GNIRS PROGRESS REPORT

November 24 – December 21, 2001

           Accomplishments / Status

  Summary:  85% of the work from the Restart Review to delivery has been completed.  Any differences in % complete shown in the detail sections of this report are due to the rescheduling tasks because of delays in mechanism testing and Radiation Shield design and fabrication.  The net effect has been to slip delivery of the instrument into late October 2002.

This review period included the Thanksgiving and Christmas holidays and end-of-year staff vacations.  Progress was made on mechanism testing, radiation shield design, Pre-Slit bench optics installation and alignment, grating turret and camera turret flexure testing, and Camera Barrel assembly.

The Radiation Shield design is proceeding but taking much longer than anticipated.  This work should be complete and into fabrication by mid-January.  Mechanism testing is also taking longer than planned and will delay bench integration into the Bulkhead Assembly until late February.  Mechanism work in process includes flexure testing of the Camera assembly and the Grating Turret Assembly.  Final wiring of the Slit-Decker and Filter Wheel assemblies is completed.  These units are ready and staged for cold testing.

The Bulkhead Assembly, complete with Front and Rear Dewar Shells and mounting truss, has been received.  Fit checks on external trusses, including the Thermal Enclosures and trusses, are complete.  The final truss fabrication is complete except for painting, which is in process.

The integration of the WFS components onto the bench is complete, alignment is complete and wiring is complete.  Software checkout is proceeding.  Installation of the actual HgCdTe detector and prism is still pending.

Change orders for delivery of GNIRS to Chile, including Testing, Training, and Commissioning, and for the Differential Pressure Switch, are still in process.  Work on the Differential Pressure Switch is complete.  The test plan for Acceptance Testing, Delivery to Chile, Training and Commissioning has been submitted to Gemini for approval

  Next Milestone: The next major project milestone is the completion of Radiation Shield design by January 15th.

  Earned Value:

 

May

June

July

August

September

October

November

December

BCWS

$2,732,977

$2,929,722

$2,976,073

$3,030,916

$3,085,811

$3,145,000

$3,192,781

$3,236,748

BCWP

$1,912,351

$2,119,911

$2,182,434

$2,357,289

$2,526,319

$2,573,084

$2,617,408

$2,884,471

ACWP

$2,031,750

$2,343,546

$2,392,603

$2,603,604

$2,762,963

$2,938,004

$3,122,731

$3,313,415

SPI

0.70

0.72

0.73

0.78

0.82

0.82

0.82

0.89

CPI

0.94

0.90

0.91

0.91

0.91

0.88

0.84

0.87


This table reflects planned and actual charges to the project as of December 21, 2001.  We have spent $1,293,183 in capital to date.

  Project Management: (79% complete)

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery date of the GNIRS instrument is October 24, 2002, due to the delays in finishing the Radiation Shields and Mechanism testing.

  Systems Engineering: (100% of planned work)

The main focus has been Camera and Grating and Prism Turret mechanism assembly and warm test and support of design updates.

  Mechanical Design, Fabrication, Assembly and Test: (93% overall)

The major activity in this work package has been fit checks of components on the Bulkhead Assembly, 3D and 2D design of radiation shields, and fabrication.

Mechanisms: (97% complete overall).

 

Mar

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Status

Camera

77%

78%

88%

90%

91%

91%

91%

92%

98%

99%

Test

Focus

24%

30%

48%

59%

59%

60%

67%

 

73%

89%

Assembly

Environmental Cover

99%

99%

99%

99%

99%

99%

99%

99%

99%

99%

 on-hold

Acquisition Mirror

68%

72%

75%

75%

75%

76%

93%

93%

-

89%

Assembly

Slit/Decker

77%

83%

85%

90%

90%

93%

93%

93%

95%

99%

Test

Filter Wheel

70%

73%

78%

83%

83%

95%

95%

95%

95%

96%

Test

Grating Turret

51%

72%

83%

85%

86%

89%

97%

98%

-

98%

Test

Prism Turret

47%

50%

56%

76%

85%

92%

98%

98%

-

95%

Test

Motor Drives

90%

100%

   -   

   -   

  -

  -

  -

  -

  -

  -

Complete


Benches:
(98% complete overall).  Benches are complete.  The Collimator has a few parts still in fabrication, and is nearly ready for assembly.  Wiring of the benches will be done in Integration.

 

Mar

Apr

May

Jun

July

Aug

Sept

Oct

Nov

Dec

Status

Post-Slit

65%

70%

   -

77%

88%

94%

99%

100%

   -

   -

Complete

OIWFS

67%

79%

   -

86%

87%

89%

99%

100%

   -

   -

Complete

Collimator

29%

29%

46%

62%

64%

77%

95%

-

-

95%

Assembly

Pre-Slit

62%

70%

81%

83%

87%

91%

99%

100%

   -

   -

Complete


Fixed Assemblies
: (81% complete overall).   The Radiation Shields are the pacing items in fixed assemblies.

 

Mar

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Status

Entrance Window

100%

   -

    -

    -

    -

    -

    -

    -

    -

    -

Complete

Detector Mount

49%

60%

67%

68%

79%

79%

97%

97%

-

96%

Waiting for wiring

Cryo Cooler

16%

16%

16%

24%

49%

51%

59%

59%

70%

88%

Fab

Molecular Sieve

 

 

 

 

 

 

 

 

45%

100%

Complete

Thermal Distribution Assembly

 

 

 

 

 

12%

26%

-

-

52%

Fab

Bulkhead Rad Shield

This task closed – effort renamed to Passive and Active Rad Shields

Task closed

LN2 Pre-Cool

4%

17%

17%

84%

89%

91%

91%

91%

-

79%

Fab

Optical Bench Gimbal Mt.

53%

54%

56%

45%

85%

95%

100%

    -

    -

    -

Complete

Bulkhead Assembly

24%

42%

52%

55%

64%

74%

75%

90%

98%

100%

Complete

Passive Rad Shield

 Task renamed -changed from Front Rad Shield assy

41%

 3D/2D design

Active Rad Shield

Task renamed -changed from Rear Rad Shield assy

15%

3D/2D design

Front Dewar Shell

34%

37%

37%

37%

38%

66%

70%

88%

100%

  -

Complete

Rear Dewar Shell

8%

21%

21%

26%

   -

57%

61%

82%

100%

  -

Complete

Vertical Inst Frame

6%

6%

11%

  -

  -

14%

77%

84%

92%

99%

Paint

Horizontal Inst Frame

   -

    -

    -

8%

8%

15%

57%

57%

100%

  -

Complete

Dewar Mount Truss

12%

12%

13%

47%

47%

47%

47%

73%

-

84%

Fab – task reschduled

Thermal Enclosure Mount

7%

 10%

44%

53%

53%

58%

70%

89%

96%

100%

Complete

Handling Fixtures

58%

   -

68%

68%

68%

100%

100%

  -

  -

  -

Complete

Ballast Weights

 

 

 

 

 

 

75%

83%

100%

  -

Complete

 

   Electronics: (89% complete overall).  
Instrument controller is complete and tested in the environmental chamber.  At this point only the IFA cage and bench (SDSU) box on the dewar remain to be tested.  Tasks that show  % complete decreases are an attribute of MS project due to rescheduling.

 

 

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Status

Component Controller TE

71%

75%

66%

   -

90%

86%

86%

-

72%

 

 

VME Crate

100%

   -

   -

   -

  -

  -

  -

-

  -

SW testing

 

Motor Drive/Cryo Cooler Crate

100%

   -

   -

   -

  -

  -

  -

-

  -

SW testing

 

Internal Cabling and Connectors

16%

18%

90%

98%

98%

98%

98%

100%

-

Complete

 

Ancillary Cage Crate

26%

59%

63%

98%

98%

98%

98%

100%

-

Complete

 

IfA Electronics Box

   -

  -

  -

    -

30%

30%

30%

30%

30%

In check out

 

Bench Thermal Controller Crate

61%

68%

94%

98%

98%

98%

98%

70%

100%

Complete

External Cabling (Dewar to TE)

23%

23%

23%

23%

23%

23%

23%

23%

23%

 

The Dewar Warm-up Controller

37%

37%

37%

37%

37%

37%

37%

-

59%

Task rescheduled

Dewar Electronics

   -

  

95%

   -

95%

95%

95%

95%

60%

 

 

Dewar Cold Station PCB’s

50%

60%

80%

80%

80%

80%

80%

80%

80%

Ready for install and fit check

 

Dewar Internal Cabling

72%

72%

96%

   -

96%

96%

96%

-

58%

On Hold – waiting for dewar

Documentation

50%

50%

85%

   -

95%

95%

95%

95%

95%

 

Software Test Fixture

 

 

 

 

100%

-

-

-

-

Complete

Array Controller Upgrade

 

 

 

 

 

 

 

 

100%

Complete

  
Software Development:
(82% complete overall).

The areas in work include testing software with the electronics crates, working on the EPICS software and on the OIWFS software.  Resources assigned to the software task are also working on the Gemini Array Controller.  Task percentage complete changes shown are due to rescheduling.

 

Mar

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Components Controller Software

91%

91%

91%

91%

   -

91%

94%

94%

94%

85%

Test & DeBug

   -

   -

   -

50%

   -

50%

75%

75%

75%

95%

EPICS Software

69%

69% 

69%

75%

   -

82%

82%

82%

-

96%

 

   Alignment and Integration: (14% complete overall)

The area has been the optical and mechanical design of the Telescope Simulator.  The Simulator optical design is complete.

 

Dec

Telescope Simulator

46%

I.    Dewar and Structure

-

II.   Mechanical Integration

-

III. Warm Tests

-

IV.  Cold Tests

-

 
 
Deliverables: (21% complete overall)

Work in this area has focused on the preparation test plans for acceptance testing.

 

Dec

Instrument Hardware

-

Training

-

Test plans

46%

Manuals

-

As-Built Fabrication Drawings

-


 
Procurement:
(85% complete overall).

The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication. 

 

Mar

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Notes

Optics

67%

71%

73%

79%

   -

89%

86%

86%

86%

86%

 

RMI optics

   -

   -

   -

   -

   -

   -

   -

   -

   -

   -

Complete

Flat Mirrors

10%

50%

50%

50%

   -

99%

99%

99%

100%

   -

Complete

Pupil Viewer

   -

   -

   -

   -

   -

  -

  -

  -

  -

  -

Complete

BaF2 lenses

50%

93%

75%

75%

   -

75%

90%

90%

99%

100%

Complete

Grating replicas

23%

50%

83%

86%

   -

100%

100%

   -

   -

   -

Complete

Prisms

13%

13%

23%

74%

   -

95%

100%

   -

   -

   -

Complete

Wollaston Prisms

   -

0%

10%

40%

   -

95%

100%

   -

   -

   -

Complete

 

The only optics left to procure are for the Telescope Simulator, which is still in design.

  

           Problems / Solutions

1.  Radiation Shields remain the pacing item on the project.  This task is much more difficult that originally estimated, and progress has been slow due to the holidays and staff vacations at the end of the calendar year.  Fabrication time after design completion is estimated to be 4-6 weeks, which will put the integration of the bench assemblies into the bulkhead assembly into March.  This may impact the scheduled delivery date of September 22.  We have a vendor standing by to do the fabrication on a high priority basis, which may shorten the anticipated fabrication time.  We are watching this carefully and will report any further slip or gain as it occurs.

2.  There are two Change Orders outstanding which need to be completed and submitted to Gemini:

·        Change Order for delivery of GNIRS to Chile

·        Change Order revision for the Differential Pressure Switch

These CO’s were scheduled to be completed in December, but will now be submitted to the USGPO by the end of January 2002.

             Key Personnel

 

Two changes in personnel have taken place since the last monthly report:

 

 

These staffing changes were planned and do not impact the work left in the design-drafting area.

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360