Progress Report

July 28-August 22, 2000

 

 

            Accomplishments / Status

 

Summary:  Overall, 30% of the work from the Restart Review to delivery has been completed. The primary focus of this reporting period has been 1) solid modeling design and deflection analysis of the Post-Slit, Pre-Slit, and OIWFS Optical Benches, 2) assembling the fabrication bid package for the benches, 3) modeling of the Slit/Decker mechanisms, 4) 2D design of the Filter Wheel mechanism, 5) fabrication of the Environmental Cover mechanism and 6) fabrication of the motor drive assembly.  In addition, the fourth Quarterly Review of the project was held on August 15th.

 

Next Milestone: The next major project milestone is the release of the OIWFS optical bench for fabrication in early September 2000.

 

Earned Value:     

 

                                BCWS    $ 1,552,209                                SPI        0.55

                                BCWP    $    850,144                                CPI        0.86

                                ACWP    $    986,250

 

Project Management: (36% completed) The project plan has again been revised to reflect changes in the work flow on benches and mechanisms and can be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning.  The scheduled delivery date of the completed GNIRS instrument has not changed.

 

A quarterly review of the project was held on August 15th.  Presentation materials for this review are posted on the GNIRS web site at http://www.noao.edu/ets/gnirs/ under Management, Reviews, and Quarterly Review Presentation.

 

A document answering Pre-Fabrication Review committee concerns and comments was prepared and sent to Gemini.  This can be viewed at http://www.noao.edu/ets/gnirs/ under Management, Reviews, and Pre-Fabrication Review Response.

 

Systems Engineering: (99%) The activities in work included 1) structural analysis and 2) linear prototype.   The Project Scientist with part time support from a staff support scientist is assigned to this task.

 

The structural analysis was completed on August 15. The results have been passed to the optical engineer for calculation of beam position on the detector as a function of bench deflection. These results will be available in the third week of August.

 

The Linear Mechanism Prototype has completed test. This is the final mechanism prototype that will be done on the project. It was determined that the bearing prototype previously planned was applicable only to the Prism and Grating mechanisms, and that the tapered bearing approach used for the Camera mechanism is applicable to all rotary mechanisms. We have committed all rotary mechanisms to use the tapered bearing approach. 

 

Mechanical Design and Fabrication: (17%) Activities include optical bench solid modeling, slit/decker mechanism design, camera design, filter wheel design, environmental cover fabrication, and motor drive assembly fabrication.

 

Wavefront Sensor Bench, Post-Slit Optical bench and Collimator Mount. The next task for these major bench assemblies is to finish 2D designs for fabrication. We plan to have a vendor under contract to fabricate the OIWFS bench by the first week of September, and the other two benches in fabrication by the end of September. One engineer and one designer are assigned to these tasks.

 

The Slit/Decker mechanism assembly 3D design is 90% complete. One engineer and one designer are assigned to this activity.

 

Camera Mechanism. The short red camera is in drawing check/revision. This is required before sending drawings to fabrication. The short blue camera 2D drafting is 16% complete and is on hold until the 3D design of the long camera is complete. The camera drive spindle hub 2D drafting is 13% complete. One designer is assigned to the camera design tasks.

 

Filter Wheel Assembly mechanism. 2D drafting is waiting to start. One designer is assigned to this task.

 

Environmental Cover Assembly.  Fabrication is 87% complete.

 

The Acquisition Mirror mechanism.  2D drafting is 35% complete.

 

The Motor Drive Assembly is in fabrication.

 

Electronics Design: (10%) Activities in this work package include 1) electrical and mechanical design and construction of a simulator for use in software testing, 2) dewar and mechanism wiring design definition, 3) array interface wiring definition, 4) cold stationing definition and 5) re-planning of the electronics work flow. One engineer and one graduate EE student intern are assigned to this work.

 

The construction of the Mechanism Simulator is complete and ready for use. Work on defining dewar wiring, and ALADDIN array interfacing details and detailed Mechanism wiring is in process.

 

Software Development: (30%) No work has been done on the software this month.  The next step involves software testing using the Mechanism Simulator.  The Components Controller Software is 59% complete, and the System Software is 5% complete.  One software engineer is assigned to this work, assisted by a second engineer on a part time basis.

 

Procurement: (32%) Major activities in this Work Package included optics work at RMI and monitoring vendor fabrication.  One parts procurement and management person is assigned to this task.

 

            Problems / Solutions.

 

An electronics technician will be needed on GNIRS starting in September.

 

            Key Personnel

 

No items

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.

NOAO Intranet Services
NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360