United States
Gemini Program
Quarterly
Review
of
The
Gemini Near Infrared Spectrograph
(GNIRS)
Held
January 24, 2002
at
Tucson, Arizona
1.
Meeting Background
A
USGP Quarterly Review (QR) of GNIRS was held on January 24, 2002. The meeting
was attended by Dan Weedman (NSF), Taft Armandroff (US Project Scientist,
acting) and Mark Trueblood (Work Package Manager) from the USGP, Mark Hunten
(Gemini observer), Larry Daggert (NOAO Engineering and Technical Services
Manager) and members of the GNIRS team including Neil Gaughan (GNIRS Project
Manager), Jay Elias (Instrument Scientist), and Dan Eklund (GNIRS Project
Assistant). Others attending by videocon were Bernadette Rodgers (Gemini GNIRS
Instrument Scientist) and Jeremy Mould (Director, NOAO).
The
goal of the QR’s is to evaluate each instrument project's overall status with
respect to the entire project lifetime and to review and assess recent progress
in a number of different areas on a periodic basis, with emphasis on management
and high-level concerns. Specifically, the USGP uses a formal mechanism to
determine whether a project is on track with respect to budget and schedule, and
to identify potential problems before they significantly impact progress.
2.
Major Findings
The
radiation shields have taken far longer than originally planned, and even longer
than predicted at the previous QR, resulting in a slip of the delivery date of
the instrument from August 2002 to October 2002. Mechanism cleaning and testing,
which had been predicted at the previous QR to have been completed by this QR,
is far behind schedule, and is competing with radiation shields for the Critical
Path.
The
result is that the Pre-Ship Acceptance Test has slipped significantly for the
first time since the Restart Review, and is now scheduled to be complete in
October 2002. As at the previous QR, the Project Manager reports schedule
contingency holding at 6 weeks. This is a result of the slip in the delivery
date, the removal of redundant tasks in the later months of 2002, and use of
previously “written off” time during the holiday season in December, 2001.
No compression of tasks during the testing phase after initial bench integration
was done to retain the 6-week contingency.
The
main area behind schedule remains mechanical design (of the radiation shields),
followed closely by cleaning of parts and mechanism testing. Although USGP had
expected mechanical design to be complete roughly two QR’s ago, and
fabrication to be completed by this QR, it appears that underestimates by the
engineers of the amount of work involved when the initial planning was done,
coupled with the project manager’s failure to take immediate action when the
engineers failed to adhere to the plan, have resulted in a very large schedule
slip that now threatens to delay instrument delivery until early 2003. A
mitigating factor in the management of the shields was that while one engineer
was designing the passive shields, the other mechanical engineer was designing
the active shield and appeared to be making good progress. However,
subsequently, it was discovered that there were problems with the design of the
active shield that required that it be abandoned late in its design cycle,
causing a major setback to the schedule. In hindsight, this might have been
avoided had some sort of cross-communication mechanism been put in place for the
two engineers to check their designs with each other to make sure they were on
the right track. This would have slowed progress on the passive shields, but in
the end, might have saved time in the overall schedule.
The
GNIRS overall status is that the instrument is leaving the final design and
fabrication phase, and entering the subsystem testing phase:
More
work needs to be done in mechanical design and fabrication, but these items
should be complete by the next QR, except for items associated with flexure
testing and the shipping container. Electronics enclosure fabrication and
checkout is complete, with only cable fabrication and dewar wiring remaining.
Basic software coding is complete, with dm-defined engineering screens
coded and running the slit slide and filter wheel using EPICS records.
Additional software effort will be required to reconfigure many of the
engineering screens already coded that have not yet been reviewed by the
Instrument Scientist for content and organization.
The
Work Package Manager (WPM) now believes that it is unlikely that the instrument
will be ready to be shipped from Tucson before February 2003, due to the
schedule slips mentioned above and the fact that the instrument has not yet
begun system integration, where unforeseen problems are likely to be
encountered.
3.
Project Summary
3.1
Project Overview and Key Accomplishments
The
key accomplishments since the last QR have been:
·
Completed
OIWFS component integration; detector installation was on hold, waiting for the
GFE prism to be delivered (since the prism is late, detector installation will
proceed)
·
Completed
fabrication of all mechanisms, some rework is in progress
·
Completed
delivery and testing of all optics for the instrument (the schedule also shows
procurement of optics for the Flexure Rig, which is not a deliverable to Gemini;
this task is on schedule)
·
Completed
fabrication and fit check of the Bulkhead Assembly and dewar shells
·
Completed
initial integration of Components Controller software with actual mechanisms and
EPICS records and dm-coded engineering screens
3.2 Project Status and Plans
The GNIRS project is on schedule according to the recently revised schedule. Note that this is the second time in as many QR’s that the schedule has been revised to accommodate schedule slips due to design and fabrication delays. Despite being on schedule now, the WPM believes the instrument will be delivered (passing the Pre-Ship A/T) about 4 months late (February 2003), since (a) the revised schedule still leaves only 6 weeks of contingency, (b) recent history has shown parts cleaning will take far longer than anticipated, even with the addition of a technician to this effort, (c) the schedule shows a great deal of parallel effort in both cleaning and mechanism testing that is unrealistically optimistic, (d) there are only four cool-down cycles planned, and other Gemini instruments have demonstrated the need for about twice this number to fix unanticipated problems. If major problems with flexure are not detected until system integration is well under way (drawing a parallel with NIRI, T-ReCS, and other Gemini instruments), the integration and testing phase could be drawn out significantly longer than currently planned.
The following goals for this January 2002 QR that were met are (some of these are from previous QR’s):
·
Complete OIWFS components integration onto the OIWFS bench
· Complete lens delivery and acceptance testing
· Complete fabrication of all mechanisms
·
Complete fabrication of the Bulkhead Assembly
·
Receive all optics
·
Complete and deliver the Acceptance Test Plan
The following goals from before the October 2001 QR that were not met are (goals have been combined for clarity):
·
Complete 3D design of all fixed assemblies. All but the
radiation shields and the thermal distribution system have 3D design complete,
with the rest expected to be complete by the next QR.
·
Complete 2D design of all fixed assemblies. This should be
complete by the next QR.
· Complete dewar to electronics thermal enclosure cabling fabrication. The design is complete, and fabrication is at a lower priority than other tasks. This should be complete by the next QR.
· Complete fabrication of most dewar components (radiation shields and shells but not mounting trusses or cryo head hardware). Radiation shield design was delayed by analysis work done on other parts. This is now on the Critical Path, and will be completed by the next QR.
· Complete 75% of mechanism and optical subassembly testing. Mechanism testing was delayed by several causes: (a) delays in receipt of parts and in subsequent assembly kitting, (b) rework often was not scheduled properly, or took longer than expected, and (c) delays in cleaning the mechanisms, due to overload of the person doing the cleaning and the fact that this one person was not assigned full time to the project. A technician from another project has been assigned to help, and the ETS Manager has made this task the top priority of both people doing the cleaning, but it is not clear that this will be adequate, given the magnitude of the task.
· Plans for documentation. The Project Manager still has not addressed the overall documentation approach, which is scheduled in the future. The USGP recommends that this important set of tasks not be overlooked, as they can consume valuable skilled resources near the end of the project when there is considerable pressure to release such resources to other projects prematurely.
The following goals from the October 2001 QR that were not met are:
· Complete 3D design of all fixed assemblies
· Complete 2D design of all fixed assemblies
· Complete fabrication of all mechanisms
· Complete mechanical fabrication, except for:
o rework items
o shipping container
o items associated with flexure testing
· Complete mechanism and optical subassembly testing
· Complete dewar to electronics thermal enclosure cabling fabrication
· Complete electronics fabrication and checkout, except for:
o some cables may remain to be fabricated
o some rework items identified in system integration may remain
· Complete testing of the Components Controller software with the electronics
· Complete and deliver the Change Order for delivery of GNIRS to Chile
· Complete and deliver the Change Order revision for the Differential Pressure Switch
· Complete and deliver manual outlines
By the next review, nominally scheduled for April 2002, the Project Manager plans to:
· Complete mechanical design
· Complete mechanical fabrication
o Except for flexure rig and shipping container
o Rework will be tracked as integration
· Complete electronics fabrication (rework tracked as integration)
· Complete electronics checkout
· Complete Component Controller software (EPICS software will require further work)
· Complete installation of the science detector into the OIWFS and close out all OIWFS integration items
· Complete manual outlines
· Start manual drafts
In addition to these items, the USGP would add the following for the next QR:
· Completing mechanism cleaning
· Assemble all cleaned mechanisms
· Completing mechanism testing, both warm and cold
· Complete radiation shield design
· Complete radiation shield fabrication
· Complete cleaning of all parts
· Complete and deliver the Change Order for delivery of GNIRS to Chile
· Complete and deliver the Change Order revision for the Differential Pressure Switch
The project is 86% complete from the Restart Review to the completion of the Pre-Ship Acceptance Test, now scheduled for late October 2002.
3.3
Project Problems and Concerns
At
the previous QR, no specific problems were identified as concerns. However, the
following were identified as concerns from previous QR’s and remained so at
the October QR:
At the January QR, the Project Manager listed the following problems and concerns:
· Schedule delays of 2 months, caused by:
o Radiation shield design took longer than expected
o Mechanism rework required to pass flexure tests and fit checks
o Focus mechanism design/fab/assembly took longer than expected
· Radiation shield fabrication will extend into February
· Documentation (Manuals)
o Maintenance manual started; procedures documented as performed
o Delayed by focus on mechanism testing and radiation shields
· OIWFS prism installation
o OIWFS is complete except for installing detector
o An opportunity exists before bench integration during which the OIWFS prism, if it can be delivered by Gemini, may be installed (per Gemini direction, it is unlikely the prism will be received in time, and the team is to proceed without the prism)
· IFU
o Proceeding with mass models
o There is a chance for integration if it arrives in February
As noted above, the WPM believes that, despite the current “on-schedule” status depicted by the latest MS Project schedule update on the recently revised schedule, the project is now 4 months behind schedule in a way that cannot be recovered, and that this will result in late delivery of the instrument by that amount. This conclusion is supported by the fact that contingency in the schedule is reduced to 6 weeks, which for the dynamic, fluid activity that is system integration, is uncomfortably small, given the experience of other Gemini instruments. The USGP recommends that the Project Manager closely monitor the integration phase because it will require the constant attention, involvement, and vigilance of the Project Manager on a daily basis to keep it on track and moving forward at a reasonable pace. Early recognition of problems and willingness to take action will be critical to success during this phase of the project.
During the QR presentation, the Project Manager admitted several times that the current schedule is “aggressive”, as he put it. Therefore, the WPM recommends that the Project Manager review the schedule from the standpoint of what is most likely to occur based on the experience of other Gemini instrument teams, identify possible corrective actions to mitigate problems, and put into place contingency plans to minimize the impact of possible problems. The goal of such an exercise is to move problems from the category of being “unanticipated” to being “unscheduled, but manageable”.
3.4 Project Schedule
The
summary-level project schedule is available on the GNIRS Web site (a copy is
attached to this report). An analysis of the schedule performance of each major
engineering discipline appears below. In past phases of the project, the
Critical Path was deliberately designed so that no single mechanism could delay
the instrument until System Integration. Instead, it included various steps in
most of the mechanisms. Now that the project is entering the System Integration
phase, this no longer applies, and the Critical Path is occupied by a limited
number of sequential tasks performed by a very limited number of people,
increasing the need for the Project Manager’s close scrutiny and active
involvement in problem identification and solution.
3.5 Project Milestones, Cost, and Manpower Charts
A
summary-level Microsoft Project schedule is attached as an appendix. This
reporting category is not repeated for each work area below, since all work
areas are represented in the project schedule and manpower charts. The manpower
charts were presented in the handouts and will not be repeated in this report,
except at a summary level.
3.6
Project Budget and Expenditures to Date
The
estimated cost (from January 1999 forward) increased significantly (+$276k) from
the October QR value of almost $4.1 million to just below $4.4 million, the
latter value being above the original estimate in January 1999 for the first
time since the Restart Review.
The
cost of the entire project is now estimated to be $6.75M, including the $2.4M
spent between the project start in October, 1995 and December 31, 1998. As of
the end of January 2002, the project had spent a total of $6,172,897 against a
planned value of $6,178,371 yielding an underrun of $5,574. Overruns in labor
are nearly offset by underruns in capital equipment in the re-planned budget
that flows from the re-phased schedule. Note that the Project Manager is
forecasting a substantial overrun in capital, the budget for which includes
contract labor for drafting staff that had to be retained longer than expected
due to delays in designing and drafting various assemblies over the life of the
project.
3.7
Organization
The
project appears to be staffed with a sufficient number of competent staff. As
mentioned in the previous QR report, some of the instrument makers have been
used for mechanism assembly and fit checks, so more parts than originally
planned had to be sent outside for fabrication, contributing to the forecast
overrun in capital costs. Due to delays in completing the design of the
radiation shields, the Project Manager was forced to recall Ed Hileman to the
project until the active radiation shield is designed.
Furthermore,
each key engineering position continues to be only one deep, so when a person
leaves the project, no immediate replacement is usually available to fill the
gap. Until the mechanical design is complete, loss of a mechanical engineer
would ensure a delay in the delivery date, perhaps of several months.
4.
Project Management
4.1
Project Management Overview and Key Accomplishments
The
Project Manager continues to exert management control over the project. Since
the previous QR, the Project Manager has been able to transition the project
from being principally one of fabrication to beginning the task of integration
and testing.
4.2 Project Management Status and Plans
The
project continues to be more or less effectively managed. The fact that the
projected delivery date and Estimated Cost At Completion have recently increased
substantially after not changing significantly for almost three years since the
current Project Manager was assigned to the project reflects a series of
problems that have eluded the normally careful scrutiny of the Project Manager.
At
the QR, the Project Manager did not voice any specific plans in the Project
Management area for the coming quarter. USGP recommends increased diligence in
overseeing the critical activities of radiation shield design, parts cleaning,
and mechanism testing to determine when these activities are deviating from the
schedule, and alerting both the ETS Manager and USGP when deviations occur, so
that assistance in solving the problem can be provided.
4.3
Project Management Problems and Concerns
As
mentioned previously, in hindsight, perhaps the Project Manager should have
taken a more pro-active role in preventing the loss of the first active shield
design effort by organizing more cross-checking of early designs by the two
engineers. Another measure, again in hindsight, to assist with determining the
true status of the cleaning and the readiness of a mechanism for testing would
be to post parts lists (not schedules or plans) for check-off when individual
parts are cleaned. Objective truth of the status of each mechanism posted for
all to see would eliminate much of the apparent finger-pointing that seems to
characterize the current multi-group effort in this area.
As
at the previous QR, the major issue now facing the Project Manager is keeping
the system integration effort on track. This will require:
The
USGP once again reminds the Project Manager of the huge documentation task that
lies ahead, and of the resources and time required to address this task.
Although some personnel have been assigned to begin writing manuals, the
enormity of the undertaking should not be underestimated. The USGP recommends
that the Project Manager direct a fair portion of his energy and time to
reviewing this task now and determining whether the plan now in place is
adequate and fits well with the current schedule and staffing plan.
4.4
Project Management Schedule
The
Project Manager usually delivers reports on schedule and meets his other
schedule obligations. Project Management is a level of effort activity that is
80% complete.
4.5
Project Management Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
4.6
Project Management Organization
The
GNIRS Project Management organization consists of Neil Gaughan (Project
Manager), Dan Eklund (assigned half time as Project Assistant), and Melissa
Bowersock (Administrative Assistant to the Project Manager).
5.
Systems Engineering
Systems
engineering is complete. All further systems engineering work is in the area of
optical alignment, subsystem integration, system integration, and testing.
6.
Optics Design
The
optics design is complete. All further optical work is in the area of
procurement, installation, alignment, and integration.
7.
Optics Fabrication
All optics fabrication is being performed by outside contractors.
This
means all GNIRS instrument optics are now in hand and ready for installation. As
a result of adding the Gemini telescope simulator optics for the NOAO flexure
rig facility to the GNIRS optical fabrication work plan, optics procurement now
stands at 90% complete.
8.
Mechanical Design
8.1
Mechanical Design Overview and Key Accomplishments
The
only remaining mechanical design activities are the radiation shields and the
shipping container. The latter is not on the Critical Path at this time.
8.2
Mechanical Design Status and Plans
Mechanical
design and fabrication (which are reported together) are 94% complete overall
with benches 96% complete, mechanisms 97%, and fixed assemblies 84%. The current
status (as of the QR date) of the design of fixed assemblies is that the passive
shield 3D design was complete and had begun 2D design, and the active shield 3D
design was expected to be complete in a matter of a few days.
Plans for the next QR are to have all 3D and 2D designs complete. The major pacing item on the Critical Path for the entire project is the design of the radiation shields.
8.3
Mechanical Design Problems and Concerns
The
primary concern is completing the design of the radiation shields as quickly as
possible, as this item is now on the Critical Path, and has already delayed the
project several months.
8.4
Mechanical Design Schedule
The
fixed assemblies are about 5 months behind the schedule from last summer, and
required reworking the schedule for the second time in two QR’s. Once this
item is completed, the major work of design will have been completed, and the
only remaining item will be the shipping container, which is not expected to be
either complex or a pacing item. However, care must be taken to ensure that the
shipping container does not follow the same path as the radiation shields, which
were thought at the time to be simple and straightforward.
8.5
Mechanical Design Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
8.6
Mechanical Design Organization
The
GNIRS mechanical engineering group consists of Ed Hileman (benches and fixed
assemblies) and Gary Muller (mechanisms and engineering management systems). The
mechanical design group consists of John Andrew (lead), Dave Rosin, and Eric
Downey. Dale Circle left the project at the end of 2001.
9.
Mechanical Fabrication
9.1
Mechanical Fabrication Overview and Key Accomplishments
Fabrication
is complete on all mechanisms. A major accomplishment during this quarter was
the delivery of the Bulkhead Assembly. Of the fixed assemblies, all had been
designed and fabricated except the radiation shields and the shipping container.
9.2
Mechanical Fabrication Status and Plans
Fabrication status is not reported separately from design (see above). By the next QR, all mechanical fabrication should be complete, except for:
· items associated with flexure testing,
· the shipping container, and
· some rework items identified during integration.
9.3
Mechanical Fabrication Problems and Concerns
In
the previous QR report, the USGP raised the following concerns:
Since
the Bulkhead Assembly was delivered, apparently in working order, this is no
longer a concern. As noted above, radiation shields are now the pacing item in
the project, and remain the chief concern of all involved.
9.4
Mechanical Fabrication Schedule
Most
of the parts fabrication delays reported in the previous QR are no longer of
concern, with the exception of the radiation shields.
9.5
Mechanical Fabrication Budget and Expenditures to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
9.6
Mechanical Fabrication Organization
Mechanical parts fabrication is performed by a combination of outside machine shops and the NOAO instrument shop. NOAO instrument makers assemble and check out each subassembly. The NOAO instrument makers assigned to GNIRS include John Stein, Randy Bennett, Lou Lederer, and Ron Harris.
10.
Electronics Design
Electronics
design is complete.
11.
Electronics Fabrication
11.1 Electronics Fabrication Overview and Key
Accomplishments
The
Instrument Controller was demonstrated at the QR to work with the EPICS software
and the “flight” filter wheel and slit slide assembly.
11.2 Electronics Fabrication Status and Plans
The overall electronics effort for design and fabrication stands at 71% complete. The only remaining electronics fabrication work is:
· fabricating the Thermal Enclosure to Dewar cables
· harnessing the cold mechanisms as they become available
· harnessing the cold benches as they become available
· harnessing the Bulkhead Assembly
· fabricating the dewar warm-up controller
· supporting software testing
By the next QR, fabrication and harnessing will be complete, and software testing will have begun.
11.3 Electronics Fabrication Problems and Concerns
None.
11.4 Electronics Fabrication Schedule
Electronics
fabrication is on schedule. At the previous QR, it was reported that the
software test fixture was behind schedule, but since the Instrument Components
Controller is now wired and checked out, it is available for software checkout
so the software test fixture is no longer needed.
11.5 Electronics Fabrication Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
11.6
Electronics Fabrication Organization
The
GNIRS electrical engineer is Jerry Penegor, assisted by electronics technician
Ron George.
12.
Software Design
The
software design is complete.
13.
Software Fabrication
13.1
Software Fabrication Overview and Key Accomplishments
At
the QR, the software engineer, Peter Ruckle, demonstrated engineering screens
built using the EPICS-based dm tool controlling the deliverable
Instrument Controller electronics in the Thermal Enclosure controlling a filter
wheel and the slit slide assembly that had been cleaned and were ready for
installation on the optical bench. All engineering screens have been built.
13.2
Software Fabrication Status and Plans
Overall,
the software is 86% complete and is about one month behind schedule according to
the GNIRS Project Summary Schedule. The coding for the Lab Support software are
complete. The EPICS code is 99% complete, and the Component Controller software
is 85% complete.
13.3
Software Fabrication Problems and Concerns
None
13.4
Software Fabrication Schedule
Although
the software is slightly behind schedule, this is not on the Critical Path at
the moment, and it appears that overall, software will not be the pacing item on
this project leading to the Pre-ship Acceptance Test. Much of the remaining work
is software testing. This includes testing of the OCS and DHS interfaces using
the tools supplied by Gemini.
13.5 Software Fabrication Budget and Expenditures to
Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
13.6
Software Fabrication Organization
The
GNIRS software engineer is Peter Ruckle. Richard Wolff, who previously led the
GNIRS software effort, retired from NOAO on October 31.
14.
Subsystem Integration
14.1
Subsystem Integration Overview and Key Accomplishments
Due to delays in the Bulkhead Assembly and the radiation shields, and a late start in beginning mechanism testing (due to their not being available as early as originally planned), subsystem integration was re-planned as part of the overall integration phase re-planning. This effort is now under way, with warm and cold testing complete for the OIWFS bench, and warm testing done in the shop for several other mechanisms.
14.2 Subsystem Integration Status and Plans
Parts cleaning has taken longer than anticipated, and other delays in testing cleaned and assembled mechanisms have required a re-phasing of the entire project. Subsystem integration of the OIWFS bench and detector mount are complete. Warm shop testing for the pre-slit and post-slit bench subassemblies is complete.
Electronics
and software checkout have proceeded as far as possible until more hardware is
available for testing.
The
Team plans to have all subsystem integration completed by the next QR.
14.3
Subsystem Integration Problems and Concerns
As mentioned above, delays in mechanism assembly and testing were caused by delays in kitting, rework, and an apparent underestimation in the time required to clean all the parts and an apparent mis-communication between those performing the cleaning and reassembly of mechanisms and those performing mechanism testing. The USGP calls upon engineering management to ensure that parts cleaning progresses at the fastest rate possible, and that those involved in mechanism testing and the Project Manager are informed when a mechanism is cleaned, assembled, and ready for testing.
14.4
Subsystem Integration Schedule
See above. Alignment and integration were due to begin April 1 according to the schedule presented at the previous QR, but due to the delays mentioned above, these activities are several months late, and have been rescheduled. They are now due to begin in late April.
14.5
Subsystem Integration Budget and Expenditures
to Date
The GNIRS Statement of Work does not require this WBS element to be reported separately to the USGP.
14.6
Subsystem Integration Organization
Bill Ditsler and Ken Don clean parts and reassemble mechanisms. Dick Joyce and Jay Elias perform mechanism testing, optical alignment, and integration.
15.
System Integration
15.1
System Integration Overview and Key Accomplishments
System
integration was scheduled to begin in October. However, due to delays in
designing the radiation shields and in mechanism testing, this activity was
rescheduled.
15.2 System Integration Status and Plans
System
integration will begin with opto-mechanical integration, starting with the
benches in April.
15.3
System Integration Problems and Concerns
Other
Gemini instruments have endured protracted integration periods that have delayed
instrument delivery, despite mechanism cold testing and other precautions.
Although the GNIRS team has endeavored to avoid the mistakes of other teams to
date, and has scheduled several months for system integration, the compacted
schedule and the virtual elimination of schedule contingency have made it
unlikely that the instrument will be delivered on schedule. It remains to be
seen if the GNIRS team will fare better than others in terms of problems they
encounter during the system integration and test and checkout phases of the
project. A well-planned and coordinated approach to system integration is
essential to maintaining control of the schedule.
15.4
System Integration Schedule
The
recently-revised schedule shows system integration beginning about the time of
the next QR.
15.5
System Integration Budget and Expenditures to Date
The GNIRS Statement of Work does not require this WBS element to be reported separately to the USGP.
15.6
System Integration Organization
Various engineers and technicians perform system integration, depending on the subsystem being integrated into the instrument. The primary personnel performing system integration are Jay Elias and Dick Joyce.
16.
Test and Checkout
No test and checkout tasks were scheduled to begin before the Quarterly Review. The previous QR report contained a note indicating it was Gemini’s responsibility to deliver a flexure rig in time for NOAO to install it by the GNIRS need date of April, 2002. Due to the rescheduling of integration, the need date is now May, which is consistent with both the contract that Gemini awarded and the availability of the new facility NOAO has planned.
17.
Documentation and Training
17.1
Documentation and Training Overview and Key Accomplishments
The Team delivered an updated draft of an Acceptance Test Plan responding to comments from Gemini and the USGP.
17.2 Documentation and Training Status and Plans
Documentation became seriously behind schedule, and was rescheduled as a result, when scientists and engineers would be available to assist in its preparation.
17.3
Documentation and Training Problems and Concerns
A concern was noted in the previous QR report regarding the Acceptance Test Plan (ATP), which has been addressed. Although work on manuals has begun, it has been the experience of USGP that other Gemini instrument teams have found it easier to let this important area lag while trying to finish the instrument. In particular, USGP notes the lack of a senior individual leading the documentation effort with the ability to command the team and to obtain the cooperation of its members to meet writing deadlines and to generate the materials needed to produce the manuals. The WPM predicts that this lack of leadership will make itself evident in the months to come as the documentation effort slips its milestones.
Besides the ATP, the team is responsible for producing two Change Orders (change of venue to Chile/Commissioning, and the Differential Pressure Switch). These Change Orders have been pending for the better part of a year, and need to be completed to permit the Team to focus on the job of completing the instrument.
17.4
Documentation and Training Schedule
The documentation task completion status is:
· electronics -- 88% complete
· test plans – 99%
· manuals – 0%
· as-built fabrication drawings – 0%.
Although
the percent complete claimed for as-built fabrication drawings is 0%, the
process for drawing update and release, and parts fabrication is to update the
drawings first before parts are fabricated, instead of redlining drawings on the
instrument makers desk. This should speed up the task of generating and
delivering as-built fabrication drawings.
17.5
Documentation and Training Budget and Expenditures
to Date
The
GNIRS Statement of Work does not require this WBS element to be reported
separately to the USGP.
17.6
Documentation and Training Organization
For
electronics documentation, the responsible parties are the GNIRS electrical
engineer, Jerry Penegor, assisted by electronics technician Ron George. Jay
Elias is writing the Test Plans. Manual outlines are being prepared by Jay
Elias, Peter Ruckle, and Al Davis.
18.
Other Activities
No
tasks for other activities were scheduled to begin before the Quarterly Review.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information
NOAO Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360