GNIRS
PROGRESS REPORT
July 21–
August 24, 2001
Accomplishments / Status
Summary: Overall, more than 76% of the work from the Restart Review to delivery has been completed.
The main focus of this report period has been completing fabrication of mechanisms, fabrication of major assemblies such as the Bulkhead Assembly and Dewar Shells and the mechanical design of remaining assemblies such as radiation shields. Except for the Focus Assembly, all mechanisms have completed initial fabrication and are in fit check, rework or test. The Pre-Slit and Post-Slit benches have finished fabrication and are due to be painted after fit checks are completed. Mechanism assembly and warm assembly testing is underway, but is proceeding more slowly than expected due to small part fabrication issues in nearly every mechanism that had to be corrected before assembly and warm testing could be effectively started.
The OIWFS components integration and alignment has been delayed due to some components not matching the interfaces given in the ICD, causing rework on the WFS bench. The bench modifications are being done on a low priority basis. Work on the WFS will continue on a non-interference basis with mechanism assembly and testing.
The project remains about 6 weeks behind schedule with respect to start of instrument integration. The fall 2002 delivery date is not impacted.
Next Milestone: The next major project milestone is the completion of the Bulkhead Assembly and Dewar Shells in September.
Earned Value:
|
|
February |
March |
April |
May |
June |
July |
August |
|
BCWS |
$2,049,349 |
$2,278,192 |
$2,565,371 |
$2,732,977 |
$2,929,722 |
$2,976,073 |
$3,030,916 |
|
BCWP |
$1,543,495 |
$1,694,322 |
$1,804.951 |
$1,912,351 |
$2,119,911 |
$2,182,434 |
$2,357,289 |
|
ACWP |
$1,739,549 |
$1,839,301 |
$1,915,889 |
$2,031,750 |
$2,343,546 |
$2,392,603 |
$2,603,604 |
|
SPI |
0.75 |
0.74 |
0.70 |
0.70 |
0.72 |
0.73 |
0.78 |
|
CPI |
0.89 |
0.92 |
0.94 |
0.94 |
0.90 |
0.91 |
0.91 |
Project Management: (65%
complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.
Systems Engineering: (100% of planned work)
The main focus has been support of procurement, mechanism assembly and warm test.
Mechanical Design, Fabrication, Assembly and Test: (82% overall)
The major activity in this work package has been the 3D and 2D design of fixed assemblies and fabrication.
Mechanisms: (89% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
91% |
91% |
Final
Fab |
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
59% |
60% |
Fab |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
99% |
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
75% |
76% |
Fab
(waiting for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
90% |
93% |
Rework,
Assembly/test |
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
83% |
95% |
Assembly/test
|
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
86% |
89% |
Fab/assembly/test |
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
85% |
92% |
Fab/assembly/test |
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
- |
|
Complete |
Benches: (87% complete overall).
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
88% |
94% |
Fab, mods in process |
|
OIWFS Bench |
67% |
67% |
79% |
- |
86% |
87% |
89% |
Bench mods on hold |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
64% |
77% |
Fab
|
|
Pre-Slit
bench |
44%
|
62%
|
70%
|
81% |
83%
|
87% |
91% |
Fab
and assembly |
Fixed Assemblies: (55% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
79% |
79% |
Fab |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
49% |
51% |
Fab |
|
Thermal
Distribution Assembly |
|
|
|
|
|
|
12% |
3D Design |
|
Bulkhead
Rad Shield |
|
|
|
|
|
|
1% |
3D Design |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
89% |
91% |
Fab |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
85% |
95% |
Test |
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
64% |
74% |
Fab |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
10% |
10% |
3D
design |
|
Rear
Rad Shield |
|
|
|
|
|
|
18% |
3D design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
38% |
66% |
Fab |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
- |
57% |
Fab |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
- |
- |
14% |
2D
drafting |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
8% |
15% |
2D
drafting |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
47% |
47% |
2D
drafting |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53
% |
53% |
58% |
Fab |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
68% |
100% |
Complete |
Electronics: (77% complete overall)
The Instrument controller design work is essentially complete and the main activity is fabrication. The OIWFS electronic components are received and work on integrating components into the thermal enclosure has started.
|
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
66% |
- |
90% |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
100%
|
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
100%
|
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
90%
|
98% |
98% |
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
63%
|
98% |
98% |
Anodization
and reassembly |
|
|
IfA
Electronics Box |
- |
- |
- |
- |
- |
- |
30% |
In
check out |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
94% |
98% |
98% |
Assembly/wiring
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
23% |
23% |
23% |
On hold |
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
37% |
37% |
37% |
On hold; Rescheduled to later date |
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
95% |
- |
95% |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
80%
|
80% |
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Conn/Cabling |
- |
72%
|
72%
|
72% |
96% |
- |
96% |
On
Hold |
|
Documentation
|
|
50%
|
50%
|
50% |
85% |
- |
95% |
|
|
Software Development: (68% complete overall).
The areas in work include some testing software with the electronics crates. EPICS software is far ahead of schedule. Resources assigned to the software task are working on the Gemini Array Controller.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
- |
91% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
- |
82% |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
- |
50% |
Procurement: (74% complete overall).
The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
- |
89% |
Only POM and Acq mirror remain |
|
RMI optics |
100% |
-
|
-
|
- |
- |
- |
|
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
- |
99% |
Fab of replica mirrors |
|
Pupil Viewer |
100% |
-
|
-
|
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
- |
75% |
August
completion forcast |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
- |
100% |
Complete |
|
Prisms |
- |
13% |
13% |
23% |
74% |
- |
95% |
Fab |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
- |
95% |
Fab |
Problems / Solutions
Mechanism assembly and warm test is taking longer than anticipated but is being worked vigorously.
Key Personnel
No
changes.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.