GNIRS PROGRESS REPORT

June 28– July 20, 2001

           Accomplishments / Status

 

  Summary:  Overall, more than 71% of the work from the Restart Review to delivery has been completed. This report does not include accurate progress updates in the areas of electronics, software and procurement. 

The main focus of this report period has been design of the dewar shells, radiation shields and support structure(s), and completing fabrication of benches and mechanism.  All mechanisms are either in or have completed fabrication.  The Pre-Slit and Post-Slit benches just finishing fabrication. The Passive Collimator Assembly has been released for fabrication.  Mechanism assembly and warm assembly testing has been started.   Subsystem integration and testing has begun; integration of subsystems into the instrument will begin in the fall.

The OIWFS components, with the exception of the field lens, have been received from IFA.  During receiving inspection of the parts and assemblies, we discovered that some components did not match the interfaces given in the ICD, and this has caused some rework on the WFS bench.  This has delayed WFS integration and alignment, as the bench modifications are being done on a low priority basis.  The WFS will continue to be integrated on a non-interference basis with mechanism assembly and testing.

The project is consistently under-spending planned labor.  This is due mainly to three factors: 1) detail design taking longer than planned, 2) delays in completing fabrication and 3) shared resources with other project efforts.  This has all contributed to fewer labor hours charged to the project.

Capital is also behind the spending plan due to the delays in releasing assemblies to fabrication.  Spending should catch up to the plan by mid-August.  The two pieces of the Bulkhead Assembly have been released and contracted for a combined total of $135K.  We have also awarded the contracts for the two dewar shells, which will cost about $50K total.  These items will be released for fabrication in late July.

The project remains about 6 weeks behind schedule with respect to start of instrument integration.  The fall 2002 delivery date is not impacted.

  Next Milestone: The next major project milestone is the completion of mechanism testing in September.

 

  Earned Value:

 

February

March

April

May

June

July

BCWS

$2,049,349

$2,278,192

$2,565,371

$2,732,977

$2,929,722

$2,976,073

BCWP

$1,543,495

$1,694,322

$1,804.951

$1,912,351

$2,119,911

$2,182,434

ACWP

$1,739,549

$1,839,301

$1,915,889

$2,031,750

$2,343,546

$2,392,603

SPI

0.75

0.74

0.70

0.70

0.72

0.73

CPI

0.89

0.92

0.94

0.94

0.90

0.91

                

  Project Management: (65% complete)

 

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.

 

  Systems Engineering: (100% of planned work)

The main focus has been OIWFS component assembly inspection, readiness for integration/testing, and support of critical parts procurement and mechanism kitting, assembly and warm test.

 

  Mechanical Design, Fabrication, Assembly and Test: (79% overall)

The major activity in this work package has been the 2D design of the Bulkhead Assembly and its interfacing components, dewar shell design, bench fabrication, and 3D and 2D design of fixed assemblies.

 

Mechanisms: (87% complete overall).

 

Feb

Mar

Apr

May

June

July

Status

Camera

69%

77%

78%

88%

90%

91%

Final Fab

Focus

24%

24%

30%

48%

59%

59%

Released for Fab

Environmental Cover

97%

99%

99%

99%

99%

99%

Test (on-hold)

Acquisition Mirror

58%

68%

72%

75%

75%

75%

Fab (waiting for mirror)

Slit/Decker

66%

77%

83%

85%

90%

90%

Fab (waiting for mirror)

Filter Wheel

71%

70%

73%

78%

83%

83%

Assembly/test

Grating Turret

42%

51%

72%

83%

85%

86%

Fabrication (nearly complete)

Prism Turret

48%

47%

50%

56%

76%

85%

Fab

Motor Drives

90%

90%

100%

   -   

   -   

  -

Complete

 

Benches: (84% complete overall).

 

Feb

Mar

Apr

May

June

July

Status

Post-Slit

56%

65%

70%

   -

77%

88%

Fab

OIWFS Bench

67%

67%

79%

   -

86%

87%

Bench mods in process

Collimator

 

29%

29%

46%

62%

64%

All parts in Fab

Pre-Slit bench

44%

62%

70%

81%

83%

87%

Fab and assembly

 

Fixed Assemblies: (49% complete overall).

 

Feb

Mar

Apr

May

June

July

Status

Entrance Window

96%

100%

   -

    -

    -

    -

Complete

Detector Mount

48%

49%

60%

67%

68%

79%

Detail check

Cryo Cooler

9%

16%

16%

16%

24%

49%

Fab

LN2 Pre-Cool

4%

4%

17%

17%

84%

89%

2D drafting

Optical Bench Gimbal Mt.

53%

53%

54%

56%

45%

85%

Fab

Bulkhead Assembly

11%

24%

42%

52%

55%

64%

Fab

Front Rad Shield

5%

 5%

5%

5%

7%

10%

 3D design

Front Dewar Shell

26%

34%

37%

37%

37%

38%

2D drafting

Rear Dewar Shell

6%

8%

21%

21%

26%

   -

Released to fab

Vertical Inst Frame

5%

6%

6%

11%

31%

31%

2D drafting

Horizontal Inst Frame

1%

   -

    -

    -

8%

8%

2D drafting

Dewar Mount Truss

12%

12%

 12%

13%

47%

47%

2D drafting

Thermal Enclosure Mount

2%

7%

 10%

44%

53 %

53%

2D drafting

Handling Fixtures

25%

58%

   -

68%

68%

68%

Fab (welding)

  

Electronics: (77% complete overall)

The Instrument controller design work is essentially complete and the main activity is fabrication.  The Gemini approved modification to the Power Supply Rack of the GNIRS Array Controller is in process.  The OIWFS electronic components are received and work on integrating components into the thermal enclosure has started. 

 

 

 

Feb

Mar

Apr

May

June

July

Status

Component Controller TE

51%

68%

71%

 75%

66%

   -

 

 

VME Crate

92%

100%

   -

   -

100%

   -

SW testing

 

Motor Drive/Cryo Cooler Crate

62%

94%

100%

   -

100%

   -

SW testing

 

Internal Cabling and Connectors

12%

16%

16%

18%

90%

98%

 

 

Ancillary Cage Crate

26%

26%

26%

59%

63%

98%

Anodization and reassembly

 

IfA Electronics Box

   -

   -

   -

  -

  -

    -

Received from IFA

 

Bench Thermal Controller Crate

   -

   -

61%

68%

94%

98%

Assembly/wiring

External Cabling (Dewar to TE)

23%

23%

23%

23%

23%

23%

On hold

The Dewar Warm-up Controller

37%

37%

37%

37%

37%

37%

On hold; Rescheduled to later date

Dewar Electronics

   -

71%

   -

  

 95%

   -

 

 

Dewar Cold Station PCB’s

60%

60%

50%

60%

80%

80%

Ready for install and fit check

 

Dewar Internal Conn/Cabling

   -

72%

72%

72%

96%

   -

Fab

Documentation

 

50%

50%

50%

85%

   -

 

 

  Software Development: (68% complete overall – no new update).

 

The areas in work include some testing software with the electronics crates.  EPICS software is far ahead of schedule.

 

 

Feb

Mar

Apr

May

June

July

Components Controller Software

67%

91%

91%

91%

91%

   -

EPICS Software

60%

69%

69% 

69%

75%

   -

Test & DeBug

   -

   -

   -

   -

50%

   -

 

  Procurement: (67% complete overall – no new update).

 

The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.

                                     

 

Feb

Mar

Apr

May

June

July

Notes

Optics

    -

67%

71%

73%

79%

   -

Only POM and Acq mirror remain

RMI optics

100%

   -

   -

   -

   -

   -

Complete

Flat Mirrors

 

10%

50%

50%

50%

   -

Fab of replica mirrors remain

Pupil Viewer

100%

   -

   -

   -

   -

   -

Complete

BaF2 lenses

8%

50%

93%

75%

75%

   -

August completion forcast

Grating replicas

    -

23%

50%

83%

86%

   -

Fab

Prisms

    -

13%

13%

23%

74%

   -

Fab

Wollaston Prisms

    -

   -

0%

 10%

40%

   -

Fab

 

             Problems / Solutions

The vendor selected for POM and Acquisition Mirror fabrication has not performed to his contract.  This contract is being re-bid and a new order will be placed by the end of July.  There is no impact to the schedule at this point.

Mechanism assembly and warm test has been off to a slow start due to final parts kitting problems.  This has taken longer than anticipated but is being worked vigorously.  This has caused a slip of two weeks in the mechanism assembly/test plan, but not overall impact to the main schedule.

 

             Key Personnel

 

Peter Ruckle will assume the lead responsibility for software development on GNIRS as of October 1st.  Richard will be available as needed on a part time basis.


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360