Management: Scheduled Meetings/Reviews
Description of Planned GNIRS Reviews
Every Tuesday, 10:30am-12pm in the Drafting Workroom (Rm. 216), Tucson
Reviews
Pre-Fabrication
Review
May 11-12, 2000
Pre-Fabrication Review Report
June 16, 2000
Pre-Fabrication
Review Response
August 15, 2000
Quarterly
Review Report
May 12, 2000
Quarterly
Review Presentation (ppt file)
August 15, 2000
Quarterly
Review Report
August 30, 2000
Quarterly Review Presentation (ppt file)
November 15, 2000
Mid-Fabrication Review
Presentation (ppt file)
March 7, 2001
Mid-Fabrication Review Report
March 20, 2001
Quarterly
Review Report
April 4, 2001
Quarterly
Review Presentation (ppt file)
June 8, 2001 (revised 6/15/01)
Quarterly
Review Report
July 2, 2001
Quarterly
Review Presentation (ppt file)
October 5, 2001 (revised 10/2/01)
Quarterly
Review Report
October 24, 2001
Quarterly
Review Presentation (ppt file)
January 24, 2002
Quarterly
Review Report
February 25, 2002
Quarterly
Review Presentation (ppt file)
(file revised 4/29/02--revisions in blue)
May 1, 2002
Quarterly
Review Report
May 30, 2002
Quarterly
Review Presentation (pdf file)
September 3, 2002
Quarterly
Review Report
September 20, 2002
Quarterly
Review Presentation (pdf file)
December 10, 2002
Quarterly
Review Report
January 8, 2003
Quarterly
Review Presentation (pdf file)
March 25, 2003
(Updated 3-24-03 - changes in blue)
Integration Review
To be announced
Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information
NOAO Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360