PROGRESS REPORT 

January 23 – February 23, 2001

 

           Accomplishments / Status

 

Summary:  Overall, 52% of the work from the Restart Review to delivery has been completed. All mechanisms have been designed (except for one camera barrel) and are either in drafting or fabrication.  All benches are in fabrication.  All optics from RMI have been received and the rest are either on order or out for bid.  Work has started on the fixed assemblies, the main focus being on the Bulkhead Assembly and its associated components.  The first round of flexure testing for rotating mechanisms has been successfully completed and will be repeated using lubricated bearings this month.  Results will be presented at the upcoming Mid-Fabrication Review.  The loss of a design drafting technician has caused some rescheduling of design and fabrication activities, but no slip in the start of integration is evident as yet.

 

Next Milestone: The next major project milestones are the Mid-Fabrication Review and Quarterly Review, both on March 7th.

 

Earned Value:     

 

                                BCWS    $ 2,049,349                                SPI        0.75

                                BCWP    $ 1,543,495                                CPI        0.89

                                ACWP    $ 1,739,549

 

Project Management: (51% complete)

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. Work is being done to prepare for integration later this year.  The August 2002 scheduled delivery date of the GNIRS instrument has not changed.

 

Systems Engineering: (100% of planned work)

The main focus has been flexure testing to verify the rotary mechanism designs.  These tests were successful and will be repeated later this month using bearings impregnated with lubricant.

 

Mechanical Design, Fabrication, Assembly and Test: (49% overall)

The major activity in this work package has been completion of all mechanism designs, bench fabrication, and starting work on fixed assemblies.  The next major item in design will be the Bulkhead Assembly and its associated component hardware.  The Passive Compensator Assembly will also receive high priority.

 

Mechanisms: (63% complete).

Mechanism overall completion summary:

 

                Camera                                   69%

                Focus                                     24%

                Environmental Cover           97%

                Acquisition Mirror               58%

                Slit Decker                            66%

                Filter Wheel                        71%

                Grating Turret                     42%

                Prism Turret                         48%

                Motor Drives                        90%

 

Detailed status:

                                Camera top Assembly:         97%

                                Short Red Camera:                57% complete, fabrication 75% complete

                                Short Blue camera:                51% complete, ready for fabrication

                                Long Red Camera:                72% complete, 2D drafting 24% complete

                                Long Blue Camera:                6% complete, 3D design 30% complete

                                Camera drive spindle Hub:  88% complete, fabrication 79% complete

Focus mechanism:                                Ready for 2D design.

Environmental cover assembly:          In test.

Acquisition mirror mechanism:           Fabrication 75% complete.

Slit-Decker mechanism:                        Fabrication 65% complete.

Filter wheel mechanism:                       Fabrication 65% complete.

Grating turret mechanism:                    2D detailing 30% complete, fabrication is 10% complete.

Prism turret mechanism:                       Fabrication 70% complete.

Motor drive assemblies:                      Assembly 75% complete.

 

Benches: (52% complete overall).

The Post-Slit bench is 56% complete overall and is in fabrication.

The OIWFS bench is complete.

The Collimator Assembly is 24% complete.

The Housing is 32% complete, ready to begin fabrication.

The Passive Compensator Assembly is 22% complete and is in 3D design.

The Pre-Slit bench consists of the POM and Offner assembly, and is 44% complete overall.

The POM is 58% complete with fabrication at 75%. 

The Offner is 35% complete with fabrication at 75% complete.

 

Fixed Assemblies: (14% complete overall).

Entrance Window Assembly is 96% complete and ready for Assembly/Test.

Detector Mount Assembly is 48% complete and ready for 2D design detail.

 LN2 Pre-Cool Assembly is 4% complete with 3D design 20% complete.

Optical Bench Gimbal Mount Assembly is 53% complete and ready for fabrication.

Bulkhead Assembly is 11% complete with 3D design 25% complete.

Front Dewar Shell is 26% complete with 3D design 76% complete.

Rear Dewar Shell is 6% complete with 3D design 25% complete.

The Vertical Installation Frame Assembly is 5% complete with 3D design 50% complete.

The Horizontal Frame Assembly is 1% complete with 3D design 25% complete.

The Dewar Mount Truss Assembly is 12% complete with 3D design 90% complete.

The Thermal Enclosure Mount Assembly is 2% complete with 3D design 10% complete.

The Handling Fixtures are 30% complete and ready for fabrication.

 

Electronics: (63% complete overall)

The Component Controller Thermal Enclosure is 51% complete:

VME Crate is 92% is complete and being used for Software test. 

Motor Drive/Cryohead Cooler Cage Crate is 62% complete.

Internal Cabling and Connectors is 12% complete.

Ancillary Cage Crate is 26% complete.

IFA Electronics Box interface schematics are 100% complete.

 

External Cabling (Dewar to TE) is 23% complete.

The Dewar Warm-up Controller is 37% complete.

The Dewar Cold Station PCB’s are 60% complete.

The Dewar Internal Connectors and Cabling schematics are complete.

 

All electronics parts are either in house or on order.  The design work is essentially complete and the main activity is fabrication.

 

Software Development: (49% complete overall).

The Components Controller Software is 67% complete.

The Lab Support Software is 6% complete.

The Epics Software is 60% complete. 

 

The next software activity is to test motor drive and mechanism status and position sensing code using the actual electronics VME crate.  Epics software is far ahead of schedule.

 

Procurement: (54% complete overall).

Optics procurement is 71% complete overall. 

 

                The RMI optics order is complete and all lenses received.

                All Pupil Viewer lenses have been received.

                The Janos four BaF2 lenses are 8% complete.

Grating replicas have been ordered.

Prism bids have been received and are being reviewed.

Bids for the Wollaston Prisms are in process.

 
The Major activities in this Work Package included inspecting optics at RMI, obtaining quotes for the prisms and monitoring vendor fabrication.   Quotes for a clean room tent have also been received and are being reviewed.

 

            Problems / Solutions.

 The OIWFS component late delivery will impact the project.  We have no information on when these parts will be provided.

 

The shortage of two Instrument makers has resulted in using outside vendors for more work than originally planned.  This will result in higher capital expenditures overall.

 

            Key Personnel

 

Rick Robles, Tech Associate Designer, has left the project.

 

 

 

   

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360