May 18– June 27, 2001

           Accomplishments / Status

  Summary:  Overall, 69% of the work from the Restart Review to delivery has been completed.  The main focus of this report period has been 3D and 2D design of the Bulkhead Assembly, Passive Collimator, and support structure(s), and fabrication.  All mechanisms are in fabrication except the Focus Assembly, which is in drafting check.  The Pre-Slit and Post-Slit benches are in fabrication. Mechanism assembly and test will start July due to delays in fabrication.

 

The OIWFS components from Gemini are expected to arrive the week of July 9th.  The integration of the components onto the OIWFS bench and subsequent alignment will impact other work in process, primarily mechanism assembly and testing.  We have hired an intern with optical technician experience to assist in component-to-bench fit check and alignment.

 

A GNIRS Quarterly Review was held on June 13.  The review was attended by Mark Trueblood and Taft Armandroff (USGPO), Jeremy Mould (NOAO director), and Dan Weedman (NSF) by telecon.

The project is under-spending planned labor.  This is due mainly to three factors: 1) detail design taking longer than planned, 2) delays in completing component fabrication (causing delays in using planned resources), and 3) our PM, AA, SW Eng, EE and ET have been shared with other project efforts.  This has all contributed to fewer labor hours charged to the project.  Sharing resources in item (3) has not impacted the critical path, or caused schedule delays.

 

Capital is also behind the spending plan due to the delays in releasing assemblies to fabrication.  Spending should catch up to the plan by mid-August.

 

The project is 6 weeks behind schedule with respect to start of instrument integration.  The fall 2002 delivery date is not impacted.

 

  Next Milestone: The next major project milestone is the start of mechanism assembly and testing in July.

 

  Earned Value:

 

February

March

April

May

June

BCWS

$2,049,349

$2,278,192

$2,565,371

$2,732,977

$2,929,722

BCWP

$1,543,495

$1,694,322

$1,804.951

$1,912,351

$2,119,911

ACWP

$1,739,549

$1,839,301

$1,915,889

$2,031,750

$2,343,546

SPI

0.75

0.74

0.70

0.70

0.72

CPI

0.89

0.92

0.94

0.94

0.90

                

  Project Management: (63% complete)

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.

 

  Systems Engineering: (100% of planned work)

The main focus has been support of design and planning for Mechanism assembly and test.

 

  Mechanical Design, Fabrication, Assembly and Test: (74% overall)

The major activity in this work package has been the 2D design of the Bulkhead Assembly and its interfacing components, bench fabrication, and 3D and 2D design of fixed assemblies.

 

Mechanisms: (86% complete overall)

 

Feb

Mar

Apr

May

June

Status

Camera

69%

77%

78%

88%

90%

Fab

Focus

24%

24%

30%

48%

59%

Detail check

Environmental Cover

97%

99%

99%

99%

99%

Test (on-hold)

Acquisition Mirror

58%

68%

72%

75%

75%

Fab (waiting for mirror)

Slit/Decker

66%

77%

83%

85%

90%

Fab

Filter Wheel

71%

70%

73%

78%

83%

Assembly/test

Grating Turret

42%

51%

72%

83%

85%

Fab

Prism Turret

48%

47%

50%

56%

76%

Fab

Motor Drives

90%

90%

100%

   -   

   -   

Complete


Benches:
(77% complete overall)

 

Feb

Mar

Apr

May

June

Status

Post-Slit

56%

65%

70%

   -

77%

Fab

OIWFS Bench

67%

67%

79%

   -

86%

Waiting for parts from IFA

Collimator

 

29%

29%

46%

62%

Final parts in drafting check

Pre-Slit bench

44%

62%

70%

81%

83%

Fab


Fixed Assemblies
: (40% complete overall)

 

Feb

Mar

Apr

May

June

Status

Entrance Window

96%

100%

   -

    -

    -

Complete

Detector Mount

48%

49%

60%

67%

68%

Detail check

Cryo Cooler

9%

16%

16%

16%

24%

2D drafting

LN2 Pre-Cool

4%

4%

17%

17%

84%

2D drafting

Optical Bench Gimbal Mt.

53%

53%

54%

56%

45%

(New estimate) Fab

Bulkhead Assembly

11%

24%

42%

52%

55%

Fab

Front Rad Shield

5%

 5%

5%

5%

7%

 3D design

Front Dewar Shell

26%

34%

37%

37%

37%

2D drafting

Rear Dewar Shell

6%

8%

21%

21%

26%

2D drafting

Vertical Inst Frame

5%

6%

6%

11%

31%

2D drafting

Horizontal Inst Frame

1%

   -

    -

    -

8%

2D drafting

Dewar Mount Truss

12%

12%

 12%

13%

47%

2D drafting

Thermal Enclosure Mount

2%

7%

 10%

44%

53 %

2D drafting

Handling Fixtures

25%

58%

   -

68%

68%

Fab (welding)


 
Electronics:
(77% complete overall)

The Instrument controller design work is essentially complete and the main activity is fabrication.   All electronics parts are either in house or on order.   Gemini has approved a modification to the Power Supply Rack of the GNIRS Array Controller that replaces several analog supplies with a switching supply, and results in a 40 lb reduction in overall weight of the controller.

 

 

Feb

Mar

Apr

May

June

Status

Component Controller TE

51%

68%

71%

 75%

66%

 

 

VME Crate

92%

100%

   -

   -

100%

SW testing

 

Motor Drive/Cryo Cooler Crate

62%

94%

100%

   -

100%

SW testing

 

Internal Cabling and Connectors

12%

16%

16%

18%

100%

 

 

Ancillary Cage Crate

26%

26%

26%

59%

63%

Assembly/wiring

 

IfA Electronics Box

100%

   -

   -

  -

  -

Waiting for IfA

 

Bench Thermal Controller Crate

   -

   -

61%

68%

94%

Assembly/wiring

External Cabling (Dewar to TE)

23%

23%

23%

23%

23%

On hold

The Dewar Warm-up Controller

37%

37%

37%

37%

37%

On hold; Rescheduled to later date

Dewar Electronics

   -

71%

   -

  

 95%

 

 

Dewar Cold Station PCB’s

60%

60%

50%

60%

80%

Ready for install and fit check

 

Dewar Internal Conn/Cabling

   -

72%

72%

72%

96%

Fab

Documentation

 

50%

50%

50%

85%

 

 

  Software Development: (68% complete overall)

The areas in work include some testing software with the electronics crates.  EPICS software is far ahead of schedule.

 

Feb

Mar

Apr

May

June

Components Controller Software

67%

91%

91%

91%

91%

EPICS Software

60%

69%

69% 

69%

75%

Test & DeBug

   -

   -

   -

   -

50%

 

  Procurement: (67% complete overall)

The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.

                                     

 

Feb

Mar

Apr

May

June

Notes

Optics

    -

67%

71%

73%

79%

 

RMI optics

100%

   -

   -

   -

   -

Complete

Flat Mirrors

 

10%

50%

50%

50%

Fab

Pupil Viewer

100%

   -

   -

   -

   -

Complete

BaF2 lenses

8%

50%

93%

75%

75%

July completion

Grating replicas

    -

23%

50%

83%

86%

Fab

Prisms

    -

13%

13%

23%

74%

Fab

Wollaston Prisms

    -

   -

0%

 10%

40%

Fab

 

             Problems / Solutions

None

             Key Personnel

Jerry Penegor, GNIRS EE, is working with Barry Starr’s R&D group in parallel with GNIRS assignments.  There is no negative impact to GNIRS.

 

Three interns have been hired to assist over the summer, two Optical Sciences students and one EE graduate student.  One Optical Sciences student is assigned to preparing for OIWFS integration and the other to parts kitting and preparing for mechanism assembly/testing.  The EE grad student is assigned to Jerry Penegor.

 

Richard Wolff will be retiring later this year.  Peter Ruckle will assume the lead responsibility for software development on GNIRS as of October 1st.  Richard will be available as needed on a part time basis.

 

  


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360