April
23 – May 17, 2001
Accomplishments / Status
Summary:
Overall, 64% of the work from the Restart Review to delivery has been
completed. The main focus of this
report period has been 3D and 2D design of the Bulkhead Assembly, the Passive
Collimator, 3D design of the support structure(s), and fabrication.
All mechanisms are in fabrication except for one camera barrel and the
Focus Assembly, which are in drafting check.
The Pre-Slit and Post-Slit benches are in fabrication. Work has started
on several fixed assemblies. Mechanism
assembly and test has been planned in detail, and will start June. The OIWFS
components from Gemini are now expected to arrive in June.
A waiver request to expand the envelope GNIRS will occupy has been
granted by Gemini. The next GNIRS
Quarterly Review will be held on June 13 in Tucson.
Next Milestone: The next major project milestone is the completion of the
3D design of the Passive Collimator Compensation Assembly in late May.
This will complete the design of the cold structure.
Earned Value:
|
|
February |
March |
April |
May |
|
BCWS |
$2,049,349 |
$2,278,192 |
$2,565,371 |
$2,732,977 |
|
BCWP |
$1,543,495 |
$1,694,322 |
$1,804.951 |
$1,912,351 |
|
ACWP |
$1,739,549 |
$1,839,301 |
$1,915,889 |
$2,031,750 |
|
SPI |
0.75 |
0.74 |
0.70 |
0.70 |
|
CPI |
0.89 |
0.92 |
0.94 |
0.94 |
Project Management: (58% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. Work is being done to prepare for integration later this year. The August 2002 scheduled delivery date of the GNIRS instrument has not changed.
Systems Engineering: (100% of planned work)
The main focus has been support of the Bulkhead Assembly and Passive Collimator designs, and the detailed planning for Mechanism assembly and test.
Mechanical Design, Fabrication, Assembly and Test: (49% overall)
The major activity in this work package has been finishing 3D and starting the 2D design of the Bulkhead Assembly and its interfacing components, bench fabrication, and 3D and 2D design of fixed assemblies. The Passive Collimator Compensator Assembly 3D design is 95% complete and 2D detail design has started.
Mechanisms: (81% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
2D
detail/Fab |
|
Focus
|
24%
|
24%
|
30%
|
48% |
detail
check |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
Fab
(waiting for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
Fab
|
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
Fab
|
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
Fab
|
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
Fab
|
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
Complete |
Benches: (70% complete overall).
|
|
Feb |
Mar |
Apr |
May |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
Fab (no new update) |
|
OIWFS Bench |
67% |
67% |
79% |
- |
Waiting for parts from IFA |
|
Collimator
|
|
29%
|
29%
|
46% |
Design/Drafting/Fab
|
|
Pre-Slit
bench |
44%
|
62%
|
70%
|
85% |
Fab
|
Fixed Assemblies: (31% complete overall).
|
|
Feb
|
Mar
|
Apr
|
May |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
detail
check |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
3D
design |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
3D
design |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
Fab
|
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
detail
check |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
3D
design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
3D
design |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
3D
design |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
2D
drafting |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
2D
drafting |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
2D
drafting |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
detail
check |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
Fab (welding) |
Electronics: (70% complete overall)
The design work is essentially complete and the main activity is fabrication. All electronics parts are either in house or on order.
|
|
|
Feb
|
Mar
|
Apr
|
May |
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
assembly/wiring
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
assembly/wiring
|
|
|
IfA
Electronics Box |
100%
|
- |
- |
- |
waiting
for IfA |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
assembly/wiring
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
assembly/wiring |
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
assembly/wiring |
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
boards
being stuffed |
|
|
Dewar
Internal Conn/Cabling |
- |
72%
|
72%
|
72% |
ready
for fab |
|
Documentation
|
|
50%
|
50%
|
50% |
schematic cleanup |
|
Software Development: (62% complete overall).
The areas in work include some testing software with the electronics crates. EPICS software is far ahead of schedule.
|
|
Feb
|
Mar
|
Apr
|
May |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
Procurement: (64% complete overall).
The major activities in this Work Package included monitoring vendor mechanical fabrication.
|
|
Feb |
Mar |
Apr |
May |
Notes |
|
Optics |
- |
67% |
71% |
73% |
|
|
RMI optics |
100% |
-
|
-
|
- |
complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
Fab |
|
Pupil Viewer |
100% |
-
|
-
|
- |
complete |
|
Janos
BaF2 lenses |
8%
|
50%
|
93%
|
75% |
3
of 4 lenses complete |
|
Grating replicas |
- |
23% |
50% |
83% |
Fab |
|
Prisms |
- |
13% |
13% |
23% |
Fab |
|
Wollaston Prisms |
- |
- |
0% |
10% |
Fab |
Problems / Solutions
One BaF2 lens was broken during the final coating process at Janos. Material to replace the lens has been found, but the lens will be delivered 12 weeks late. We have adjusted our camera assembly/test plan to compensate.
Key Personnel
Jerry Penegor, GNIRS EE, is working Array Controller issues in parallel with GNIRS assignments. There is no negative impact to GNIRS. Two interns have been hired to assist over the summer, one Junior Optical Sciences student and one EE graduate student. Both will start work on June 4th and be here for 10 weeks. John Pina, part-time technician and Optical Sciences student, will be participating in the NOAO REU program over the summer and will not be working on the GNIRS project except as time allows.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360