GNIRS PROGRESS REPORT

January 1 – January 31, 2002

           Accomplishments / Status

  Summary:  87% of the work from the Restart Review to delivery has been completed.  Progress was made on mechanism testing, radiation shield design, Pre-Slit bench optics installation and alignment, grating turret and camera turret flexure testing, and Camera Barrel assembly.

The Radiation Shield design should be complete and into fabrication by mid-February.  Mechanism work in process includes Camera, Prism Turret, and Focus assembly.  The Slit-Decker and Filter Wheel assemblies are being prepared for cold testing.

The integration of the actual WFS HgCdTe detector is yet to be done, and the Gemini-furnished prism is still pending.

Change orders for delivery of GNIRS to Chile, including Testing, Training, and Commissioning, and for the Differential Pressure Switch, are still in process.

  Next Milestone: The next major project milestone is the completion of Active Radiation Shield design by February 28th.

 

  Earned Value:

 

Jun

Jul

Aug

Sept

Oct

Nov

Dec

Jan

BCWS

$2,929,722

$2,976,073

$3,030,916

$3,085,811

$3,145,000

$3,192,781

$3,236,748

$3,304,286

BCWP

$2,119,911

$2,182,434

$2,357,289

$2,526,319

$2,573,084

$2,617,408

$2,884,471

$2,911,411

ACWP

$2,343,546

$2,392,603

$2,603,604

$2,762,963

$2,938,004

$3,122,731

$3,313,415

$3,383,383

SPI

0.72

0.73

0.78

0.82

0.82

0.82

0.89

0.88

CPI

0.90

0.91

0.91

0.91

0.88

0.84

0.87

0.85

 

This table reflects planned and actual charges to the project as of January 31, 2002.  We have spent $1,351,673 in capital to date.

 

  Project Management: (81% complete)

The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery date of the GNIRS instrument is October 24, 2002, due to the delays in finishing the Radiation Shields and Mechanism testing.

 

  Systems Engineering: (100% of planned work)

The main focus has been mechanism assembly, cold test preparation, and support of design updates.

 

Mechanical Design, Fabrication, Assembly and Test: (94% overall)

The major activity in this work package has been 3D and 2D design of radiation shields and fabrication.

 

Mechanisms: (98% complete overall).

 

 

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Status

Camera

78%

88%

90%

91%

91%

91%

92%

98%

99%

99%

Test

Focus

30%

48%

59%

59%

60%

67%

 

73%

89%

92%

Assembly

Environmental Cover

99%

99%

99%

99%

99%

99%

99%

99%

99%

99%

 on-hold

Acquisition Mirror

72%

75%

75%

75%

76%

93%

93%

-

89%

89%

Assembly

Slit/Decker

83%

85%

90%

90%

93%

93%

93%

95%

99%

99%

Test

Filter Wheel

73%

78%

83%

83%

95%

95%

95%

95%

96%

96%

Test

Grating Turret

72%

83%

85%

86%

89%

97%

98%

-

98%

98%

Test

Prism Turret

50%

56%

76%

85%

92%

98%

98%

-

95%

95%

Test

Motor Drives

100%

   -   

   -   

  -

  -

  -

  -

  -

  -

-

Complete

 

Benches: (98% complete overall).  Benches are complete.  The Collimator has a few parts still in fabrication, and is nearly ready for assembly.  Wiring of the benches will be done in Integration.

 

 

Apr

May

Jun

July

Aug

Sept

Oct

Nov

Dec

Jan

Status

Post-Slit

70%

   -

77%

88%

94%

99%

100%

   -

   -

-

Complete

OIWFS

79%

   -

86%

87%

89%

99%

100%

   -

   -

-

Complete

Collimator

29%

46%

62%

64%

77%

95%

-

-

95%

95%

Assembly

Pre-Slit

70%

81%

83%

87%

91%

99%

100%

   -

   -

-

Complete

 

Fixed Assemblies: (86% complete overall).   The Radiation Shields are the pacing items in fixed assemblies.

 

 

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Status

Entrance Window

   -

    -

    -

    -

    -

    -

    -

    -

    -

-

Complete

Detector Mount

60%

67%

68%

79%

79%

97%

97%

-

96%

100%

Complete

Cryo Cooler

16%

16%

24%

49%

51%

59%

59%

70%

88%

89%

Fab

Molecular Sieve

 

 

 

 

 

 

 

45%

100%

-

Complete

Thermal Distribution Assembly

 

 

 

 

12%

26%

-

-

52%

75%

Fab

Bulkhead Rad Shield

 

 

 

 

1%

5%

9%

53%

100%

-

Task closed

LN2 Pre-Cool

17%

17%

84%

89%

91%

91%

91%

-

79%

83%

Fab

Optical Bench Gimbal Mt.

54%

56%

45%

85%

95%

100%

    -

    -

    -

-

Complete

Bulkhead Assembly

42%

52%

55%

64%

74%

75%

90%

98%

100%

-

Complete

Passive Rad Shield

5%

5%

7%

10%

10%

10%

16%

42%

41%

74%

2D design Fab

Active Rad Shield

 

 

 

 

18%

18%

30%

42%

15%

39%

3D/2D design

Front Dewar Shell

37%

37%

37%

38%

66%

70%

88%

100%

  -

-

Complete

Rear Dewar Shell

21%

21%

26%

   -

57%

61%

82%

100%

  -

-

Complete

Vertical Inst Frame

6%

11%

  -

  -

14%

77%

84%

92%

99%

100%

Complete

Horizontal Inst Frame

    -

    -

8%

8%

15%

57%

57%

100%

  -

-

Complete

Dewar Mount Truss

12%

13%

47%

47%

47%

47%

73%

-

84%

85%

Fab

Thermal Enclosure Mount

 10%

44%

53%

53%

58%

70%

89%

96%

100%

-

Complete

Handling Fixtures

   -

68%

68%

68%

100%

100%

  -

  -

  -

-

Complete

Ballast Weights

 

 

 

 

 

75%

83%

100%

  -

-

Complete

 

   Electronics: (89% complete overall).

 

 

 

May

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Status

Component Controller TE

75%

66%

   -

90%

86%

86%

-

72%

72%

 

 

VME Crate

   -

   -

   -

  -

  -

  -

-

  -

-

SW testing

 

Motor Drive/Cryo Cooler Crate

   -

   -

   -

  -

  -

  -

-

  -

-

SW testing

 

Internal Cabling and Connectors

18%

90%

98%

98%

98%

98%

100%

-

-

Complete

 

Ancillary Cage Crate

59%

63%

98%

98%

98%

98%

100%

-

-

Complete

 

IfA Electronics Box

  -

  -

    -

30%

30%

30%

30%

30%

33%

In check out

 

Bench Thermal Controller Crate

68%

94%

98%

98%

98%

98%

70%

100%

-

Complete

External Cabling (Dewar to TE)

23%

23%

23%

23%

23%

23%

23%

23%

36%

 

The Dewar Warm-up Controller

37%

37%

37%

37%

37%

37%

-

59%

87%

 

Dewar Electronics

  

95%

   -

95%

95%

95%

95%

60%

60%

 

 

Dewar Cold Station PCB’s

60%

80%

80%

80%

80%

80%

80%

80%

80%

Ready for install and fit check

 

Dewar Internal Cabling

72%

96%

   -

96%

96%

96%

-

58%

58%

On Hold – waiting for dewar

Documentation

50%

85%

   -

95%

95%

95%

95%

95%

95%

 

Software Test Fixture

 

 

 

100%

-

-

-

-

-

Complete

Array Controller Upgrade

 

 

 

 

 

 

 

100%

-

Complete

 

 Software Development: (82% complete overall).

The areas in work include testing software with the electronics crates, working on the EPICS software and on the OIWFS software.  Resources assigned to the software task are also working on the Gemini Array Controller.  Task percentage complete changes shown are due to rescheduling.

 

 

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Components Controller Software

91%

91%

91%

   -

91%

94%

94%

94%

85%

86%

Test & DeBug

   -

   -

50%

   -

50%

75%

75%

75%

95%

100%

EPICS Software

69% 

69%

75%

   -

82%

82%

82%

-

96%

99%

 

   Alignment and Integration: (24% complete overall)

 

 

Dec

Telescope Simulator

62%

I.    Dewar and Structure

-

II.   Mechanical Integration

-

III. Warm Tests

-

IV.  Cold Tests

-

  

Deliverables: (45% complete overall)

Work in this area has focused on the preparation test plans for acceptance testing.

 

 

Dec

Jan

Instrument Hardware

-

-

Training

-

-

Test plans

46%

99%

Manuals

-

-

As-Built Fabrication Drawings

-

-

  

Procurement: (88% complete overall).

 

 

Apr

May

June

July

Aug

Sept

Oct

Nov

Dec

Jan

Notes

Optics

71%

73%

79%

   -

89%

86%

86%

86%

86%

90%

 

RMI optics

   -

   -

   -

   -

   -

   -

   -

   -

   -

-

Complete

Flat Mirrors

50%

50%

50%

   -

99%

99%

99%

100%

   -

-

Complete

Pupil Viewer

   -

   -

   -

   -

  -

  -

  -

  -

  -

-

Complete

BaF2 lenses

93%

75%

75%

   -

75%

90%

90%

99%

100%

-

Complete

Grating replicas

50%

83%

86%

   -

100%

100%

   -

   -

   -

-

Complete

Prisms

13%

23%

74%

   -

95%

100%

   -

   -

   -

-

Complete

Wollaston Prisms

0%

10%

40%

   -

95%

100%

   -

   -

   -

-

Complete

Simulator Optics

 

 

 

 

 

 

 

 

 

10%

 

 

 

           Problems / Solutions

Radiation Shields remain the pacing item on the project.  Cleaning and testing mechanisms are also a high priority item.

 

             Key Personnel

 Ed Hileman has rejoined the project for the Active Radiation Shield design effort.


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services

NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360