GNIRS
PROGRESS REPORT
September 22 –
October 19, 2001
Accomplishments / Status
Summary:
82% of the work from the Restart Review to delivery has been completed.
The work during this period included hosting a Quarterly Review on October 5th. In addition to the review, significant progress was made on mechanical design of the radiation shields and the vendor fabrication of the Bulkhead Assembly and Dewar Shells. Except for the Focus Assembly, all mechanisms have completed fabrication. Grating and Prism Turret mechanism testing is underway.
An update to the Envelope Waiver, submitted to Gemini last month, has been approved.
A problem with the OIWFS Gimbal Mirror assembly has stopped work on the integration of the WFS components onto the bench. We are waiting for Gemini direction on how to proceed. Work on the WFS electronics and software checkout is proceeding and we have successfully tested the mux readout.
The two replica mirrors and the final camera lens are still in fabrication. All other optics are received. Two camera barrels are still in fabrication, but test and alignment of the other two camera barrels are ready to start as soon as the test fixture is completed.
A design modification to the Bulkhead Assembly was required to compensate for a vendor fabrication error. This involved the design of a new support ring, which will permanently install on the Bulkhead Assembly. Leak testing of the entire dewar assembly is scheduled for late November.
Change orders for delivery of GNIRS to Chile, including Testing, Training, and
Commissioning, and for the Differential Pressure Switch, are in process.
Next Milestone: The next major project milestone is the completion of
Bulkhead Assembly and Dewar Shell fabrication and leak test in November.
Earned
Value:
|
|
March |
April |
May |
June |
July |
August |
September |
October |
|
BCWS |
$2,278,192 |
$2,565,371 |
$2,732,977 |
$2,929,722 |
$2,976,073 |
$3,030,916 |
$3,085,811 |
$3,145,000 |
|
BCWP |
$1,694,322 |
$1,804.951 |
$1,912,351 |
$2,119,911 |
$2,182,434 |
$2,357,289 |
$2,526,319 |
$2,573,084 |
|
ACWP |
$1,839,301 |
$1,915,889 |
$2,031,750 |
$2,343,546 |
$2,392,603 |
$2,603,604 |
$2,762,963 |
$2,938,004 |
|
SPI |
0.74 |
0.70 |
0.70 |
0.72 |
0.73 |
0.78 |
0.82 |
0.82 |
|
CPI |
0.92 |
0.94 |
0.94 |
0.90 |
0.91 |
0.91 |
0.91 |
0.88 |
This table reflects planned and actual charges to the project as of October 19,
2001. We have spent $1,220,474 in
capital to date.
Project Management: (74% complete)
The
project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/
under Management, Planning. The current scheduled delivery date of the GNIRS
instrument is September 25, 2002.
Systems
Engineering: (100% of planned work)
The
main focus has been support of design updates, mechanism assembly and warm test,
and preparation of the Test Plan for Acceptance Testing, Delivery to Chile,
Training and Commissioning. The
Test Plan has been submitted to Gemini for approval.
Mechanical
Design, Fabrication, Assembly and Test: (90% overall)
The
major activity in this work package has been a design modification to the
Bulkhead assembly, 3D and 2D design of radiation shields, and fabrication.
Mechanisms:
(93% complete overall). The Focus
Mechanism is the only mechanism assembly still in fabrication. Most mechanisms
are essentially ready for test. Testing is underway for the Grating and Prism
turrets and the Slit Slide is in the final stages of rework. The IFU mass models
have been fabricated and installed. The Acquisition Mirror mechanism is waiting
for the mirror, and two camera barrels are in fabrication.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Status
|
|
Camera
|
69%
|
77%
|
78%
|
88% |
90% |
91% |
91% |
91% |
92% |
Final
Fab/test |
|
Focus
|
24%
|
24%
|
30%
|
48% |
59% |
59% |
60% |
67% |
|
Fab |
|
Environmental
Cover |
97%
|
99%
|
99%
|
99% |
99% |
99% |
99% |
99% |
99% |
Test
(on-hold) |
|
Acquisition
Mirror |
58%
|
68%
|
72%
|
75% |
75%
|
75% |
76% |
93% |
93% |
(waiting
for mirror) |
|
Slit/Decker
|
66%
|
77%
|
83%
|
85% |
90%
|
90% |
93% |
93% |
93% |
Rework,
Assembly/test |
|
Filter
Wheel |
71%
|
70%
|
73%
|
78% |
83%
|
83% |
95% |
95% |
95% |
Ready
for test |
|
Grating
Turret |
42%
|
51%
|
72%
|
83% |
85%
|
86% |
89% |
97% |
98% |
Test |
|
Prism
Turret |
48%
|
47%
|
50%
|
56% |
76%
|
85% |
92% |
98% |
98% |
Test |
|
Motor
Drives |
90%
|
90%
|
100%
|
- |
- |
- |
- |
- |
- |
Complete |
Benches: (98% complete overall). Benches are complete. The Collimator has a
few parts still in fabrication, and is nearly ready for assembly. Wiring of the
benches will be done in Integration.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Sept |
Oct |
Status |
|
Post-Slit |
56% |
65% |
70% |
- |
77% |
88% |
94% |
99% |
100% |
Complete |
|
OIWFS |
67% |
67% |
79% |
- |
86% |
87% |
89% |
99% |
100% |
Complete |
|
Collimator
|
|
29%
|
29%
|
46% |
62% |
64% |
77% |
95% |
96% |
Fab
|
|
Pre-Slit
|
44%
|
62%
|
70%
|
81% |
83%
|
87% |
91% |
99% |
100% |
Complete |
Fixed Assemblies: (73% complete overall). The Radiation Shields are the
pacing items in fixed assemblies, followed by the Thermal Distribution Assembly.
Fabrication of the Dewar Shells and the Bulkhead Assembly is proceeding
according to planned schedule.
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Status
|
|
Entrance
Window |
96%
|
100%
|
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
48%
|
49%
|
60%
|
67% |
68%
|
79% |
79% |
97% |
97% |
Waiting
for wiring |
|
Cryo
Cooler |
9%
|
16%
|
16% |
16% |
24%
|
49% |
51% |
59% |
59% |
Fab |
|
Thermal
Distribution Assembly |
|
|
|
|
|
|
12% |
26% |
66% |
3D/2D Design |
|
Bulkhead
Rad Shield |
|
|
|
|
|
|
1% |
5% |
9% |
3D Design |
|
LN2
Pre-Cool |
4%
|
4%
|
17%
|
17% |
84%
|
89% |
91% |
91% |
91% |
Fab |
|
Optical
Bench Gimbal Mt. |
53%
|
53%
|
54%
|
56% |
45%
|
85% |
95% |
100% |
- |
Complete |
|
Bulkhead
Assembly |
11%
|
24%
|
42%
|
52% |
55%
|
64% |
74% |
75% |
90% |
Fab |
|
Front
Rad Shield |
5%
|
5%
|
5% |
5% |
7%
|
10% |
10% |
10% |
16% |
3D
design |
|
Rear
Rad Shield |
|
|
|
|
|
|
18% |
18% |
30% |
3D/2D design |
|
Front
Dewar Shell |
26%
|
34%
|
37%
|
37% |
37%
|
38% |
66% |
70% |
88% |
Fab |
|
Rear
Dewar Shell |
6%
|
8%
|
21%
|
21% |
26%
|
- |
57% |
61% |
82% |
Fab |
|
Vertical
Inst Frame |
5%
|
6%
|
6%
|
11% |
- |
- |
14% |
77% |
84% |
Fab
(welding) |
|
Horizontal
Inst Frame |
1%
|
- |
- |
- |
8%
|
8% |
15% |
57% |
57% |
Fab
(welding) |
|
Dewar
Mount Truss |
12%
|
12%
|
12%
|
13% |
47%
|
47% |
47% |
47% |
73% |
Fab |
|
Thermal
Enclosure Mount |
2%
|
7%
|
10%
|
44% |
53
% |
53% |
58% |
70% |
89% |
Fab |
|
Handling
Fixtures |
25%
|
58%
|
- |
68% |
68%
|
68% |
100% |
100% |
- |
Complete |
|
Ballast
Weights |
|
|
|
|
|
|
|
75% |
83% |
Fab |
Electronics: (86% complete overall). Instrument
controller is essentially complete. The OIWFS electronic components have been
installed in the Thermal Enclosure and are being checked out as OIWFS
integration proceeds. The Leach controller has been checked out and seems to
work.
|
|
|
Feb
|
Mar
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Status
|
|
Component
Controller TE |
51%
|
68%
|
71%
|
75% |
66% |
- |
90% |
86% |
86% |
|
|
|
|
VME
Crate |
92%
|
100%
|
- |
- |
100%
|
- |
- |
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
62%
|
94%
|
100%
|
- |
100%
|
- |
- |
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
12%
|
16%
|
16%
|
18% |
90%
|
98% |
98% |
98% |
98% |
|
|
|
Ancillary
Cage Crate |
26%
|
26%
|
26%
|
59% |
63%
|
98% |
98% |
98% |
98% |
Assembly
|
|
|
IfA
Electronics Box |
- |
- |
- |
- |
- |
- |
30% |
30% |
30% |
In
check out |
|
|
Bench
Thermal Controller Crate |
- |
- |
61%
|
68% |
94% |
98% |
98% |
98% |
98% |
Assembly/wiring |
|
External
Cabling (Dewar to TE) |
23%
|
23%
|
23%
|
23% |
23% |
23% |
23% |
23% |
23% |
|
|
|
The
Dewar Warm-up Controller |
37%
|
37%
|
37%
|
37% |
37% |
37% |
37% |
37% |
37% |
|
|
|
Dewar
Electronics |
- |
71%
|
- |
- |
95% |
- |
95% |
95% |
95% |
|
|
|
|
Dewar
Cold Station PCB’s |
60%
|
60%
|
50%
|
60% |
80%
|
80% |
80% |
80% |
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Cabling |
- |
72%
|
72%
|
72% |
96% |
- |
96% |
96% |
96% |
On
Hold – waiting for dewar fab completion |
|
Documentation
|
|
50%
|
50%
|
50% |
85% |
- |
95% |
95% |
95% |
|
|
Software Development: (85% complete overall).
The
areas in work include testing software with the electronics crates and working
on the EPICS software. The OCSwish software has been received and checked out.
Resources assigned to the software task are also working on the Gemini Array
Controller.
|
|
Feb
|
Mar
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
|
Components
Controller Software |
67%
|
91%
|
91%
|
91% |
91% |
- |
91% |
94% |
94% |
|
EPICS
Software |
60%
|
69%
|
69%
|
69% |
75% |
- |
82% |
82% |
82% |
|
Test
& DeBug |
- |
- |
- |
- |
50% |
- |
50% |
75% |
75% |
Procurement: (79% complete overall).
The
major activities in this Work Package included monitoring vendor mechanical and
optical component assembly fabrication. Fabrication
of the final camera lens and the two replica mirrors will be complete and
delivered in November.
|
|
Feb |
Mar |
Apr |
May |
June |
July |
Aug |
Sept |
Oct |
Notes |
|
Optics |
- |
67% |
71% |
73% |
79% |
- |
89% |
86% |
86% |
|
|
RMI optics |
100% |
-
|
-
|
- |
- |
- |
- |
- |
- |
Complete |
|
Flat Mirrors |
|
10% |
50% |
50% |
50% |
- |
99% |
99% |
99% |
Fab of replica mirrors |
|
Pupil Viewer |
100% |
-
|
-
|
- |
- |
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
8%
|
50%
|
93%
|
75% |
75% |
- |
75% |
90% |
90% |
Fab |
|
Grating replicas |
- |
23% |
50% |
83% |
86% |
- |
100% |
100% |
- |
Complete |
|
Prisms |
- |
13% |
13% |
23% |
74% |
- |
95% |
100% |
- |
Complete |
|
Wollaston Prisms |
- |
- |
0% |
10% |
40% |
- |
95% |
100% |
- |
Complete |
Problems
/ Solutions
A modification to the Bulkhead Assembly was required due to a vendor error in fabrication. This has been accomplished and incorporated into the design and fabrication of the assembly. No schedule delay resulted.
The OIWFS Gimbal Mirror assembly has an internal problem that has been referred to Gemini for resolution. The GNIRS team is prepared to effect repair of the assembly, but can do so only as directed by Gemini.
There are two Change Orders outstanding which need to be completed and submitted to Gemini:
·
Change
Order for delivery of GNIRS to Chile
· Change Order revision for the Differential Pressure Switch
These
CO’s will be completed and submitted to the USGPO by mid-November, 2001.
Key
Personnel
Ed
Hileman, SR. Mechanical Engineer and a Design Draftsman, scheduled for release
from GNIRS on November 1st, have been extended on the project until
the Radiation Shields are in fabrication.
Dale
Circle, Sr. Designer, is scheduled to leave the project on December 31st.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360