PROGRESS REPORT
October 20 –
November 23, 2001
Accomplishments / Status
Summary:
85% of the work from the Restart Review to delivery has been completed.
The work during this period included design of the Molecular Sieve, radiation shield design, Bulkhead Assembly and Dewar Shell fabrication and mechanism testing. The Bulkhead Assembly and Dewar Shells have been inspected, leak tested and accepted at the vendor, and are due to be shipped to NOAO on November 30th after painting. Grating and Prism Turret mechanism testing is in process. All mechanisms have completed parts fabrication.
All optics have been inspected and accepted. One camera lens is being coated and is yet to be received. Pre-Slit bench optics installation and alignment is ready to start. Camera test and alignment is ready to start.
The integration of the WFS components onto the bench is complete, and alignment is complete. Wiring and software checkout are proceeding.
Change
orders for delivery of GNIRS to Chile, including Testing, Training, and
Commissioning, and for the Differential Pressure Switch, are still in process.
Work on the Differential Pressure Switch is complete. The test plan for
Acceptance Testing, Delivery to Chile, Training and Commissioning has been
submitted to Gemini for approval.
Next Milestone: The next major project milestone is the completion of Radiation Shield design by December 3rd.
Earned Value:
| |
April |
May | June | July | August | September | October | November |
|
BCWS |
$2,565,371 |
$2,732,977 |
$2,929,722 |
$2,976,073 |
$3,030,916 |
$3,085,811 |
$3,145,000 |
$3,192,781 |
|
BCWP |
$1,804.951 |
$1,912,351 |
$2,119,911 |
$2,182,434 |
$2,357,289 |
$2,526,319 |
$2,573,084 |
$2,617,408 |
|
ACWP |
$1,915,889 |
$2,031,750 |
$2,343,546 |
$2,392,603 |
$2,603,604 |
$2,762,963 |
$2,938,004 |
$3,122,731 |
|
SPI |
0.70 |
0.70 |
0.72 |
0.73 |
0.78 |
0.82 |
0.82 |
0.82 |
|
CPI |
0.94 |
0.94 |
0.90 |
0.91 |
0.91 |
0.91 |
0.88 |
0.84 |
This table reflects planned and actual charges to the project as of October 31, 2001. NOAO has spent $1,264,118 in capital to date.
Project Management: (77% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery date of the GNIRS instrument is still September 25, 2002.
Systems Engineering: (100% of planned work)
The main focus has been Grating and Prism Turret mechanism assembly and warm test and support of design updates.
Mechanical Design, Fabrication, Assembly and Test: (93% overall)
The major activity in this work package has been a design modification to the Bulkhead assembly, 3D and 2D design of radiation shields, and fabrication.
Mechanisms: (96% complete overall). The Focus Mechanism is the only mechanism still to be assembled for warm testing. Testing is underway for the Grating and Prism turrets.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
91% |
91% |
91% |
92% |
98% |
Final
Fab/test |
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
59% |
60% |
67% |
|
|
Assembly |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
99% |
99% |
99% |
99% |
99% |
on-hold |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
75% |
76% |
93% |
93% |
95% |
Assembly/test |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
90% |
93% |
93% |
93% |
95% |
Assembly/test |
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
83% |
95% |
95% |
95% |
95% |
Ready
for test |
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
86% |
89% |
97% |
98% |
98% |
Test |
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
85% |
92% |
98% |
98% |
98% |
Test |
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
- |
- |
- |
- |
- |
Complete |
Benches: (98% complete overall). Benches are complete. The Collimator has a few parts still in fabrication, and is nearly ready for assembly. Wiring of the benches will be done in Integration.
|
|
Feb
|
Mar |
Apr |
May |
Jun |
July |
Aug |
Sept |
Oct |
Nov |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
88% |
94% |
99% |
100% |
- |
Complete |
|
OIWFS |
67% |
67% |
79% |
- |
86% |
87% |
89% |
99% |
100% |
- |
Complete |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
64% |
77% |
95% |
96% |
96% |
Fab
|
|
Pre-Slit
|
44%
|
62%
|
70%
|
81% |
83%
|
87% |
91% |
99% |
100% |
- |
Complete |
Fixed Assemblies: (80% complete overall). The Radiation Shields are the pacing items in fixed assemblies.
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
79% |
79% |
97% |
97% |
97% |
Waiting
for wiring |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
49% |
51% |
59% |
59% |
70% |
Fab |
|
Molecular
Sieve |
|
|
|
|
|
|
|
|
|
45% |
3D design |
|
Thermal
Distribution Assembly |
|
|
|
|
|
|
12% |
26% |
66% |
69% |
3D/2D Design |
|
Bulkhead
Rad Shield |
|
|
|
|
|
|
1% |
5% |
9% |
53% |
3D/2D Design |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
89% |
91% |
91% |
91% |
91% |
Fab |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
85% |
95% |
100% |
- |
- |
Complete |
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
64% |
74% |
75% |
90% |
98% |
Paint |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
10% |
10% |
10% |
16% |
42% |
3D/2D
design |
|
Rear
Rad Shield |
|
|
|
|
|
|
18% |
18% |
30% |
42% |
3D/2D design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
38% |
66% |
70% |
88% |
100% |
Complete |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
- |
57% |
61% |
82% |
100% |
Complete |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
- |
- |
14% |
77% |
84% |
92% |
Fab
(welding) |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
8% |
15% |
57% |
57% |
100% |
Complete |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
47% |
47% |
47% |
73% |
67% |
Fab |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53% |
53% |
58% |
70% |
89% |
96% |
Assembly |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
68% |
100% |
100% |
- |
- |
Complete |
|
Ballast
Weights |
|
|
|
|
|
|
|
75% |
83% |
100% |
Complete |
Electronics: (89% complete overall). The Instrument Controller is essentially complete. The OIWFS electronic components have been installed in the Thermal Enclosure and are being checked out as OIWFS integration proceeds.
|
TASK |
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Status
|
|
|
Component
Controller TE |
68%
|
71%
|
75% |
66% |
- |
90% |
86% |
86% |
92% |
|
|
|
|
VME
Crate |
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
Motor
Drive/Cryo Cooler Crate |
94%
|
100%
|
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
16%
|
16%
|
18% |
90%
|
98% |
98% |
98% |
98% |
100% |
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
59% |
63%
|
98% |
98% |
98% |
98% |
100% |
Complete |
|
|
IfA
Electronics Box |
- |
- |
- |
- |
- |
30% |
30% |
30% |
30% |
In
check out |
|
|
Bench
Thermal Controller Crate |
- |
61%
|
68% |
94% |
98% |
98% |
98% |
98% |
70% |
Complete |
|
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23% |
23% |
23% |
23% |
23% |
23% |
23% |
|
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37% |
37% |
37% |
37% |
37% |
37% |
37% |
|
|
|
Dewar
Electronics |
71%
|
- |
- |
95% |
- |
95% |
95% |
95% |
95% |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
50%
|
60% |
80%
|
80% |
80% |
80% |
80% |
80% |
Ready
for install and fit check |
|
Dewar
Internal Cabling |
72%
|
72%
|
72% |
96% |
- |
96% |
96% |
96% |
96% |
On
Hold – waiting for dewar |
|
|
Documentation
|
50%
|
50%
|
50% |
85% |
- |
95% |
95% |
95% |
95% |
|
|
Software Development: (85% complete overall).
The areas in work include testing software with the electronics crates and working on the EPICS software. Resources assigned to the software task are also working on the Gemini Array Controller.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
- |
91% |
94% |
94% |
94% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
- |
82% |
82% |
82% |
82% |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
- |
50% |
75% |
75% |
75% |
Procurement: (79% complete overall).
The major activities in this Work Package included monitoring vendor mechanical and optical component assembly fabrication.
|
|
Feb
|
Mar |
Apr |
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
- |
89% |
86% |
86% |
86% |
|
|
RMI optics |
100% |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
- |
99% |
99% |
99% |
100% |
Complete |
|
Pupil Viewer |
100% |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
- |
75% |
90% |
90% |
99% |
Coating
last lens |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
- |
100% |
100% |
- |
- |
Complete |
|
Prisms |
- |
13% |
13% |
23% |
74% |
- |
95% |
100% |
- |
- |
Complete |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
- |
95% |
100% |
- |
- |
Complete |
Problems /
Solutions
There are two Change Orders outstanding which need to be completed and submitted to Gemini:
·
Change
Order for delivery of GNIRS to Chile
· Change Order revision for the Differential Pressure Switch
These
CO’s will be completed and submitted to the USGP by mid-December, 2001.
Key
Personnel
No
changes.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.