
GNIRS
PROGRESS REPORT
June 28– July
20, 2001
Accomplishments / Status
Summary: Overall, more than 71% of the work from the Restart Review to delivery has been completed. This report does not include accurate progress updates in the areas of electronics, software and procurement.
The main focus of this report period has been design of the dewar shells, radiation shields and support structure(s), and completing fabrication of benches and mechanism. All mechanisms are either in or have completed fabrication. The Pre-Slit and Post-Slit benches just finishing fabrication. The Passive Collimator Assembly has been released for fabrication. Mechanism assembly and warm assembly testing has been started. Subsystem integration and testing has begun; integration of subsystems into the instrument will begin in the fall.
The OIWFS components, with the exception of the field lens, have been received from IFA. During receiving inspection of the parts and assemblies, we discovered that some components did not match the interfaces given in the ICD, and this has caused some rework on the WFS bench. This has delayed WFS integration and alignment, as the bench modifications are being done on a low priority basis. The WFS will continue to be integrated on a non-interference basis with mechanism assembly and testing.
The project is consistently under-spending planned labor. This is due mainly to three factors: 1) detail design taking longer than planned, 2) delays in completing fabrication and 3) shared resources with other project efforts. This has all contributed to fewer labor hours charged to the project.
Capital is also behind the spending plan due to the delays in releasing assemblies to fabrication. Spending should catch up to the plan by mid-August. The two pieces of the Bulkhead Assembly have been released and contracted for a combined total of $135K. We have also awarded the contracts for the two dewar shells, which will cost about $50K total. These items will be released for fabrication in late July.
The project remains about 6 weeks behind schedule with respect to start of instrument integration. The fall 2002 delivery date is not impacted.
Next Milestone: The next major project milestone is the completion of mechanism testing in September.
Earned Value:
|
|
February |
March |
April |
May |
June |
July |
|
BCWS |
$2,049,349 |
$2,278,192 |
$2,565,371 |
$2,732,977 |
$2,929,722 |
$2,976,073 |
|
BCWP |
$1,543,495 |
$1,694,322 |
$1,804.951 |
$1,912,351 |
$2,119,911 |
$2,182,434 |
|
ACWP |
$1,739,549 |
$1,839,301 |
$1,915,889 |
$2,031,750 |
$2,343,546 |
$2,392,603 |
|
SPI |
0.75 |
0.74 |
0.70 |
0.70 |
0.72 |
0.73 |
|
CPI |
0.89 |
0.92 |
0.94 |
0.94 |
0.90 |
0.91 |
Project Management: (65% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.
Systems Engineering: (100% of planned work)
The main focus has been OIWFS component assembly inspection, readiness for integration/testing, and support of critical parts procurement and mechanism kitting, assembly and warm test.
Mechanical Design, Fabrication, Assembly and Test: (79% overall)
The major activity in this work package has been the 2D design of the Bulkhead Assembly and its interfacing components, dewar shell design, bench fabrication, and 3D and 2D design of fixed assemblies.
Mechanisms: (87% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
91% |
Final
Fab |
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
59% |
Released
for Fab |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
75% |
Fab
(waiting for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
90% |
Fab
(waiting for mirror) |
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
83% |
Assembly/test
|
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
86% |
Fabrication
(nearly complete) |
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
85% |
Fab
|
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
- |
Complete |
Benches: (84% complete overall).
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
88% |
Fab |
|
OIWFS Bench |
67% |
67% |
79% |
- |
86% |
87% |
Bench mods in process |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
64% |
All
parts in Fab |
|
Pre-Slit
bench |
44%
|
62%
|
70%
|
81% |
83%
|
87% |
Fab
and assembly |
Fixed Assemblies: (49% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
79% |
Detail
check |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
49% |
Fab |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
89% |
2D
drafting |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
85% |
Fab
|
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
64% |
Fab |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
10% |
3D
design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
38% |
2D
drafting |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
- |
Released
to fab |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
31%
|
31% |
2D
drafting |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
8% |
2D
drafting |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
47% |
2D
drafting |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53
% |
53% |
2D
drafting |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
68% |
Fab
(welding) |
Electronics: (77% complete overall)
The Instrument controller design work is essentially complete and the main activity is fabrication. The Gemini approved modification to the Power Supply Rack of the GNIRS Array Controller is in process. The OIWFS electronic components are received and work on integrating components into the thermal enclosure has started.
|
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
66% |
- |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
100%
|
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
100%
|
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
90%
|
98% |
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
63%
|
98% |
Anodization
and reassembly |
|
|
IfA
Electronics Box |
- |
- |
- |
- |
- |
- |
Received
from IFA |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
94% |
98% |
Assembly/wiring
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
23% |
23% |
On hold |
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
37% |
37% |
On hold; Rescheduled to later date |
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
95% |
- |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
80%
|
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Conn/Cabling |
- |
72%
|
72%
|
72% |
96% |
- |
Fab
|
|
Documentation
|
|
50%
|
50%
|
50% |
85% |
- |
|
|
Software Development: (68% complete overall – no new update).
The areas in work include some testing software with the electronics crates. EPICS software is far ahead of schedule.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
- |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
- |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
- |
Procurement: (67% complete overall – no new update).
The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
- |
Only POM and Acq mirror remain |
|
RMI optics |
100% |
-
|
-
|
- |
- |
- |
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
- |
Fab of replica mirrors remain |
|
Pupil Viewer |
100% |
-
|
-
|
- |
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
- |
August
completion forcast |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
- |
Fab |
|
Prisms |
- |
13% |
13% |
23% |
74% |
- |
Fab |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
- |
Fab |
Problems
/ Solutions
The vendor selected for POM and Acquisition Mirror fabrication has not performed to his contract. This contract is being re-bid and a new order will be placed by the end of July. There is no impact to the schedule at this point.
Mechanism assembly and warm test has been off to a slow start due to final parts kitting problems. This has taken longer than anticipated but is being worked vigorously. This has caused a slip of two weeks in the mechanism assembly/test plan, but not overall impact to the main schedule.
Key
Personnel
Peter
Ruckle will assume the lead responsibility for software development on GNIRS as
of October 1st. Richard
will be available as needed on a part time basis.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360