Delivery Milestone Schedule 2-24-03
Scheduled Milestones | Milestones by Task | Milestones by Month
There
are currently 227designated project milestones, which reflect task completions
to the 4th, 5th, and 6th levels of the WBS.
Examples of these milestones include:
Structural analysis complete
Grating turret 3D design complete
II-VI mirrors inspected and accepted
The following
table gives an overall summary of progress on meeting the milestone goals set
down in the project schedule. Also
available (above) are a chart of all milestones and a pdf file that
shows the schedule with every milestone and its scheduled due date.
Milestone Status
|
Total number of project milestones |
227 |
|
Milestones completed |
222 |
Released Drawings* Milestone
|
Estimated Number of Total Drawings |
Number of Drawings Assigned To Date |
Number of Released Drawings To Date |
% Released to Total Estimate |
| 1179 | 1159 | 1078 | 93% |
*These numbers include only actual GNIRS flight
hardware; drawings for prototypes, test fixtures, handling
fixtures, or electronic drawings are not included.
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information
NOAO Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360