
PROGRESS REPORT
December 21 – January 22, 2001
Accomplishments / Status
Summary: Overall, 46% of the work from the Restart Review to delivery has been completed. The primary focus of this reporting period has been 1) Post-Slit Optical Bench detailing and fabrication; 2) Focus mechanism 3D and 2D design; 3) Pre-Slit optical bench fabrication; 4) Slit/Decker mechanism fabrication; 5) Prism, Grating and Camera Turret 2D detailing; 6) Filter Wheel mechanism fabrication.
Next
Milestone:
The next major project milestones are the Mid-Fabrication Review and Quarterly
Review, both on March 7th.
Earned
Value:
BCWS $ 1,798,138
SPI
0.75
BCWP $ 1,341,727
CPI 0.84
ACWP $ 1,595,701
Project
Management:
(44% completed) The project plan may be viewed on the GNIRS web site at: http://www.noao.edu/ets/gnirs/
under Management, Planning. Work is being done to prepare for integration later
this year. The August 2002
scheduled delivery date of the GNIRS instrument has not changed.
Systems
Engineering:
(100% of planned work) The activity in work included systems engineering input
to the design process, primarily focus mechanism design and the LN2
Pre-Cool system, and preparing for flexure tests which will be done in February
to verify the rotary mechanism designs.
Mechanical
Design: (44%
overall including: Mechanisms 56%, Benches 53%, and Fixed Assemblies 11%).
Activities included optical bench solid modeling and detailing, focus
mechanism design, grating turret design, prism turret design and detailing, and
filter wheel detailing. Also,
handling fixtures for use in bench integration are being designed.
Mechanism
completion summary:
Camera
59%
Focus
23%
Environmental Cover
96%
Acquisition Mirror
51%
Slit Decker
64%
Filter Wheel
60%
Grating Turret
39%
Prism Turret
37%
Motor Drives
74%
All
mechanisms are in 2D design or in fabrication except the Camera, which has one
camera in 3D design.
Detailed
status:
Camera mechanism is in various stages of 3D and 2D
design and fabrication:
Camera top Assembly:
87%
Short Red Camera:
90% complete, fabrication 75% complete
Short Blue camera:
33% complete, 2D drafting 50% complete
Long Red Camera:
14% complete, 2D drafting 20% complete
Long Blue Camera:
8% complete, 3D design 13% complete
Camera drive spindle Hub:
82% complete, fabrication
61% complete
Focus
mechanism:
3D design 95% complete
Environmental
cover assembly:
in test
Acquisition
mirror mechanism:
fabrication 2% complete
Slit-Decker
mechanism:
fabrication 70% complete
Filter
wheel mechanism:
fabrication 10% complete
Grating
turret mechanism:
2D detailing 17% complete
Prism
turret mechanism:
fabrication 4% complete
Motor
drive assemblies:
assembly 10% complete
Benches:
The
Post-Slit bench is 59% complete overall, fabrication started.
The
OIWFS bench is 100% complete.
The
Collimator housing is 26% complete overall, and is ready to begin 2D design.
The Pre-Slit bench consists of the POM and Offner assembly. The POM is 49% complete with fabrication at 23%. The Offner is 34% complete with fabrication at 20% complete.
Electronics:
(58%) The component controller thermal enclosure VME crate is complete and has
been tested. Dewar and shield
interface PCB’s are being fabricated at a vendor.
Software
Development:
(27%) The Components Controller Software is 29% complete, lab support software
is 6% complete, and the high level Epics software is 1% complete.
The next phase is actual testing of the component controller code, which
will test motor drive and mechanism status and position sensing.
Optics: 11 of 14 RMI camera lenses and windows have been completed
and accepted, with three remaining to be inspected and coated.
A
new contract has been let to Janos for the four BaF2 lenses for the
short red and blue cameras.
Grating
replicas have been ordered.
Prism
drawings are complete and currently out for quote to several vendors.
Procurement:
(52%) Major activities in this Work Package included optics work at RMI,
contracting with Janos for the four BaF2 lenses, obtaining quotes for
the prisms and monitoring vendor fabrication.
Quotes are also being obtained for a clean room tent for use during
assembly and integration.
Problems / Solutions
The OIWFS component late delivery will impact the project. We have no information on when these parts will be provided.
Key Personnel
No changes.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |
If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.
National Optical Astronomy Observatories,
950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360