GNIRS
PROGRESS REPORT
May
21– June 20, 2002
Accomplishments
/ Status
Summary:
92% of the work from the Restart Review to delivery has been completed.
Progress was made on radiation shield assembly, bench assembly and
wiring, and mechanism cold testing.
The
Dewar vacuum checks were successfully completed. Delivery of the remaining SR
camera lens is expected in late June, and will be integrated into the camera
in early July. Flexure testing has been delayed until mid-July due to late
shipment and installation of the flex rig.
The
investigation into the cause of the Slit mechanism cold test failure has been
completed. The cause was primarily due to bearing failure. The bearings are in
the process of being replaced with tungsten-sulfide coated bearings and the
mechanism will be cold tested in the last week of June. Because of the nature
of the bearing failure, the relevant bearings in the other cold mechanisms are
also being replaced.
All
testing is scheduled to complete and the instrument shipped to Chile in late
November. All planned schedule contingency has been used.
Next
Milestone:
The next major project milestones are:
- Slit mechanism cold testing completion in June
- Bench installation in July
- Thermal Distribution Assembly installation in June
- Flexure testing in mid-late July
Earned Value:
|
|
October
|
November
|
December
|
January
|
February
|
March
|
April
|
May
|
June
|
|
BCWS |
$3,145,000 |
$3,192,781 |
$3,236,748 |
$3,304,286 |
$3,344,496 |
$3,413,125 |
$3,462,160 |
$3,504,878 |
$3,546,177 |
|
BCWP |
$2,573,084 |
$2,617,408 |
$2,884,471 |
$2,911,411 |
$2,930,888 |
$2,970,031 |
$3,035,216 |
$3,156,912 |
$3,173,288 |
|
ACWP |
$2,938,004 |
$3,122,731 |
$3,313,415 |
$3,383,383 |
$3,453,168 |
$3,537,018 |
$3,756,257 |
$3,858,289 |
$3,956,665 |
|
SPI |
0.82 |
0.82 |
0.89 |
0.88 |
0.88 |
0.87 |
0.88 |
0.90 |
.89 |
|
CPI |
0.88 |
0.84 |
0.87 |
0.85 |
0.85 |
0.84 |
0.81 |
0.82 |
.80 |
This table reflects planned and actual charges to the project as of June 20, 2002. We have spent $1,514,255 in capital to date.
Project Management: (91% complete)
The
project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/
under Management, Planning. The current delivery of the GNIRS instrument is
November 29, 2002.
Systems Engineering: (100% of planned work)
Mechanical Design, Fabrication, Assembly and Test: (96%
overall) The major activity in this work package has been mechanism testing
and rework.
Mechanisms:
(96% complete overall).
|
|
March |
April |
May
|
June
|
Status
|
|
Slit |
99% |
99% |
99% |
90% |
Rework
and Cold test |
Benches:
(100% complete overall). Benches
are complete. Bench wiring is in
process, but is considered an integration activity.
Fixed
Assemblies:
(89% complete overall). Only
the Thermal Distribution Assembly is left, which will be closed out when it is
sized and installed into the dewar.
|
|
March
|
April |
May
|
June
|
Status
|
|
Cryo
Cooler |
90% |
94% |
100% |
100% |
Complete |
|
Thermal
Distribution Assembly |
75% |
75% |
75% |
90% |
Cleaning
and Assembly |
|
LN2
Pre-Cool |
87% |
83% |
100% |
100% |
Complete |
Electronics: (89% complete overall). Basic
work is complete.
|
|
March |
April |
May
|
June
|
Status
|
IfA
Electronics Box
|
33% |
33% |
33% |
57% |
In
check out |
|
External
Cabling |
36% |
36% |
36% |
- |
Used
in mechanism test; need only termination at one end |
|
Bulkhead
Internal Cabling |
58% |
58% |
69% |
- |
Assembly |
|
Documentation
|
95% |
95% |
95% |
95% |
|
Software Development: (100% complete overall). The work includes adjustments to the software during testing
|
|
May
|
June
|
|
Array
and Instrument Controller checkout |
88% |
90% |
Alignment and Integration: (46% complete overall)
|
|
March
|
April
|
May
|
June
|
|
Telescope
Simulator |
69% |
88% |
93% |
99% |
|
I.
Dewar and Structure |
- |
- |
- |
- |
|
II.
Mechanical Integration |
- |
43% |
43% |
43% |
|
III.
Warm Tests |
- |
- |
- |
9% |
|
IV.
Cold Tests |
- |
- |
- |
- |
Deliverables: (54% complete overall)
Work
in this area has focused on the outlines for the Hardware and Software
Maintenance manuals.
|
|
March
|
April
|
May
|
June
|
Comments
|
|
Instrument
Hardware |
- |
- |
- |
- |
|
|
Training
|
- |
- |
- |
- |
|
|
Manuals |
15% |
15% |
16% |
22% |
Manual
outlines complete. Draft
Software manual 67% complete |
|
As-Built
Fabrication Drawings |
- |
- |
- |
- |
|
Procurement: (97% complete overall).
|
|
Mar |
April |
May
|
June
|
Comments
|
|
Optics
|
98% |
99% |
99% |
99% |
SRC camera lens,
simulator optics still outstanding |
Problems / Solutions
Flexure
rig delay and slit mechanism rework have caused a delay in the start of
integration.
Key Personnel
No
changes.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360