GNIRS PROGRESS REPORT

February 20 – March 22, 2002

 

           Accomplishments / Status

  Summary:  90% of the work from the Restart Review to delivery has been completed.  Progress was made on radiation shield fabrication and mechanism assembly cold testing. The Passive Radiation Shield fabrication is complete.  The Active Shields are in fabrication and should be complete this month. The Camera Assembly has completed cold test functional testing and optics were installed into the camera barrels.  Normalizing the focus of each camera remains before the assembly is ready to install into the post-slit bench. Final adjustments are being made to the Slit/Decker Assembly prior to warm and cold testing.  Cold tests will include the entire Pre-slit Assembly (two Filter Wheels, Slit/Decker, Fore-Optics).  The IFU mass model from Durham has been fit checked to the Slit-Slide.

The Grating Turret has completed cold test.  The Acquisition Mirror is next in line for cold testing, followed by the Slit/Decker Assembly and then the Prism Turret.  Wiring of the benches is in process. 

The Collimator Assembly is complete and final adjustments are being made prior to installation into the post-slit bench.

  Next Milestone: The next major project milestone is the release of the completion of mechanism testing by April 15th.

  Earned Value:

 

August

September

October

November

December

January

February

March

BCWS

$3,030,916

$3,085,811

$3,145,000

$3,192,781

$3,236,748

$3,304,286

$3,344,496

$3,413,125

BCWP

$2,357,289

$2,526,319

$2,573,084

$2,617,408

$2,884,471

$2,911,411

$2,930,888

$2,970,031

ACWP

$2,603,604

$2,762,963

$2,938,004

$3,122,731

$3,313,415

$3,383,383

$3,453,168

$3,537,018

SPI

0.78

0.82

0.82

0.82

0.89

0.88

0.88

0.87

CPI

0.91

0.91

0.88

0.84

0.87

85.

85.

0.84

This table reflects planned and actual charges to the project as of March 22, 2002.  We have spent $1,381,986 in capital to date.

  Project Management: (83% complete)

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery of the GNIRS instrument is October 2002.

  Systems Engineering: (100% of planned work)

The main focus has been mechanism assembly and cold testing, and support of design changes and updates.

  Mechanical Design, Fabrication, Assembly and Test: (96% overall)

The major activity in this work package has been 2D design of radiation shields and fabrication.

Mechanisms: (98% complete overall).


 

Jun

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Status

Camera

90%

91%

91%

91%

92%

98%

99%

99%

99%

100%

Test

Focus

59%

59%

60%

67%

 

73%

89%

92%

88%

91%

Assembly

Environmental Cover

99%

99%

99%

99%

99%

99%

99%

99%

99%

99%

 on-hold

Acquisition Mirror

75%

75%

76%

93%

93%

-

89%

89%

89%

90%

Assembly

Slit/Decker

90%

90%

93%

93%

93%

95%

99%

99%

99%

99%

Test

Filter Wheel

83%

83%

95%

95%

95%

95%

96%

96%

96%

96%

Test

Grating Turret

85%

86%

89%

97%

98%

-

98%

98%

98%

100%

Test

Prism Turret

76%

85%

92%

98%

98%

-

95%

95%

95%

96%

Test

Motor Drives

   -   

  -

  -

  -

  -

  -

  -

-

-

-

Complete


Benches: (98% complete overall).  Benches are complete.  The Collimator is in final assembly.

 

Jun

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Status

Post-Slit

77%

88%

94%

99%

100%

   -

   -

-

-

-

Complete

OIWFS

86%

87%

89%

99%

100%

   -

   -

-

-

-

Complete

Collimator

62%

64%

77%

95%

-

-

95%

95%

95%

95%

Assembly

Pre-Slit

83%

87%

91%

99%

100%

   -

   -

-

-

-

Complete


Fixed Assemblies
: (91% complete overall).   The Radiation Shields are the pacing items in fixed assemblies.

 

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Status

Entrance Window

    -

    -

    -

    -

    -

    -

    -

-

-

-

Complete

Detector Mount

68%

79%

79%

97%

97%

-

96%

100%

-

-

Complete

Cryo Cooler

24%

49%

51%

59%

59%

70%

88%

89%

87%

90%

Assembly

Molecular Sieve

 

 

 

 

 

45%

100%

-

-

-

Complete

Thermal Distribution Assembly

 

 

12%

26%

-

-

52%

75%

75%

75%

Assembly

Bulkhead Rad Shield

 

 

1%

5%

9%

53%

100%

-

-

-

Task closed

LN2 Pre-Cool

84%

89%

91%

91%

91%

-

79%

83%

83%

87%

Assembly

Optical Bench Gimbal Mt.

45%

85%

95%

100%

    -

    -

    -

-

-

-

Complete

Bulkhead Assembly

55%

64%

74%

75%

90%

98%

100%

-

-

-

Complete

Passive Rad Shield

7%

10%

10%

10%

16%

42%

41%

74%

83%

98%

Assembly

Active Rad Shield

 

 

18%

18%

30%

42%

15%

39%

56%

76%

Fab

Front Dewar Shell

37%

38%

66%

70%

88%

100%

  -

-

-

-

Complete

Rear Dewar Shell

26%

   -

57%

61%

82%

100%

  -

-

-

-

Complete

Vertical Inst Frame

  -

  -

14%

77%

84%

92%

99%

100%

-

-

Complete

Horizontal Inst Frame

8%

8%

15%

57%

57%

100%

  -

-

-

-

Complete

Dewar Mount Truss

47%

47%

47%

47%

73%

-

84%

85%

100%

100%

Complete

Thermal Enclosure Mount

53%

53%

58%

70%

89%

96%

100%

-

-

-

Complete

Handling Fixtures

68%

68%

100%

100%

  -

  -

  -

-

-

-

Complete

Ballast Weights

 

 

 

75%

83%

100%

  -

-

-

-

Complete

 

   Electronics: (89% complete overall).

 

 

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Status

Component Controller TE

   -

90%

86%

86%

-

72%

72%

72%

72%

 

 

VME Crate

   -

  -

  -

  -

-

  -

-

 

-

Complete

 

Motor Drive/Cryo Cooler Crate

   -

  -

  -

  -

-

  -

-

 

-

Complete

 

Internal Cabling and Connectors

98%

98%

98%

98%

100%

-

-

 

-

Complete

 

Ancillary Cage Crate

98%

98%

98%

98%

100%

-

-

 

-

Complete

 

IfA Electronics Box

    -

30%

30%

30%

30%

30%

33%

33%

33%

In check out

 

Bench Thermal Controller Crate

98%

98%

98%

98%

70%

100%

-

-

-

Complete

External Cabling (Dewar to TE)

23%

23%

23%

23%

23%

23%

36%

36%

36%

 

The Dewar Warm-up Controller

37%

37%

37%

37%

-

59%

87%

100%

-

Complete

Dewar Electronics

   -

95%

95%

95%

95%

60%

60%

60%

60%

 

 

Dewar Cold Station PCB’s

80%

80%

80%

80%

80%

80%

80%

80%

80%

Ready for install and fit check

 

Dewar Internal Cabling

   -

96%

96%

96%

-

58%

58%

58%

58%

On Hold – waiting for dewar

Documentation

   -

95%

95%

95%

95%

95%

95%

95%

95%

 

Software Test Fixture

 

100%

-

-

-

-

-

-

-

Complete

Array Controller Upgrade

 

 

 

 

 

100%

-

-

-

Complete


 
Software Development:
(86% complete overall).

The areas in work include testing software with the electronics crates, working on the EPICS software and on the OIWFS software. 

 

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Components Controller Software

91%

   -

91%

94%

94%

94%

85%

86%

86%

86%

Test & DeBug

50%

   -

50%

75%

75%

75%

95%

100%

-

-

EPICS Software

75%

   -

82%

82%

82%

-

96%

99%

99%

99%

 

  

Alignment and Integration: (27% complete overall)

 

Feb

Mar

Telescope Simulator

69%

69%

I.    Dewar and Structure

-

-

II.   Mechanical Integration

-

-

III. Warm Tests

-

-

IV.  Cold Tests

-

-


 
Deliverables: (47% complete overall)


Work in this area has focused on the preparation test plans for acceptance testing.

 

Dec

Jan

Feb

Mar

Instrument Hardware

-

-

-

-

Training

-

-

-

-

Test plans

46%

99%

99%

99%

Manuals

-

-

2%

15%

As-Built Fabrication Drawings

-

-

-

-


 
Procurement:
(93% complete overall).

 

July

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Optics

   -

89%

86%

86%

86%

86%

90%

90%

98%

 

 

           Problems / Solutions 

Radiation Shields remain the pacing item on the project.  Cleaning and testing mechanisms is also a high priority item.

             Key Personnel

 

No Changes

 

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360