GNIRS Mid-Fabrication Review Report
March 20,
2001
Committee
Tom Geballe
Kim Gillies
Bret Goodrich
Mark Hunten
Manuel Lazo
Jim Oschmann
Doug Simons
(Chair)
Summary
GNIRS was reviewed on 7 March 2001
during the mid-phase of its fabrication by an engineering and science team to
evaluate progress and identify any outstanding issues that have emerged since
its last formal review, the Prefabrication Review (PFR) held in May 2000. The
GNIRS team continued to make good overall progress toward completing the
instrument close to original budget and schedule targets, as originally
identified during the Restart Review. The team gave a confident and candid
appraisal of progress and issues that naturally emerge in an instrument as
complex as GNIRS. Assuming integration can be completed during the third quarter
of 2001, it appears feasible that GNIRS can be delivered ~1 year thereafter to
Gemini, on schedule.
Comments and Recommendations
- Mechanical
- The
predicted mass and CG of the instrument look like they will meet the
required values. That said, most instruments have made a similar
prediction at a similar time in their production, and generally the mass
and CG is not measured with complete confidence until instruments are
nearly done and remedies to any unforeseen problems are time consuming or
expensive. We therefore encourage the GNIRS team to build some flexibility
into the mass distribution of the instrument. Ballast weights that can be
attached at various points around the instrument are already planned. A
potentially low cost additional strategy would be to mount the electronics
cabinets on adjustable racks. Given the impact of these cabinets on the
overall mass/moment, building such adjustment into GNIRS will permit
additional freedom to tune the mass and CG at the end of the integration
phase. Furthermore, having such adjustability permits greater freedom in
the balancing of GNIRS vs. other instruments on the ISS.
- The
passive flexure compensation system, though elegant, represents some risk
in terms of cold cycles required to tune it to match the actual flexure of
the instrument. A motor driven system would permit faster convergence with
tuning the compensator, but would also be more mechanically complex. In
order to reduce the potential for using precious cold cycles to tune the
compensator, we recommend looking into using a bare MUX and making warm
tests, e.g., pressing on the sides of the compensator while recording
images to make sure motion at the detector has the direction and amplitude
expected.
- The
planned flexure tests of the completed instrument are similar to what was
used for NIRI and places the instrument at risk of not fully demonstrating
its flexure performance prior to shipment to Chile. In NIRI’s case,
single axis tests were completed in Honolulu and this was the extent of
the testing completed due to lack of proper facilities at the IfA to
complete multi-axis tests. Such tests were run when NIRI was placed on the
telescope and, of course, the flexure along untested rotation axes was
then demonstrated to be unacceptably large. Gemini and the IfA worked
together to resolve the problem, but the solution required having the NIRI
PI on-site, working in the Gemini lab, and shuttling to/from the IfA shop
in Honolulu. It is important to note that NIRI was not formally accepted
due to flexure problems, hence it was the clear responsibility of the IfA
to lead the effort to fix the problem under these circumstances. If we
have a similar problem with GNIRS due to lack of proper flexure testing,
it will require NOAO personnel to be in Chile for extended periods of
time, potentially with parts being sent to and from Tucson, i.e. the
remedy stands to be much more complex, costly, and time consuming. GNIRS
must therefore be properly flexure tested before it is sent to Chile as
part of the on-site acceptance tests in order to demonstrate that it meets
an acceptable level of flexure before it is shipped. Details of these
tests will be defined through the GNIRS Acceptance Test Plan.
- Overall
the electronics subsystems appeared to be in good shape and at a level
consistent with the rest of the instrument’s development. We encourage
an on-going dialog between the GNIRS EE and Mark Hunten, particularly
regarding the use of mains vs. UPS power and instrument/telescope
grounding schemes.
- Providing
some level of protection for the GNIRS cryocoolers in the accidental and
sudden loss of helium flow should be factored into the control system.
Gemini is now providing differential pressure switches at each telescope
that trigger when facility helium pressure is lost. These switches can be
used, for example, to cut the power to cryocoolers instantly. Long term
Gemini will link helium pressure status with the GIS so a single signal
can trigger the shutdown of all instruments’ cryocoolers. Continued
dialog with Gemini is encouraged in order to make sure GNIRS will be
compatible with at least one of these approaches to protecting its 4 cold
heads after it is sent to Chile.
- Overall
the progress on the GNIRS software since the PFR has been very good and
GNIRS is in the unique position of not having software on its critical
path. The GNIRS design relies heavily on low level C code to provide an
interim engineering control environment. An EPICS layer that interfaces to
the underlying C code will be completed later. This is similar in nature
to the already successful GMOS CCD/controller software, and the Gemini TCS.
That said the committee believes development of the most complex portion
of the code (the EPICS layer) has been deferred until late in the project,
which represents risk. A parallel presentation describing plans for the
EPICS layer above the C code would have been helpful in assessing this
risk level. Successfully retrofitting the EPICS layer onto the established
C code will require that people handling both tasks (Richard and Peter)
are in good communication throughout the process to streamline interfaces
and assure that all required functionality is provided in the final
system.
- Using
NIRI code does not guarantee that the OCS interface will be correct. In
fact the NIRI/OCS interface delivered does not meet Gemini’s ICD and
this is an issue that still needs to be resolved. We urge NOAO to use a
standalone version of the OCSwish tool, available through Kim Gillies, to
confirm that the GNIRS/OCS interface works properly, rather than assuming
the NIRI code properly interfaces to the OCS.
- While
Gemini in general encourages the reuse of instrumentation software, there
will undoubtedly be divergent development efforts between NIRI and GNIRS
on the same code and controlling this will take effort within NOAO and
Gemini. We therefore encourage regular dialog between NOAO and Gemini on
this matter, particularly as NIRI’s software is now being maintained and
updated by Gemini personnel. For example, DHS integration, PPC support,
WCS implementation and image header parameters have all been recently
handled by Gemini staff working on the delivered NIRI software.
- GNIRS
is being well managed as key performance metrics are understood on
timescales fast enough that corrective action, if needed, can be
effective. This is reflected in the speed with which CAS now reports labor
data to the GNIRS management group, compared to the problems noted at the
PFR. As noted in the summary, the basic metrics of budget and schedule
indicate GNIRS progress has been very good since the PFR.
- We
share the NOAO concern about a “wave” of manpower being pushed
steadily outward in the labor projections. The real impact of this problem
will probably not be realize until the integration phase begins. In any
event we believe that the integration plan has sufficient latitude and
flexibility to be adjusted to minimize the effect of this wave. The
availability of Bill Ditsler during the integration phase is also an area
of concern, given that he will likely be consumed to some extent by other
projects, notably work on the dewar for the Gemini bench spectrograph.
- The
committee noted some concern about the fact that a significant amount of
design work remains before the full system integration can begin. Again
this is not an ideal situation but is manageable.
- Gemini
will send periodically its southern instrument engineer and lead GNIRS
scientist to Tucson at key points in the integration and test phase of the
instrument. This is primarily intended to provide hands-on training in the
assembly and maintenance of the instrument and to let the Gemini personnel
who will eventually be responsible for maintaining and operating GNIRS
become thoroughly familiar with it before it leaves Tucson.
If you have any questions or suggestions regarding this website,
please contact Melissa Bowersock.
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360