
GNIRS
PROGRESS REPORT
August 25 –
September 21, 2001
Accomplishments / Status
Summary: 80% of the work from the Restart Review to delivery has been completed.
The main focus of this report period has been completing fabrication of mechanisms, mechanical design of remaining assemblies such as radiation shields, and vendor fabrication of the Bulkhead Assembly and Dewar Shells. Except for the Focus Assembly, all mechanisms have completed fabrication. The Slit/Decker slide is in rework. All bench-mechanism fit checks were completed. The Pre-Slit, Post-Slit and OIWFS benches are being painted. Mechanism testing is underway.
An update to the Envelope Waiver has been submitted to Gemini. The new request includes hardware that will extend outside of the allowed envelope in two locations.
Rework of the OIWFS bench is complete. Work on the WFS has been hampered by missing or late delivery of components and incomplete ICD details, and will continue on a non-interference basis with mechanism assembly and testing.
All optics except two replica mirrors, one flat mirror and the final camera lens have been received. The final camera lens and flat mirror were each damaged during coating. The mirror is being recoated and the camera lens is being remade. The defective camera lens will be used in initial camera set up and replaced when the final lens is received. The replica mirrors are again delayed due to a procurement/vendor mix up.
Design modifications to the Bulkhead Assembly and Rear Dewar Shell were required to insure the proper location of CG. In addition, we have contracted the vendor to do vacuum/leak testing of the entire assembly at his site.
To protect the fall 2002 delivery date we have modified the schedule to parallel the following efforts:
Following these activities are the assembly of the benches, radiation shields and Bulkhead Assembly, and then the integration testing as already planned. Flexure testing is now scheduled for mid-April. The last camera lens should be received in March 2002, and we plan to open the dewar, remove the Post-slit Bench assembly and replace the lens. This would be a good time to install the IFU and OIWFS prism as well.
A Change Order modification addressing Testing, Training, and Commissioning in Chile is in process.
Next Milestone: The next major project milestone is the completion of Bulkhead Assembly and Dewar Shell fabrication and leak test, now due in November.
Earned Value:
|
|
February |
March |
April |
May |
June |
July |
August |
September |
|
BCWS |
$2,049,349 |
$2,278,192 |
$2,565,371 |
$2,732,977 |
$2,929,722 |
$2,976,073 |
$3,030,916 |
$3,085,811 |
|
BCWP |
$1,543,495 |
$1,694,322 |
$1,804.951 |
$1,912,351 |
$2,119,911 |
$2,182,434 |
$2,357,289 |
$2,526,319 |
|
ACWP |
$1,739,549 |
$1,839,301 |
$1,915,889 |
$2,031,750 |
$2,343,546 |
$2,392,603 |
$2,603,604 |
$2,762,963 |
|
SPI |
0.75 |
0.74 |
0.70 |
0.70 |
0.72 |
0.73 |
0.78 |
0.82 |
|
CPI |
0.89 |
0.92 |
0.94 |
0.94 |
0.90 |
0.91 |
0.91 |
0.91 |
This table reflects capital and labor charges to the project as of August 31, 2001. We have spent $1,123K in capital so far, for a total program expenditure of $3,174K to date.
Project Management: (71%
complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The plan reflects changes due to the slip in delivery of the Bulkhead Assembly and Dewar Shells, and integration of the benches into the top assembly. The current scheduled delivery date of the GNIRS instrument is September 25, 2002. There is a total of 3 weeks contingency left in the schedule.
Systems Engineering: (100% of planned work)
The main focus has been support of design updates, mechanism assembly and warm test, procurement, preparation of the Test Plan for Acceptance Testing, Delivery to Chile, Training and Commissioning, and work on the new Envelope Waiver request.
Mechanical Design, Fabrication, Assembly and Test: (87% overall)
The major activity in this work package has been design modifications to the Bulkhead and Dewar Shell assemblies, Post-Slit, Pre-Slit and OIWFS Benches, 3D and 2D design of fixed assemblies and fabrication. A new interface plate to collect all input-output connections to and from the wrap-up has been designed. This is included in the Envelope Waiver request.
Mechanisms: (89% complete overall). The Focus Mechanism is the only outstanding assembly still in fabrication. All Design is complete and most mechanisms are essentially ready for test.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
91% |
91% |
91% |
Final
Fab |
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
59% |
60% |
67% |
Fab |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
99% |
99% |
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
75% |
76% |
93% |
(waiting
for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
90% |
93% |
93% |
Rework,
Assembly/test |
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
83% |
95% |
95% |
Ready
for test |
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
86% |
89% |
97% |
Ready
for test |
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
85% |
92% |
98% |
Ready
for test |
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
- |
- |
- |
Complete |
Benches: (95% complete overall). All modifications have been completed and the benches sent for final finish coating. The Collimator has a few parts still in fabrication, and is nearly ready for assembly.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Sept |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
88% |
94% |
99% |
Paint |
|
OIWFS |
67% |
67% |
79% |
- |
86% |
87% |
89% |
99% |
Paint |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
64% |
77% |
95% |
Fab
|
|
Pre-Slit
|
44%
|
62%
|
70%
|
81% |
83%
|
87% |
91% |
99% |
Paint |
Fixed Assemblies: (62% complete overall). The Radiation Shields are the pacing items in fixed assemblies.
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
79% |
79% |
97% |
Waiting
for wiring |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
49% |
51% |
59% |
Fab |
|
Thermal
Distribution Assembly |
|
|
|
|
|
|
12% |
26% |
3D Design |
|
Bulkhead
Rad Shield |
|
|
|
|
|
|
1% |
5% |
3D Design |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
89% |
91% |
91% |
Fab |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
85% |
95% |
100% |
Complete |
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
64% |
74% |
75% |
Fab |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
10% |
10% |
10% |
3D
design |
|
Rear
Rad Shield |
|
|
|
|
|
|
18% |
18% |
3D design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
38% |
66% |
70% |
Fab |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
- |
57% |
61% |
Fab |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
- |
- |
14% |
77% |
Fab |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
8% |
15% |
57% |
Fab |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
47% |
47% |
47% |
2D
drafting |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53
% |
53% |
58% |
70% |
Fab |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
68% |
100% |
100% |
Complete |
|
Ballast
Weights |
|
|
|
|
|
|
|
75% |
Fab |
Electronics: (86% complete overall) The Instrument Controller design work is essentially complete and the main activity is fabrication. The OIWFS electronic components have been received and parts installed in the Thermal Enclosure. The Leach controller checkout is in process.
|
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
66% |
- |
90% |
86% |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
100%
|
- |
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
100%
|
- |
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
90%
|
98% |
98% |
98% |
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
63%
|
98% |
98% |
98% |
Assembly
|
|
|
IfA
Electronics Box |
- |
- |
- |
- |
- |
- |
30% |
30% |
In
check out |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
94% |
98% |
98% |
98% |
Assembly/wiring
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
23% |
23% |
23% |
23% |
|
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
37% |
37% |
37% |
37% |
|
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
95% |
- |
95% |
95% |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
80%
|
80% |
80% |
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Conn/Cabling |
- |
72%
|
72%
|
72% |
96% |
- |
96% |
96% |
On
Hold |
|
Documentation
|
|
50%
|
50%
|
50% |
85% |
- |
95% |
95% |
|
|
Software Development: (85% complete overall).
The areas in work include testing software with the electronics crates. EPICS software is far ahead of schedule. Resources assigned to the software task are also working on the Gemini Array Controller.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
- |
91% |
94% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
- |
82% |
82% |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
- |
50% |
75% |
Procurement: (74% complete overall).
The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Sept |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
- |
89% |
86% |
Only POM and Acq mirror remain |
|
RMI optics |
100% |
-
|
-
|
- |
- |
- |
- |
- |
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
- |
99% |
99% |
Fab of replica mirrors |
|
Pupil Viewer |
100% |
-
|
-
|
- |
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
- |
75% |
90% |
Final
SRC lens failed. Replacement
in Fab |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
- |
100% |
100% |
Complete |
|
Prisms |
- |
13% |
13% |
23% |
74% |
- |
95% |
100% |
Complete |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
- |
95% |
100% |
Complete |
Problems / Solutions
Some schedule time was lost due to required revisions to the Bulkhead and Dewar Shell assemblies. This caused a 1-month slip in delivery of these items from the vendor. In order to keep our fall 2002 delivery schedule, we have re-ordered some of the tasks in the initial parts of the instrument Integration sequence. This is discussed in some detail in the Accomplishments/Status portion of this report.
We have submitted to Gemini an updated Envelope Waiver Request. This waiver request includes the following items that extend beyond the allowed envelope:
o Interface plate for connecting Helium, power, signal, air, etc to/from the GNIRS instrument
o Helium Manifold on side of Bulkhead Assembly
These intrusions are minor and we are proceeding while waiting for Gemini concurrence.
Key
Personnel
Ed
Hileman, SR. Mechanical Engineer, and Eric Downey, Design Draftsman have been
extended on the project through November 1st.
Dale Circle, Sr. Designer, has been extended until December 31st.
All were scheduled to leave the project on October 1st.
In
view of the design effort winding down and fabrication being nearly complete, it
seems appropriate to recognize the technical staff for their hard work and
commitment to the GNIRS project. It
should be noted that all the individuals on the project are doing outstanding
work, and are considered by the project manager to be “Top People” in their
respective fields. This project has
had the benefit of being staffed properly to do the work and enjoyed the work
priority at NOAO that enabled work to be done on schedule without interference
from other activities. There are no
“average” people working on the project.
The
instrument design has been based on the optical design done by Ming Liang.
Ming has provided continual input and worked very effectively with the
mechanical engineers to ensure that the opto-mechanical hardware and optical
design converge.
The
Opto-Mechanical team (Ed Hileman, John Andrew, David Rosin, Eric Downey and Dale
Circle, under the leadership of Gary Muller) has done an outstanding job of
getting the work done, and for the most part done right the first time.
Their proficiency in SolidWorks, learned in the midst of the design
effort, has been a key item in the success of the design effort.
The
Instrument Shop team (Ron Harris, Randy Bennett, and Lou Lederer under the
guidance of John Stein assisted by Roger Repp) has done an outstanding job of
fabrication and assembly of the most difficult parts of the instrument.
Roger has also been an invaluable help in assisting Al Davis by
participating in make-buy decisions.
Our
procurement, handled exclusively by Al Davis, has been done so professionally
that we have had little or no anomalies develop due to vendor contract or vendor
fabrication. This includes
mechanical, optical and electrical fabrication, development and screening of
vendors and parts and inventory control of fabricated parts and components.
Optics
inspection, done mostly by Al Camacho with some assistance by Heidi Yarborough,
has been exceptionally professional and thorough.
Al has been responsive to the needs of the project by being available to
travel to do on-site inspections on relatively short notice.
Bill
Ditsler has handled all parts cleaning and preparation.
His work is in some ways just getting underway, but he has done his usual
outstanding job in support of the fabrication and test effort.
Bill will ensure that every component integrated into the instrument is
indeed ready to do so.
Jerry
Penegor and Ron George have built and tested all the electronics used in the
instrument, including updating the Array Controller.
Their work has been thorough, complete and professional.
Our
software effort, under the guidance of Richard Wolff, has been outstanding.
He has ensured that software has not been a problem on GNIRS, and the
effort has always been ahead of schedule. Peter
Ruckle, initially handling all EPICS level code and all work with the Array
Controller, has now moved into prime responsibility for GNIRS software.
The
GNIRS Scientists (Jay Elias, PS, and Dick Joyce, PSS) primarily working systems
and hardware issues, have done a great systems engineering job by producing
specifications, evaluating performance, controlling interfaces, and testing
assemblies. Both Dick and Jay have
done an outstanding job. Brook
Gregory has been a continual assist, working both here in Tucson and from CTIO
in Chile. His contribution has been
invaluable.
As
project manager I have had invaluable assistance from Mark Trueblood, Dan Eklund
and my Administrative Assistant Melissa Bowersock.
I could not have performed my function without their assistance and
advice. Melissa has also done an
outstanding job managing the GNIRS web site.
Our
summer intern program has ended, and the three interns of the four assigned to
GNIRS have returned to studies at UA. Each
made significant contributions, and our thanks go to Shona Kroto for her work on
the opto-mechanical assembly kitting and parts control and organization, Eric
Mountford for his work on the OIWFS parts inventory and test set up, and Alex
Lowe for his work in designing a bench temperature controller.
John Pina will be remaining on the program to assist with test and
integration.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360