
May 18– June
27, 2001
Accomplishments / Status
Summary: Overall, 69% of the work from the Restart Review to delivery has been completed. The main focus of this report period has been 3D and 2D design of the Bulkhead Assembly, Passive Collimator, and support structure(s), and fabrication. All mechanisms are in fabrication except the Focus Assembly, which is in drafting check. The Pre-Slit and Post-Slit benches are in fabrication. Mechanism assembly and test will start July due to delays in fabrication.
The OIWFS components from Gemini are expected to arrive the week of July 9th. The integration of the components onto the OIWFS bench and subsequent alignment will impact other work in process, primarily mechanism assembly and testing. We have hired an intern with optical technician experience to assist in component-to-bench fit check and alignment.
A GNIRS Quarterly Review was held on June 13. The review was attended by Mark Trueblood and Taft Armandroff (USGPO), Jeremy Mould (NOAO director), and Dan Weedman (NSF) by telecon.
The project is under-spending planned labor. This is due mainly to three factors: 1) detail design taking longer than planned, 2) delays in completing component fabrication (causing delays in using planned resources), and 3) our PM, AA, SW Eng, EE and ET have been shared with other project efforts. This has all contributed to fewer labor hours charged to the project. Sharing resources in item (3) has not impacted the critical path, or caused schedule delays.
Capital is also behind the spending plan due to the delays in releasing assemblies to fabrication. Spending should catch up to the plan by mid-August.
The project is 6 weeks behind schedule with respect to start of instrument integration. The fall 2002 delivery date is not impacted.
Next Milestone: The next major project milestone is the start of mechanism assembly and testing in July.
Earned Value:
|
|
February |
March |
April |
May |
June |
|
BCWS |
$2,049,349 |
$2,278,192 |
$2,565,371 |
$2,732,977 |
$2,929,722 |
|
BCWP |
$1,543,495 |
$1,694,322 |
$1,804.951 |
$1,912,351 |
$2,119,911 |
|
ACWP |
$1,739,549 |
$1,839,301 |
$1,915,889 |
$2,031,750 |
$2,343,546 |
|
SPI |
0.75 |
0.74 |
0.70 |
0.70 |
0.72 |
|
CPI |
0.89 |
0.92 |
0.94 |
0.94 |
0.90 |
Project Management: (63% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.
Systems Engineering: (100% of planned work)
The main focus has been support of design and planning for Mechanism assembly and test.
Mechanical Design, Fabrication, Assembly and Test: (74% overall)
The major activity in this work package has been the 2D design of the Bulkhead Assembly and its interfacing components, bench fabrication, and 3D and 2D design of fixed assemblies.
Mechanisms:
(86% complete overall)
|
|
Feb
|
Mar
|
Apr
|
May |
June |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
Fab
|
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
Detail
check |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
Fab
(waiting for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
Fab
|
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
Assembly/test
|
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
Fab
|
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
Fab
|
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
Complete |
Benches: (77% complete overall)
|
|
Feb |
Mar |
Apr |
May |
June |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
Fab |
|
OIWFS Bench |
67% |
67% |
79% |
- |
86% |
Waiting for parts from IFA |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
Final
parts in drafting check |
|
Pre-Slit
bench |
44%
|
62%
|
70%
|
81% |
83%
|
Fab
|
Fixed Assemblies: (40% complete overall)
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
Detail
check |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
2D
drafting |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
2D
drafting |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
(New
estimate) Fab |
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
Fab |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
3D
design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
2D
drafting |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
2D
drafting |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
31%
|
2D
drafting |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
2D
drafting |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
2D
drafting |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53
% |
2D
drafting |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
Fab
(welding) |
Electronics: (77% complete overall)
The
Instrument controller design work is essentially complete and the main activity
is fabrication. All
electronics parts are either in house or on order.
Gemini has approved a modification to the Power Supply Rack of the GNIRS
Array Controller that replaces several analog supplies with a switching supply,
and results in a 40 lb reduction in overall weight of the controller.
|
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
66% |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
100%
|
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
100%
|
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
100%
|
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
63%
|
Assembly/wiring
|
|
|
IfA
Electronics Box |
100%
|
- |
- |
- |
- |
Waiting
for IfA |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
94% |
Assembly/wiring
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
23% |
On hold |
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
37% |
On hold; Rescheduled to later date |
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
95% |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
80%
|
Ready
for install and fit check |
|
|
Dewar
Internal Conn/Cabling |
- |
72%
|
72%
|
72% |
96% |
Fab
|
|
Documentation
|
|
50%
|
50%
|
50% |
85% |
|
|
Software Development: (68% complete overall)
The
areas in work include some testing software with the electronics crates.
EPICS software is far ahead of schedule.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
Procurement: (67% complete overall)
The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.
|
|
Feb |
Mar |
Apr |
May |
June |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
|
|
RMI optics |
100% |
-
|
-
|
- |
- |
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
Fab |
|
Pupil Viewer |
100% |
-
|
-
|
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
July
completion |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
Fab |
|
Prisms |
- |
13% |
13% |
23% |
74% |
Fab |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
Fab |
Problems
/ Solutions
None
Key
Personnel
Jerry Penegor, GNIRS EE, is working with Barry Starr’s R&D group in parallel with GNIRS assignments. There is no negative impact to GNIRS.
Three interns have been hired to assist over the summer, two Optical Sciences students and one EE graduate student. One Optical Sciences student is assigned to preparing for OIWFS integration and the other to parts kitting and preparing for mechanism assembly/testing. The EE grad student is assigned to Jerry Penegor.
Richard Wolff will be retiring later this year. Peter Ruckle will assume the lead responsibility for software development on GNIRS as of October 1st. Richard will be available as needed on a part time basis.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360