PROGRESS REPORT 

 October 24 – November 22, 2000

 

           Accomplishments / Status

 

Summary:  Overall, 40% of the work from the Restart Review to delivery has been completed. The primary focus of this reporting period has been 1) solid modeling and 2D detailing of the Post-Slit Optical Bench; 2) fabrication of the OIWFS and Pre-Slit optical benches; 3) 2D detailing and fabrication of the Slit/Decker mechanisms; 4) 2D detailing of the Prism, Grating and Camera Turrets and 5) 2D detailing and fabrication of the Filter Wheel mechanism.

 

Next Milestone: The next major project milestone is the ordering of all remaining optics by December 16th.

 

Earned Value:     

 

                                BCWS    $ 1,431,064                                SPI        0.75

                                BCWP    $ 1,074,179                                CPI        1.16

                                ACWP    $    928,176

 

Project Management: (39% completed) The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning.  The scheduled delivery date of the completed GNIRS instrument has not changed. 

 

Systems Engineering: (100% of planned work) The activity in work included 1) structural analysis, and 2) systems engineering input to the design process.  The structural analysis is complete and the results show no need for active compensation.  Passive compensation via the collimator mount will be included in the design.  No additional structural analysis is planned except to support collimator mirror mount design. The analysis results were presented at the Quarterly Review held on November 15th. 

 

Cold Motors:  Four of 12 Phytron motors were cold tested and 3 of these failed.  All 12 motors were returned to Phytron, which is replacing all 12 motors.  We have received 4 of these new motors and are currently testing them.  If these pass, the rest of the motors will be sent from Phytron and tested.  We still have 2 spare motors on loan from Gemini that we are using to support mechanism cold testing until our own motors are available.

 

Mechanical Design: (31% overall including: Mechanisms 39%, Benches 35%, and Fixed Assemblies 7%).  Activities included optical bench solid modeling and detailing, focus mechanism design, grating turret design, prism turret design and detailing, and filter wheel detailing.

 

The prism turret 3D design is 100% complete and 2D detailing is 6% complete.

 

The grating turret 3D design is 10% complete and 2D detailing is 7% complete.

 

The focus mechanism 3D design is 90% complete.

 

The filter wheel mechanism 2D drafting is complete and released to fabrication.

 

The acquisition mirror mechanism 2D drafting is complete and released to fabrication.

 

The Post-Slit bench 3D design and 2D detailing are 95% complete.

 

Mechanical Fabrication:

 

The camera drive spindle hub fabrication is 45% complete. 

 

The filter wheel mechanism fabrication is 81% complete. 

 

The acquisition mirror mechanism fabrication is 35% complete.

 

OIWFS Bench fabrication is 60% complete. This bench is in fabrication in the NOAO Instrument Shop and should complete on December 4th.

 

The Pre-slit bench is in fabrication at a selected vendor and is 10% complete.

 

The Detector mount assembly fabrication is 74% complete.

 

The Motor Drive Assembly assembly/test is 9% complete.

 

Electronics: (42%) Activities in this work package include 1) dewar and mechanism wiring design definition; 2) array interface wiring definition; 3) cold stationing definition; 4) thermal enclosure wiring definition and 5) OIWFS electronics wiring and packaging definition.

 

The component controller thermal enclosure design is complete and a complete parts list has been prepared.  The hard-stop circuit for the mechanisms and the Phytron drivers have been designed and the schematics released.  Cable routing issues in the dewar are being addressed using a scale model of the optical bench.

 

Work on defining dewar wiring and ALADDIN array interfacing details and detailed mechanism wiring is in process.

 

The thermal enclosure wiring and assembly are in process.  Dewar and shield interface PCB’s are being fabricated at a vendor, and all connectors and boards are on order.

 

Software Development: (27%) The Components Controller Software is 42% complete, lab support software is 6% complete, and the high level Epics software is 1% complete.  The next phase is actual testing of the component controller code, which will test motor drive and mechanism status and position sensing.  Component controller software completion is waiting for completion of the electronics thermal enclosure.

 

Optics:  11 of 18 camera lenses and windows have been completed and accepted.  Only the BaF2  lenses for the short red and blue cameras remain to be fabricated.  Two lots of BaF2 material have failed thus far, and a third lot is in process.  We are also looking to other sources for these remaining lenses.

 

Grating master rulings have been completed and tested.  Grating replicas are scheduled to be ordered by December 15th.

 

7 filters were ordered through the UH consortium. Two of these failed to meet specifications and the vendor is expected to replace them.

 

Prism drawings are complete and are scheduled to be ordered by December 15th.

 

Procurement: (44%) Major activities in this Work Package included optics work at RMI, and monitoring vendor fabrication.

 

            Problems / Solutions

 The OIWFS component late delivery will impact the project next calendar year.  A cost and schedule impact change order has been submitted to Gemini.

 Completion of the RMI camera optics procurement.  Obtaining BaF2 material seems to be an industry-wide problem.  We are trying to help RMI find sources of this material, and have also sent out requests for bid to other optics manufacturers to complete the lens build in case RMI defaults.

 

            Key Personnel

 

Dale Circle, a Drafting Technician, joined the GNIRS team on October 30th.

 

 

 

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360