PROGRESS REPORT 

June 5 – July 7, 2000

 Accomplishments / Status

 

Summary:  Overall, 25% of the work from the Restart Review to delivery has been completed. The primary focus of this reporting period has been 1) the solid model design/analysis of the Post-Slit, Pre-Slit, and OIWFS Optical Benches, 2) the risk reduction testing of the Linear and Rotary drive prototypes, and 3) the design of camera barrels, Filter Wheel mechanism, and fabrication of the Environmental Cover mechanism and motor drive assembly.

 

Next Milestone: The next major project milestone is the release of the optical benches for fabrication in August 2000.

 

Earned Value:     

                                BCWS    $1,181,580                              SPI         .63

                                BCWP    $   739,873                              CPI        .97

                                ACWP    $   761,603

 

Project Management: (32% completed)  A summary task schedule can be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/.

 

Systems Engineering: (81%) The activities in work are 1) structural analysis, 3) linear prototype, 4) rotary prototype, 5) bearing test fixture.

 

The structural analysis is in process and will be complete by the mid-July.

 

The Linear Mechanism Prototype is ready for cold testing.  The Rotary Mechanism Prototype is in cold test.  The bearing test prototype is fabrication.

 

Mechanical Design and Fabrication: (9%) Activities include optical bench solid modeling, camera design, filter wheel design, environmental cover fabrication, and motor drive assembly fabrication.

 

Wavefront Sensor Bench, Post-Slit Optical bench, the Pre-Slit Bench, the Collimator Mount.  The next task for these assemblies is to finish the detail 3D and 2D designs for fabrication.  This should be completed by mid-August.

 

The 3D design of the Short Red and Short Blue Camera Barrels are complete.  The 2D drafting of these camera barrels is 100% and 16% complete, respectively.  The 3D design of the Long Red Camera is 80% complete, and the Blue camera 3D design is 20% complete.  The 3D design of the camera drive spindle hub is 100% complete.

 

The 3D solid model design of the Filter Wheel Assembly mechanism is 94% complete.

 

The fabrication of the Environmental Cover Assembly is 85% complete.

 

The Acquisition Mirror mechanism 2D drafting is 7% complete.

 

The Motor Drive Assembly has been released for fabrication.

 

Electronics Design: (10%) Activities in this work package include electrical and mechanical design and construction of a simulator for use in software testing, dewar and mechanism wiring design definition, and array interface details. 

The construction of the Mechanism Simulator started in June and will complete in July.  Work on defining dewar wiring, and ALADDIN array interfacing details and on the detailed Mechanism wiring in process.

 

Software Development: (27%) The Components Controller Software is 56% complete.  Work has started on the System Software and is 6% complete.

 

Procurement: (27%) Major activities in this Work Package included optics work at RMI (50% complete) and monitoring vendor fabrication for the Environmental Cover Assembly.   We have inspected and accepted 4 entrance windows and 8 lenses from RMI and one filter from NDC in the UK.

 

 

Problems / Solutions

 

No items.

 

 

Key Personnel

 

No items

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360