GNIRS
PROGRESS REPORT
April
24– May 20, 2002
Accomplishments / Status
Summary:
92% of the work from the Restart Review to delivery has been completed.
Progress was made on radiation shield assembly, bench assembly and
wiring, collimator characterization and mechanism cold testing.
Fabrication
is complete. Any remaining fabrication will be considered part of assembly
rework or part of the integration process.
Delivery of the remaining SR camera lens is expected in late May, and
the lens will be integrated into the camera following flexure testing. Two
gratings, which had wrong rulings, have been redone and delivery is expected
this week. Integration of the gratings and prisms onto their respective
turrets is scheduled for next week.
All
mechanisms have completed cold testing except the Slit mechanism, which did
not pass cold testing. An
investigative team has been assigned to determine the exact cause of the
anomaly. The assembly has until June 30 to complete cold testing
before impacting the instrument delivery schedule.
Flexure
testing has been delayed until mid-July due to late shipment and installation
of the flex rig, and will occur after the 1st instrument cold test
instead of before.
All testing is scheduled to complete and the instrument shipped to Chile on November 29th. All planned contingency, except for the 4th cold cycle, has been used.
Next
Milestone:
The next major project milestones are:
- Instrument vacuum checks in June
- Bench installation in June
- Slit mechanism cold testing completion in June
Earned Value:
|
|
October
|
November
|
December
|
January
|
February
|
March
|
April
|
May
|
|
BCWS |
$3,145,000 |
$3,192,781 |
$3,236,748 |
$3,304,286 |
$3,344,496 |
$3,413,125 |
$3,462,160 |
$3,504,878 |
|
BCWP |
$2,573,084 |
$2,617,408 |
$2,884,471 |
$2,911,411 |
$2,930,888 |
$2,970,031 |
$3,035,216 |
$3,156,912 |
|
ACWP |
$2,938,004 |
$3,122,731 |
$3,313,415 |
$3,383,383 |
$3,453,168 |
$3,537,018 |
$3,756,257 |
$3,858,289 |
|
SPI |
0.82 |
0.82 |
0.89 |
0.88 |
0.88 |
0.87 |
0.88 |
0.90 |
|
CPI |
0.88 |
0.84 |
0.87 |
0.85 |
0.85 |
0.84 |
0.81 |
0.82 |
This table reflects planned and actual charges to the project as of May 20, 2002. We have spent $1,491,615 in capital to date.
Project Management: (92% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current delivery of the GNIRS instrument is November 29, 2002.
Systems Engineering: (100% of planned work)
Mechanical Design, Fabrication, Assembly and Test: (96%
overall) The major activity
in this work package has been drawing completion and cleanup, fabrication,
mechanism testing and rework.
Mechanisms:
(96% complete overall).
|
|
March |
April |
May
|
Status
|
|
Slit |
99% |
99% |
99% |
Rework
and Cold test |
Benches: (100% complete overall). Benches are complete. Bench wiring is in process, but is considered an integration activity.
Fixed Assemblies: (91% complete overall). Only the Thermal Distribution Assembly left which will be closed out when it is sized and installed into the dewar.
|
|
March
|
April |
May
|
Status
|
|
Cryo
Cooler |
90% |
94% |
100% |
Complete |
|
Thermal
Distribution Assembly |
75% |
75% |
75% |
Assembly |
|
LN2
Pre-Cool |
87% |
83% |
100% |
Complete |
Electronics: (89% complete overall). Basic work complete.
|
|
March |
April |
May
|
Status
|
IfA
Electronics Box
|
33% |
33% |
33% |
In
check out |
|
External
Cabling |
36% |
36% |
36% |
Used
in mechanism test; need only termination at one end |
|
Bulkhead
Internal Cabling |
58% |
58% |
69% |
Assembly |
|
Documentation
|
95% |
95% |
95% |
|
Software Development: (90% complete overall). The work includes adjustments to the software during testing
|
|
May
|
|
Array
and Instrument Controller checkout |
88% |
Alignment and Integration: (43% complete overall)
|
|
March
|
April
|
May
|
|
Telescope
Simulator |
69% |
88% |
93% |
|
I.
Dewar and Structure |
- |
- |
- |
|
II.
Mechanical Integration |
- |
43% |
43% |
|
III.
Warm Tests |
- |
- |
- |
|
IV.
Cold Tests |
- |
- |
- |
Deliverables: (51% complete overall)
Work in this area has focused on the outlines for the Hardware and Software Maintenance manuals.
|
|
March
|
April
|
May
|
Comments
|
|
Instrument
Hardware |
- |
- |
- |
|
|
Training
|
- |
- |
- |
|
|
Manuals |
15% |
15% |
16% |
Manual
outlines complete. Draft
Software manual 67% complete |
|
As-Built
Fabrication Drawings |
- |
- |
- |
|
Procurement: (96% complete overall).
|
|
Mar |
April |
May |
Comments |
|
Optics
|
98% |
99% |
99% |
SRC camera lens,
simulator optics still outstanding |
Problems / Solutions
Flexure rig delay has caused re-planning of first integration steps. The slit mechanism did not pass cold testing; the cause is being investigated.
Key Personnel
One
mechanical designer and two instrument makers released from project effective
May 1st.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360