GNIRS
PROGRESS REPORT
February 20
– March 22, 2002
Accomplishments / Status
Summary: 90% of the work from the Restart Review to delivery has been completed. Progress was made on radiation shield fabrication and mechanism assembly cold testing. The Passive Radiation Shield fabrication is complete. The Active Shields are in fabrication and should be complete this month. The Camera Assembly has completed cold test functional testing and optics were installed into the camera barrels. Normalizing the focus of each camera remains before the assembly is ready to install into the post-slit bench. Final adjustments are being made to the Slit/Decker Assembly prior to warm and cold testing. Cold tests will include the entire Pre-slit Assembly (two Filter Wheels, Slit/Decker, Fore-Optics). The IFU mass model from Durham has been fit checked to the Slit-Slide.
The Grating Turret has completed cold test. The Acquisition Mirror is next in line for cold testing, followed by the Slit/Decker Assembly and then the Prism Turret. Wiring of the benches is in process.
The
Collimator Assembly is complete and final adjustments are being made prior to
installation into the post-slit bench.
Next Milestone: The next major project milestone is the release
of the completion of mechanism testing by April 15th.
Earned Value:
|
|
August |
September |
October |
November |
December |
January |
February |
March |
|
BCWS |
$3,030,916 |
$3,085,811 |
$3,145,000 |
$3,192,781 |
$3,236,748 |
$3,304,286 |
$3,344,496 |
$3,413,125 |
|
BCWP |
$2,357,289 |
$2,526,319 |
$2,573,084 |
$2,617,408 |
$2,884,471 |
$2,911,411 |
$2,930,888 |
$2,970,031 |
|
ACWP |
$2,603,604 |
$2,762,963 |
$2,938,004 |
$3,122,731 |
$3,313,415 |
$3,383,383 |
$3,453,168 |
$3,537,018 |
|
SPI |
0.78 |
0.82 |
0.82 |
0.82 |
0.89 |
0.88 |
0.88 |
0.87 |
|
CPI |
0.91 |
0.91 |
0.88 |
0.84 |
0.87 |
85. |
85. |
0.84 |
This
table reflects planned and actual charges to the project as of March 22, 2002.
We have spent $1,381,986 in capital to date.
Project Management: (83% complete)
The
project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/
under Management, Planning. The current scheduled delivery of the GNIRS
instrument is October 2002.
Systems Engineering: (100% of planned work)
The
main focus has been mechanism assembly and cold testing, and support of design
changes and updates.
Mechanical Design, Fabrication, Assembly and Test: (96% overall)
The major activity in this work package has been 2D design of radiation shields and fabrication.
Mechanisms: (98% complete overall).
|
|
Jun |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Status
|
|
Camera
|
90% |
91% |
91% |
91% |
92% |
98% |
99% |
99% |
99% |
100% |
Test
|
|
Focus
|
59% |
59% |
60% |
67% |
|
73% |
89% |
92% |
88% |
91% |
Assembly |
|
Environmental
Cover |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
on-hold |
|
Acquisition
Mirror |
75%
|
75% |
76% |
93% |
93% |
- |
89% |
89% |
89% |
90% |
Assembly |
|
Slit/Decker
|
90%
|
90% |
93% |
93% |
93% |
95% |
99% |
99% |
99% |
99% |
Test |
|
Filter
Wheel |
83%
|
83% |
95% |
95% |
95% |
95% |
96% |
96% |
96% |
96% |
Test |
|
Grating
Turret |
85%
|
86% |
89% |
97% |
98% |
- |
98% |
98% |
98% |
100% |
Test |
|
Prism
Turret |
76%
|
85% |
92% |
98% |
98% |
- |
95% |
95% |
95% |
96% |
Test |
|
Motor
Drives |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
Benches:
(98% complete overall). Benches are
complete. The Collimator is in
final assembly.
|
|
Jun |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Status |
|
Post-Slit |
77% |
88% |
94% |
99% |
100% |
- |
- |
- |
- |
- |
Complete |
|
OIWFS |
86% |
87% |
89% |
99% |
100% |
- |
- |
- |
- |
- |
Complete |
|
Collimator
|
62% |
64% |
77% |
95% |
- |
- |
95% |
95% |
95% |
95% |
Assembly |
|
Pre-Slit
|
83%
|
87% |
91% |
99% |
100% |
- |
- |
- |
- |
- |
Complete |
Fixed Assemblies: (91% complete overall).
The Radiation Shields are the pacing items in fixed assemblies.
|
|
June
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Status
|
|
Entrance
Window |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
68%
|
79% |
79% |
97% |
97% |
- |
96% |
100% |
- |
- |
Complete |
|
Cryo
Cooler |
24%
|
49% |
51% |
59% |
59% |
70% |
88% |
89% |
87% |
90% |
Assembly |
|
Molecular
Sieve |
|
|
|
|
|
45% |
100% |
- |
- |
- |
Complete |
|
Thermal
Distribution Assembly |
|
|
12% |
26% |
- |
- |
52% |
75% |
75% |
75% |
Assembly |
|
Bulkhead
Rad Shield |
|
|
1% |
5% |
9% |
53% |
100% |
- |
- |
- |
Task closed |
|
LN2
Pre-Cool |
84%
|
89% |
91% |
91% |
91% |
- |
79% |
83% |
83% |
87% |
Assembly |
|
Optical
Bench Gimbal Mt. |
45%
|
85% |
95% |
100% |
- |
- |
- |
- |
- |
- |
Complete |
|
Bulkhead
Assembly |
55%
|
64% |
74% |
75% |
90% |
98% |
100% |
- |
- |
- |
Complete |
|
Passive
Rad Shield |
7%
|
10% |
10% |
10% |
16% |
42% |
41% |
74% |
83% |
98% |
Assembly |
|
Active
Rad Shield |
|
|
18% |
18% |
30% |
42% |
15% |
39% |
56% |
76% |
Fab |
|
Front
Dewar Shell |
37%
|
38% |
66% |
70% |
88% |
100% |
- |
- |
- |
- |
Complete |
|
Rear
Dewar Shell |
26%
|
- |
57% |
61% |
82% |
100% |
- |
- |
- |
- |
Complete |
|
Vertical
Inst Frame |
- |
- |
14% |
77% |
84% |
92% |
99% |
100% |
- |
- |
Complete |
|
Horizontal
Inst Frame |
8%
|
8% |
15% |
57% |
57% |
100% |
- |
- |
- |
- |
Complete |
|
Dewar
Mount Truss |
47%
|
47% |
47% |
47% |
73% |
- |
84% |
85% |
100% |
100% |
Complete |
|
Thermal
Enclosure Mount |
53% |
53% |
58% |
70% |
89% |
96% |
100% |
- |
- |
- |
Complete |
|
Handling
Fixtures |
68%
|
68% |
100% |
100% |
- |
- |
- |
- |
- |
- |
Complete |
|
Ballast
Weights |
|
|
|
75% |
83% |
100% |
- |
- |
- |
- |
Complete |
Electronics: (89% complete overall).
|
|
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Status |
|
Component
Controller TE |
- |
90% |
86% |
86% |
- |
72% |
72% |
72% |
72% |
|
|
|
|
VME
Crate |
- |
- |
- |
- |
- |
- |
- |
|
- |
Complete |
|
|
Motor
Drive/Cryo Cooler Crate |
- |
- |
- |
- |
- |
- |
- |
|
- |
Complete |
|
|
Internal
Cabling and Connectors |
98% |
98% |
98% |
98% |
100% |
- |
- |
|
- |
Complete |
|
|
Ancillary
Cage Crate |
98% |
98% |
98% |
98% |
100% |
- |
- |
|
- |
Complete |
|
|
IfA
Electronics Box |
- |
30% |
30% |
30% |
30% |
30% |
33% |
33% |
33% |
In check out |
|
|
Bench
Thermal Controller Crate |
98% |
98% |
98% |
98% |
70% |
100% |
- |
- |
- |
Complete |
|
External
Cabling (Dewar to TE) |
23% |
23% |
23% |
23% |
23% |
23% |
36% |
36% |
36% |
|
|
|
The
Dewar Warm-up Controller |
37% |
37% |
37% |
37% |
- |
59% |
87% |
100% |
- |
Complete |
|
|
Dewar
Electronics |
- |
95% |
95% |
95% |
95% |
60% |
60% |
60% |
60% |
|
|
|
|
Dewar
Cold Station PCB’s |
80% |
80% |
80% |
80% |
80% |
80% |
80% |
80% |
80% |
Ready for install and fit check |
|
|
Dewar
Internal Cabling |
- |
96% |
96% |
96% |
- |
58% |
58% |
58% |
58% |
On Hold – waiting for dewar |
|
Documentation
|
- |
95% |
95% |
95% |
95% |
95% |
95% |
95% |
95% |
|
|
|
Software
Test Fixture |
|
100% |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
|
Array
Controller Upgrade |
|
|
|
|
|
100% |
- |
- |
- |
Complete |
|
Software Development: (86% complete overall).
The
areas in work include testing software with the electronics crates, working on
the EPICS software and on the OIWFS software.
|
|
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
|
Components
Controller Software |
91% |
- |
91% |
94% |
94% |
94% |
85% |
86% |
86% |
86% |
|
Test
& DeBug |
50% |
- |
50% |
75% |
75% |
75% |
95% |
100% |
- |
- |
|
EPICS
Software |
75% |
- |
82% |
82% |
82% |
- |
96% |
99% |
99% |
99% |
Alignment
and Integration: (27% complete overall)
|
|
Feb |
Mar |
|
Telescope
Simulator |
69% |
69% |
|
I.
Dewar and Structure |
- |
- |
|
II.
Mechanical Integration |
- |
- |
|
III.
Warm Tests |
- |
- |
|
IV.
Cold Tests |
- |
- |
Deliverables: (47% complete overall)
Work in this area has focused on the preparation test plans for acceptance
testing.
|
|
Dec |
Jan |
Feb |
Mar |
|
Instrument
Hardware |
- |
- |
- |
- |
|
Training
|
- |
- |
- |
- |
|
Test
plans |
46% |
99% |
99% |
99% |
|
Manuals |
- |
- |
2% |
15% |
|
As-Built
Fabrication Drawings |
- |
- |
- |
- |
Procurement: (93% complete overall).
|
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
|
Optics |
- |
89% |
86% |
86% |
86% |
86% |
90% |
90% |
98% |
Problems / Solutions
Radiation
Shields remain the pacing item on the project.
Cleaning and testing mechanisms is also a high priority item.
Key Personnel
No
Changes
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360