
GNIRS
PROGRESS REPORT
November 24 –
December 21, 2001
Accomplishments / Status
Summary:
85% of the work from the Restart Review to delivery has been completed.
Any differences in % complete shown in the detail sections of this report
are due to the rescheduling tasks because of delays in mechanism testing and
Radiation Shield design and fabrication. The
net effect has been to slip delivery of the instrument into late October 2002.
This
review period included the Thanksgiving and Christmas holidays and end-of-year
staff vacations. Progress was made
on mechanism testing, radiation shield design, Pre-Slit bench optics
installation and alignment, grating turret and camera turret flexure testing,
and Camera Barrel assembly.
The
Radiation Shield design is proceeding but taking much longer than anticipated.
This work should be complete and into fabrication by mid-January.
Mechanism testing is also taking longer than planned and will delay bench
integration into the Bulkhead Assembly until late February.
Mechanism work in process includes flexure testing of the Camera assembly
and the Grating Turret Assembly. Final
wiring of the Slit-Decker and Filter Wheel assemblies is completed.
These units are ready and staged for cold testing.
The
Bulkhead Assembly, complete with Front and Rear Dewar Shells and mounting truss,
has been received. Fit checks on
external trusses, including the Thermal Enclosures and trusses, are complete.
The final truss fabrication is complete except for painting, which is in
process.
The integration of the WFS components onto the bench is complete, alignment is complete and wiring is complete. Software checkout is proceeding. Installation of the actual HgCdTe detector and prism is still pending.
Change
orders for delivery of GNIRS to Chile, including Testing, Training, and
Commissioning, and for the Differential Pressure Switch, are still in process.
Work on the Differential Pressure Switch is complete.
The test plan for Acceptance Testing, Delivery to Chile, Training and
Commissioning has been submitted to Gemini for approval
Next Milestone: The next major project
milestone is the completion of Radiation Shield design by January 15th.
Earned Value:
|
|
May |
June |
July |
August |
September |
October |
November |
December |
|
BCWS |
$2,732,977 |
$2,929,722 |
$2,976,073 |
$3,030,916 |
$3,085,811 |
$3,145,000 |
$3,192,781 |
$3,236,748 |
|
BCWP |
$1,912,351 |
$2,119,911 |
$2,182,434 |
$2,357,289 |
$2,526,319 |
$2,573,084 |
$2,617,408 |
$2,884,471 |
|
ACWP |
$2,031,750 |
$2,343,546 |
$2,392,603 |
$2,603,604 |
$2,762,963 |
$2,938,004 |
$3,122,731 |
$3,313,415 |
|
SPI |
0.70 |
0.72 |
0.73 |
0.78 |
0.82 |
0.82 |
0.82 |
0.89 |
|
CPI |
0.94 |
0.90 |
0.91 |
0.91 |
0.91 |
0.88 |
0.84 |
0.87 |
This table reflects planned and actual charges to the project as of December 21,
2001. We have spent $1,293,183 in
capital to date.
Project Management: (79% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery date of the GNIRS instrument is October 24, 2002, due to the delays in finishing the Radiation Shields and Mechanism testing.
Systems Engineering: (100% of planned work)
The
main focus has been Camera and Grating and Prism Turret mechanism assembly and
warm test and support of design updates.
Mechanical Design, Fabrication, Assembly and
Test: (93% overall)
The
major activity in this work package has been fit checks of components on the
Bulkhead Assembly, 3D and 2D design of radiation shields, and fabrication.
Mechanisms:
(97% complete overall).
|
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Status
|
|
Camera
|
77%
|
78%
|
88% |
90% |
91% |
91% |
91% |
92% |
98% |
99% |
Test
|
|
Focus
|
24%
|
30%
|
48% |
59% |
59% |
60% |
67% |
|
73% |
89% |
Assembly |
|
Environmental
Cover |
99%
|
99%
|
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
on-hold |
|
Acquisition
Mirror |
68%
|
72%
|
75% |
75%
|
75% |
76% |
93% |
93% |
- |
89% |
Assembly |
|
Slit/Decker
|
77%
|
83%
|
85% |
90%
|
90% |
93% |
93% |
93% |
95% |
99% |
Test |
|
Filter
Wheel |
70%
|
73%
|
78% |
83%
|
83% |
95% |
95% |
95% |
95% |
96% |
Test |
|
Grating
Turret |
51%
|
72%
|
83% |
85%
|
86% |
89% |
97% |
98% |
- |
98% |
Test |
|
Prism
Turret |
47%
|
50%
|
56% |
76%
|
85% |
92% |
98% |
98% |
- |
95% |
Test |
|
Motor
Drives |
90%
|
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
Benches: (98% complete overall). Benches
are complete. The Collimator has a
few parts still in fabrication, and is nearly ready for assembly.
Wiring of the benches will be done in Integration.
|
|
Mar
|
Apr |
May |
Jun |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Status |
|
Post-Slit |
65% |
70% |
- |
77% |
88% |
94% |
99% |
100% |
- |
- |
Complete |
|
OIWFS |
67% |
79% |
- |
86% |
87% |
89% |
99% |
100% |
- |
- |
Complete |
|
Collimator
|
29%
|
29%
|
46% |
62% |
64% |
77% |
95% |
- |
- |
95% |
Assembly |
|
Pre-Slit
|
62%
|
70%
|
81% |
83%
|
87% |
91% |
99% |
100% |
- |
- |
Complete |
Fixed Assemblies: (81% complete overall).
The Radiation Shields are the pacing items in fixed assemblies.
|
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Status
|
|
Entrance
Window |
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
49%
|
60%
|
67% |
68%
|
79% |
79% |
97% |
97% |
- |
96% |
Waiting
for wiring |
|
Cryo
Cooler |
16%
|
16% |
16% |
24%
|
49% |
51% |
59% |
59% |
70% |
88% |
Fab |
|
Molecular
Sieve |
|
|
|
|
|
|
|
|
45% |
100% |
Complete |
|
Thermal
Distribution Assembly |
|
|
|
|
|
12% |
26% |
- |
- |
52% |
Fab |
|
Bulkhead
Rad Shield |
This
task closed – effort renamed to Passive and Active Rad Shields |
Task
closed |
|||||||||
|
LN2
Pre-Cool |
4%
|
17%
|
17% |
84%
|
89% |
91% |
91% |
91% |
- |
79% |
Fab |
|
Optical
Bench Gimbal Mt. |
53%
|
54%
|
56% |
45%
|
85% |
95% |
100% |
- |
- |
- |
Complete |
|
Bulkhead
Assembly |
24%
|
42%
|
52% |
55%
|
64% |
74% |
75% |
90% |
98% |
100% |
Complete |
|
Passive
Rad Shield |
Task
renamed -changed from Front Rad Shield assy |
41% |
3D/2D
design |
||||||||
|
Active
Rad Shield |
Task
renamed -changed from Rear Rad Shield assy |
15% |
3D/2D
design |
||||||||
|
Front
Dewar Shell |
34%
|
37%
|
37% |
37%
|
38% |
66% |
70% |
88% |
100% |
- |
Complete |
|
Rear
Dewar Shell |
8%
|
21%
|
21% |
26%
|
- |
57% |
61% |
82% |
100% |
- |
Complete |
|
Vertical
Inst Frame |
6%
|
6%
|
11% |
- |
- |
14% |
77% |
84% |
92% |
99% |
Paint |
|
Horizontal
Inst Frame |
- |
- |
- |
8%
|
8% |
15% |
57% |
57% |
100% |
- |
Complete |
|
Dewar
Mount Truss |
12%
|
12%
|
13% |
47%
|
47% |
47% |
47% |
73% |
- |
84% |
Fab
– task reschduled |
|
Thermal
Enclosure Mount |
7%
|
10%
|
44% |
53% |
53% |
58% |
70% |
89% |
96% |
100% |
Complete |
|
Handling
Fixtures |
58%
|
- |
68% |
68%
|
68% |
100% |
100% |
- |
- |
- |
Complete |
|
Ballast
Weights |
|
|
|
|
|
|
75% |
83% |
100% |
- |
Complete |
Electronics: (89% complete overall).
Instrument controller is complete and tested in the environmental chamber. At this point only the IFA cage and bench (SDSU) box on the
dewar remain to be tested. Tasks
that show % complete decreases are
an attribute of MS project due to rescheduling.
|
|
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Status
|
|
Component
Controller TE |
71%
|
75% |
66% |
- |
90% |
86% |
86% |
- |
72% |
|
|
|
|
VME
Crate |
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
16%
|
18% |
90%
|
98% |
98% |
98% |
98% |
100% |
- |
Complete |
|
|
Ancillary
Cage Crate |
26%
|
59% |
63%
|
98% |
98% |
98% |
98% |
100% |
- |
Complete |
|
|
IfA
Electronics Box |
- |
- |
- |
- |
30% |
30% |
30% |
30% |
30% |
In
check out |
|
|
Bench
Thermal Controller Crate |
61%
|
68% |
94% |
98% |
98% |
98% |
98% |
70% |
100% |
Complete |
|
External
Cabling (Dewar to TE) |
23%
|
23% |
23% |
23% |
23% |
23% |
23% |
23% |
23% |
|
|
|
The
Dewar Warm-up Controller |
37%
|
37% |
37% |
37% |
37% |
37% |
37% |
- |
59% |
Task rescheduled |
|
|
Dewar
Electronics |
- |
- |
95% |
- |
95% |
95% |
95% |
95% |
60% |
|
|
|
|
Dewar
Cold Station PCB’s |
50%
|
60% |
80%
|
80% |
80% |
80% |
80% |
80% |
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Cabling |
72%
|
72% |
96% |
- |
96% |
96% |
96% |
- |
58% |
On
Hold – waiting for dewar |
|
Documentation
|
50%
|
50% |
85% |
- |
95% |
95% |
95% |
95% |
95% |
|
|
|
Software
Test Fixture |
|
|
|
|
100% |
- |
- |
- |
- |
Complete |
|
|
Array
Controller Upgrade |
|
|
|
|
|
|
|
|
100% |
Complete |
|
Software Development: (82% complete overall).
The
areas in work include testing software with the electronics crates, working on
the EPICS software and on the OIWFS software.
Resources assigned to the software task are also working on the Gemini
Array Controller. Task percentage
complete changes shown are due to rescheduling.
|
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
|
Components
Controller Software |
91%
|
91%
|
91% |
91% |
- |
91% |
94% |
94% |
94% |
85% |
|
Test
& DeBug |
- |
- |
- |
50% |
- |
50% |
75% |
75% |
75% |
95% |
|
EPICS
Software |
69%
|
69%
|
69% |
75% |
- |
82% |
82% |
82% |
- |
96% |
Alignment and Integration: (14% complete overall)
The
area has been the optical and mechanical design of the Telescope Simulator.
The Simulator optical design is complete.
|
|
Dec
|
|
Telescope
Simulator |
46% |
|
I.
Dewar and Structure |
- |
|
II.
Mechanical Integration |
- |
|
III.
Warm Tests |
- |
|
IV.
Cold Tests |
- |
Deliverables: (21% complete overall)
Work
in this area has focused on the preparation test plans for acceptance testing.
|
|
Dec
|
|
Instrument
Hardware |
- |
|
Training
|
- |
|
Test
plans |
46% |
|
Manuals |
- |
|
As-Built
Fabrication Drawings |
- |
Procurement: (85%
complete overall).
The
major activities in this Work Package included monitoring vendor mechanical and
optical component assembly fabrication.
|
|
Mar
|
Apr |
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Notes |
|
Optics |
67% |
71% |
73% |
79% |
- |
89% |
86% |
86% |
86% |
86% |
|
|
RMI optics |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Flat Mirrors |
10% |
50% |
50% |
50% |
- |
99% |
99% |
99% |
100% |
- |
Complete |
|
Pupil Viewer |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
50%
|
93%
|
75% |
75% |
- |
75% |
90% |
90% |
99% |
100% |
Complete |
|
Grating replicas |
23% |
50% |
83% |
86% |
- |
100% |
100% |
- |
- |
- |
Complete |
|
Prisms |
13% |
13% |
23% |
74% |
- |
95% |
100% |
- |
- |
- |
Complete |
|
Wollaston Prisms |
- |
0% |
10% |
40% |
- |
95% |
100% |
- |
- |
- |
Complete |
The only optics
left to procure are for the Telescope Simulator, which is still in design.
Problems /
Solutions
1. Radiation Shields remain the pacing item on the project. This task is much more difficult that originally estimated, and progress has been slow due to the holidays and staff vacations at the end of the calendar year. Fabrication time after design completion is estimated to be 4-6 weeks, which will put the integration of the bench assemblies into the bulkhead assembly into March. This may impact the scheduled delivery date of September 22. We have a vendor standing by to do the fabrication on a high priority basis, which may shorten the anticipated fabrication time. We are watching this carefully and will report any further slip or gain as it occurs.
2. There are two Change Orders outstanding which need to be completed and submitted to Gemini:
·
Change
Order for delivery of GNIRS to Chile
· Change Order revision for the Differential Pressure Switch
These CO’s were scheduled to be completed in December, but will now be submitted to the USGPO by the end of January 2002.
Key
Personnel
Two
changes in personnel have taken place since the last monthly report:
Ed
Hileman, Sr. Mechanical Engineer, has been assigned to another NOAO project.
Ed will remain available to GNIRS on an as-needed basis.
Dale
Circle, Sr. Mechanical Designer, has left the project.
These
staffing changes were planned and do not impact the work left in the
design-drafting area.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360