GNIRS
PROGRESS REPORT
January 1 –
January 31, 2002
Accomplishments / Status
Summary: 87% of the work from the Restart Review to delivery has been completed. Progress was made on mechanism testing, radiation shield design, Pre-Slit bench optics installation and alignment, grating turret and camera turret flexure testing, and Camera Barrel assembly.
The Radiation Shield design should be complete and into fabrication by mid-February. Mechanism work in process includes Camera, Prism Turret, and Focus assembly. The Slit-Decker and Filter Wheel assemblies are being prepared for cold testing.
The integration of the actual WFS HgCdTe detector is yet to be done, and the Gemini-furnished prism is still pending.
Change orders for delivery of GNIRS
to Chile, including Testing, Training, and Commissioning, and for the
Differential Pressure Switch, are still in process.
Next Milestone: The next major project milestone is the completion of Active Radiation Shield design by February 28th.
Earned Value:
|
|
Jun |
Jul |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
|
BCWS |
$2,929,722 |
$2,976,073 |
$3,030,916 |
$3,085,811 |
$3,145,000 |
$3,192,781 |
$3,236,748 |
$3,304,286 |
|
BCWP |
$2,119,911 |
$2,182,434 |
$2,357,289 |
$2,526,319 |
$2,573,084 |
$2,617,408 |
$2,884,471 |
$2,911,411 |
|
ACWP |
$2,343,546 |
$2,392,603 |
$2,603,604 |
$2,762,963 |
$2,938,004 |
$3,122,731 |
$3,313,415 |
$3,383,383 |
|
SPI |
0.72 |
0.73 |
0.78 |
0.82 |
0.82 |
0.82 |
0.89 |
0.88 |
|
CPI |
0.90 |
0.91 |
0.91 |
0.91 |
0.88 |
0.84 |
0.87 |
0.85 |
This table reflects planned and actual charges to the project as of January 31, 2002. We have spent $1,351,673 in capital to date.
Project Management: (81% complete)
The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/ under Management, Planning. The current scheduled delivery date of the GNIRS instrument is October 24, 2002, due to the delays in finishing the Radiation Shields and Mechanism testing.
Systems Engineering: (100% of planned work)
The main focus has been mechanism assembly, cold test preparation, and support of design updates.
Mechanical Design, Fabrication, Assembly and Test: (94% overall)
The major activity in this work package has been 3D and 2D design of radiation shields and fabrication.
Mechanisms: (98% complete overall).
|
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Status
|
|
Camera
|
78%
|
88% |
90% |
91% |
91% |
91% |
92% |
98% |
99% |
99% |
Test
|
|
Focus
|
30%
|
48% |
59% |
59% |
60% |
67% |
|
73% |
89% |
92% |
Assembly |
|
Environmental
Cover |
99%
|
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
99% |
on-hold |
|
Acquisition
Mirror |
72%
|
75% |
75%
|
75% |
76% |
93% |
93% |
- |
89% |
89% |
Assembly |
|
Slit/Decker
|
83%
|
85% |
90%
|
90% |
93% |
93% |
93% |
95% |
99% |
99% |
Test |
|
Filter
Wheel |
73%
|
78% |
83%
|
83% |
95% |
95% |
95% |
95% |
96% |
96% |
Test |
|
Grating
Turret |
72%
|
83% |
85%
|
86% |
89% |
97% |
98% |
- |
98% |
98% |
Test |
|
Prism
Turret |
50%
|
56% |
76%
|
85% |
92% |
98% |
98% |
- |
95% |
95% |
Test |
|
Motor
Drives |
100%
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
Benches: (98% complete overall). Benches are complete. The Collimator has a few parts still in fabrication, and is nearly ready for assembly. Wiring of the benches will be done in Integration.
|
|
Apr |
May |
Jun |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Status |
|
Post-Slit |
70% |
- |
77% |
88% |
94% |
99% |
100% |
- |
- |
- |
Complete |
|
OIWFS |
79% |
- |
86% |
87% |
89% |
99% |
100% |
- |
- |
- |
Complete |
|
Collimator
|
29%
|
46% |
62% |
64% |
77% |
95% |
- |
- |
95% |
95% |
Assembly |
|
Pre-Slit
|
70%
|
81% |
83%
|
87% |
91% |
99% |
100% |
- |
- |
- |
Complete |
Fixed Assemblies: (86% complete overall). The Radiation Shields are the pacing items in fixed assemblies.
|
|
Apr
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Status
|
|
Entrance
Window |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Detector
Mount |
60%
|
67% |
68%
|
79% |
79% |
97% |
97% |
- |
96% |
100% |
Complete |
|
Cryo
Cooler |
16% |
16% |
24%
|
49% |
51% |
59% |
59% |
70% |
88% |
89% |
Fab |
|
Molecular
Sieve |
|
|
|
|
|
|
|
45% |
100% |
- |
Complete |
|
Thermal
Distribution Assembly |
|
|
|
|
12% |
26% |
- |
- |
52% |
75% |
Fab |
|
Bulkhead
Rad Shield |
|
|
|
|
1% |
5% |
9% |
53% |
100% |
- |
Task closed |
|
LN2
Pre-Cool |
17%
|
17% |
84%
|
89% |
91% |
91% |
91% |
- |
79% |
83% |
Fab |
|
Optical
Bench Gimbal Mt. |
54%
|
56% |
45%
|
85% |
95% |
100% |
- |
- |
- |
- |
Complete |
|
Bulkhead
Assembly |
42%
|
52% |
55%
|
64% |
74% |
75% |
90% |
98% |
100% |
- |
Complete |
|
Passive
Rad Shield |
5% |
5% |
7%
|
10% |
10% |
10% |
16% |
42% |
41% |
74% |
2D
design Fab |
|
Active
Rad Shield |
|
|
|
|
18% |
18% |
30% |
42% |
15% |
39% |
3D/2D design |
|
Front
Dewar Shell |
37%
|
37% |
37%
|
38% |
66% |
70% |
88% |
100% |
- |
- |
Complete |
|
Rear
Dewar Shell |
21%
|
21% |
26%
|
- |
57% |
61% |
82% |
100% |
- |
- |
Complete |
|
Vertical
Inst Frame |
6%
|
11% |
- |
- |
14% |
77% |
84% |
92% |
99% |
100% |
Complete |
|
Horizontal
Inst Frame |
- |
- |
8%
|
8% |
15% |
57% |
57% |
100% |
- |
- |
Complete |
|
Dewar
Mount Truss |
12%
|
13% |
47%
|
47% |
47% |
47% |
73% |
- |
84% |
85% |
Fab
|
|
Thermal
Enclosure Mount |
10%
|
44% |
53% |
53% |
58% |
70% |
89% |
96% |
100% |
- |
Complete |
|
Handling
Fixtures |
- |
68% |
68%
|
68% |
100% |
100% |
- |
- |
- |
- |
Complete |
|
Ballast
Weights |
|
|
|
|
|
75% |
83% |
100% |
- |
- |
Complete |
Electronics: (89% complete overall).
|
|
|
May |
June
|
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Status
|
|
Component
Controller TE |
75% |
66% |
- |
90% |
86% |
86% |
- |
72% |
72% |
|
|
|
|
VME
Crate |
- |
- |
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
|
Motor
Drive/Cryo Cooler Crate |
- |
- |
- |
- |
- |
- |
- |
- |
- |
SW
testing |
|
|
Internal
Cabling and Connectors |
18% |
90%
|
98% |
98% |
98% |
98% |
100% |
- |
- |
Complete |
|
|
Ancillary
Cage Crate |
59% |
63%
|
98% |
98% |
98% |
98% |
100% |
- |
- |
Complete |
|
|
IfA
Electronics Box |
- |
- |
- |
30% |
30% |
30% |
30% |
30% |
33% |
In
check out |
|
|
Bench
Thermal Controller Crate |
68% |
94% |
98% |
98% |
98% |
98% |
70% |
100% |
- |
Complete |
|
External
Cabling (Dewar to TE) |
23% |
23% |
23% |
23% |
23% |
23% |
23% |
23% |
36% |
|
|
|
The
Dewar Warm-up Controller |
37% |
37% |
37% |
37% |
37% |
37% |
- |
59% |
87% |
|
|
|
Dewar
Electronics |
- |
95% |
- |
95% |
95% |
95% |
95% |
60% |
60% |
|
|
|
|
Dewar
Cold Station PCB’s |
60% |
80%
|
80% |
80% |
80% |
80% |
80% |
80% |
80% |
Ready
for install and fit check |
|
|
Dewar
Internal Cabling |
72% |
96% |
- |
96% |
96% |
96% |
- |
58% |
58% |
On
Hold – waiting for dewar |
|
Documentation
|
50% |
85% |
- |
95% |
95% |
95% |
95% |
95% |
95% |
|
|
|
Software
Test Fixture |
|
|
|
100% |
- |
- |
- |
- |
- |
Complete |
|
|
Array
Controller Upgrade |
|
|
|
|
|
|
|
100% |
- |
Complete |
|
Software Development: (82% complete overall).
The areas in work include testing software with the electronics crates, working on the EPICS software and on the OIWFS software. Resources assigned to the software task are also working on the Gemini Array Controller. Task percentage complete changes shown are due to rescheduling.
|
|
Apr
|
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
|
Components
Controller Software |
91%
|
91% |
91% |
- |
91% |
94% |
94% |
94% |
85% |
86% |
|
Test
& DeBug |
- |
- |
50% |
- |
50% |
75% |
75% |
75% |
95% |
100% |
|
EPICS
Software |
69%
|
69% |
75% |
- |
82% |
82% |
82% |
- |
96% |
99% |
Alignment and Integration: (24% complete overall)
|
|
Dec |
|
Telescope
Simulator |
62% |
|
I.
Dewar and Structure |
- |
|
II.
Mechanical Integration |
- |
|
III.
Warm Tests |
- |
|
IV.
Cold Tests |
- |
Deliverables: (45% complete overall)
Work in this area has focused on the preparation test plans for acceptance testing.
|
|
Dec |
Jan |
|
Instrument
Hardware |
- |
- |
|
Training
|
- |
- |
|
Test
plans |
46% |
99% |
|
Manuals |
- |
- |
|
As-Built
Fabrication Drawings |
- |
- |
Procurement: (88% complete overall).
|
|
Apr |
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Notes |
|
Optics |
71% |
73% |
79% |
- |
89% |
86% |
86% |
86% |
86% |
90% |
|
|
RMI optics |
-
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
Flat Mirrors |
50% |
50% |
50% |
- |
99% |
99% |
99% |
100% |
- |
- |
Complete |
|
Pupil Viewer |
-
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Complete |
|
BaF2
lenses |
93%
|
75% |
75% |
- |
75% |
90% |
90% |
99% |
100% |
- |
Complete |
|
Grating replicas |
50% |
83% |
86% |
- |
100% |
100% |
- |
- |
- |
- |
Complete |
|
Prisms |
13% |
23% |
74% |
- |
95% |
100% |
- |
- |
- |
- |
Complete |
|
Wollaston Prisms |
0% |
10% |
40% |
- |
95% |
100% |
- |
- |
- |
- |
Complete |
|
Simulator Optics |
|
|
|
|
|
|
|
|
|
10% |
|
Problems / Solutions
Radiation Shields remain the pacing item on the project. Cleaning and testing mechanisms are also a high priority item.
Key Personnel
Ed
Hileman has rejoined the project for the Active Radiation Shield design effort.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360