Milestone Summary 
updated 7/23/03

Delivery Milestone Schedule 2-24-03

Scheduled Milestones  |  Milestones by Task  |  Milestones by Month    

There are currently 227designated project milestones, which reflect task completions to the 4th, 5th, and 6th levels of the WBS.  Examples of these milestones include: 

         Structural analysis complete
         Grating turret 3D design complete
         Top camera cover 3D design complete
         II-VI mirrors inspected and accepted

 The following table gives an overall summary of progress on meeting the milestone goals set down in the project schedule. Also available (above) are a chart of all milestones and a pdf file that shows the schedule with every milestone and its scheduled due date. Updates to this chart will be posted by the end of each month.

 Milestone Status

 

Total number of project milestones

227

Milestones completed

222


Released Drawings* Milestone

 

Estimated Number of Total Drawings

Number of Drawings Assigned To Date

Number of Released Drawings To Date

% Released to Total Estimate

1179 1159 1078 93%

*These numbers include only actual GNIRS flight
hardware; drawings for prototypes, test fixtures, handling
fixtures, or electronic drawings are not included.


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services
NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360