.3
Mechanical Fabrication Problems and Concerns
The
new senior mechanical engineer, Ed Hileman, who was hired to replace Larry
Goble, has accepted responsibility for the bench design and analysis and has
performed well, as noted earlier. However, problems in the drawings left behind
by Mr. Goble and in the interface between Mechanical Desktop and NASTRAN have
caused further schedule slips, despite many hours of overtime worked by both
mechanical engineers. These interface problems have been solved, but further
overtime will be required to get the project back on schedule.
One
concern is that the current schedule is based on internal fabrication estimates
based on mechanical concepts developed a year ago. Until 2-D fabrication
drawings are ready and firm quotes are obtained from machine shops, it will not
be known if these estimates were realistic. Multiple vendors will be used to
find shops that (a) can finish work in the shortest time and that (b) are not
heavily loaded with GNIRS work or other competing work. To the extent possible,
the NOAO instrument shop will be used for incoming inspection of parts made
elsewhere and for assembly of subassemblies and for correction of parts
fabrication errors.
The
USGP views the transition of the project from what has been largely a design
enterprise to a fabrication effort as a challenge. At the next QR, the
experience with fabrication and impact on the schedule will be reviewed.
9.4
Mechanical Fabrication Schedule
The
post-slit optical bench design and analysis activities are about two months
behind schedule,
with
other activities about a month behind schedule. If the engineers work additional
overtime, the first attempt at the post-slit bench fabrication is successful,
and no serious problems are encountered in system integration, it is likely this
will not significantly impact the final delivery date of the instrument.
9.5
Mechanical Fabrication Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
9.6
Mechanical Fabrication Organization
Mechanical parts fabrication will be performed by a combination of outside machine shops and the NOAO instrument shop. The latter will assemble and check out each subassembly.
10.
Electronics Design
10.1 Electronics Design Overview and Key
Accomplishments
Since
the previous QR, the electronics engineer, Jerry Penegor, reviewed the
requirements and the Statement of Work and developed a plan and task schedule
that were incorporated into the project schedule. He also designed a mechanism
motor simulator for software testing, which has been fabricated and delivered to
the software engineer.
10.2 Electronics Design Status and Plans
Electronics
design is on schedule. Electronics design and fabrication are reported together
as 4% complete. Design activities underway include the cabling for the dewar,
mechanisms, and the OIWFS.
10.3 Electronics Design Problems and Concerns
None.
10.4 Electronics Design Schedule
Electronics
design is on schedule.
10.5 Electronics Design Budget and Expenditures to
Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
10.6
Electronics Design Organization
The
GNIRS electrical engineer is Jerry Penegor.
11.
Electronics Fabrication
11.1 Electronics Fabrication Overview and Key
Accomplishments
The
mechanism motor simulator for software testing was fabricated and is ready for
test and checkout.
11.2 Electronics Fabrication Status and Plans
Fabrication
of the deliverable electronic hardware will begin in September.
11.3 Electronics Fabrication Problems and Concerns
None.
11.4 Electronics Fabrication Schedule
Electronics
fabrication is on schedule.
11.5 Electronics Fabrication Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
11.6
Electronics Fabrication Organization
The
GNIRS electrical engineer is Jerry Penegor. The Project Manager was recently
given permission to hire a contract electronics technician to assist the
engineer with construction tasks.
12.
Software Design
12.1
Software Design Overview and Key Accomplishments
Since
the previous QR, the software design was elaborated and coding progressed.
12.2
Software Design Status and Plans
The
software design is considered to be mature. When the T-ReCS EPICS OCS interface
design becomes available, this will be compared to the GNIRS design and the
latter updated if needed.
12.3
Software Design Problems and Concerns
None
12.4
Software Design Schedule
The
software design is on schedule.
12.5 Software Design Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
12.6
Software Design Organization
The
GNIRS software engineer is Richard Wolff.
13.
Software Fabrication
13.1
Software Fabrication Overview and Key Accomplishments
Work
has progressed on the Components Controller and the EPICS code.
13.2
Software Fabrication Status and Plans
Overall,
the software is 27% complete. The Components Controller is 56% complete, and the
EPICS code is 5% complete. The Project Manager reports software to be under
control.
13.3
Software Fabrication Problems and Concerns
None
13.4
Software Fabrication Schedule
The
software fabrication is slightly behind schedule, due to the software
engineer’s waiting for test apparatus to be fabricated. That was recently
completed, so now rapid progress is expected to be made and USGP expects the
schedule to be recovered in full.
13.5 Software Fabrication Budget and Expenditures to
Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
13.6
Software Fabrication Organization
The
GNIRS software engineer is Richard Wolff.
14.
Subsystem Integration
No
subsystem integration was scheduled to begin before the Quarterly Review.
15.
System Integration
No
system integration was scheduled to begin before the Quarterly Review.
16.
Test and Checkout
No
test and checkout tasks were scheduled to begin before the Quarterly Review.
17.
Documentation and Training
No
documentation or training tasks were scheduled to begin before the Quarterly
Review.
18.
Other Activities
No
tasks for other activities were scheduled to begin before the Quarterly Review.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
NOAO
Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360