Project Start Date: Mon 4/16/01
Project Finish Date: Wed 5/8/02
| ID |
Task Name |
Work | Duration | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 1 |
Recharge PSL contract |
0 hrs | 1 day | Mon 4/16/01 | Mon 4/16/01 | 100% |
| 2 |
Deliver drawings in AutoCad |
0 hrs | 2 wks? | Sat 6/16/01 | Fri 6/29/01 | 100% |
| 3 |
Backviewing optics |
248 hrs | 114 days | Wed 5/16/01 | Mon 10/22/01 | 84% |
| 4 |
Check Yale spectrograph vs. focal
distance |
40 hrs | 1 wk | Tue 10/16/01 | Mon 10/22/01 | 0% |
| 5 |
Jeff Snyder |
40 hrs | Tue 10/16/01 | Mon 10/22/01 | 0% | |
| 5 |
Check Yale spectrograph need for
pellicle |
208 hrs | 5.2 wks | Wed 5/16/01 | Wed 6/20/01 | 100% |
| 5 |
Jeff Snyder |
208 hrs | Wed 5/16/01 | Wed 6/20/01 | 100% | |
| 6 |
Mechanical |
5,120 hrs | 113 days? | Wed 8/1/01 | Thu 1/3/02 | 43% |
| 7 |
Mechanical procurement and
alignment |
1,920 hrs | 4 mons | Wed 8/1/01 | Tue 11/20/01 | 85% |
| 2 |
Chris Anderson |
640 hrs | Wed 8/1/01 | Tue 11/20/01 | 85% | |
| 15 |
Scott Buckley |
640 hrs | Wed 8/1/01 | Tue 11/20/01 | 85% | |
| 16 |
Rick Williams |
640 hrs | Wed 8/1/01 | Tue 11/20/01 | 85% | |
| 8 |
Anodization |
240 hrs | 2 wks | Wed 11/21/01 | Mon 12/3/01 | 0% |
| 2 |
Chris Anderson |
80 hrs | Wed 11/21/01 | Mon 12/3/01 | 0% | |
| 15 |
Scott Buckley |
80 hrs | Wed 11/21/01 | Mon 12/3/01 | 0% | |
| 16 |
Rick Williams |
80 hrs | Wed 11/21/01 | Mon 12/3/01 | 0% | |
| 9 |
Access panel to reach ICCD |
1,280 hrs | 2 mons | Mon 9/3/01 | Fri 10/26/01 | 35% |
| 1 |
Charles Corson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 35% | |
| 2 |
Chris Anderson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 35% | |
| 8 |
Shelby Gott |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 35% | |
| 15 |
Scott Buckley |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 35% | |
| 10 |
Outrigger bars |
600 hrs | 20 days? | Mon 10/29/01 | Fri 11/23/01 | 0% |
| 11 |
Check need to watch for friction |
40 hrs | 1 wk | Mon 10/29/01 | Fri 11/2/01 | 0% |
| 16 |
Rick Williams |
40 hrs | Mon 10/29/01 | Fri 11/2/01 | 0% | |
| 12 |
Check if need to seal bars |
160 hrs | 2 wks? | Mon 10/29/01 | Fri 11/9/01 | 0% |
| 2 |
Chris Anderson |
80 hrs | Mon 10/29/01 | Fri 11/9/01 | 0% | |
| 16 |
Rick Williams |
80 hrs | Mon 10/29/01 | Fri 11/9/01 | 0% | |
| 13 |
PM procedure for cleaning and
lubrication |
320 hrs | 4 wks? | Mon 10/29/01 | Fri 11/23/01 | 0% |
| 2 |
Chris Anderson |
160 hrs | Mon 10/29/01 | Fri 11/23/01 | 0% | |
| 22 |
Rick Willams |
160 hrs | Mon 10/29/01 | Fri 11/23/01 | 0% | |
| 14 |
Check if THK motors are sealed |
80 hrs | 1 wk? | Mon 11/5/01 | Fri 11/9/01 | 0% |
| 2 |
Chris Anderson |
40 hrs | Mon 11/5/01 | Fri 11/9/01 | 0% | |
| 16 |
Rick Williams |
40 hrs | Mon 11/5/01 | Fri 11/9/01 | 0% | |
| 15 |
Lab Testing/Verification |
1,080 hrs | 47 days | Thu 11/1/01 | Thu 1/3/02 | 10% |
| 16 |
Initial Assembly |
120 hrs | 1 wk | Thu 11/1/01 | Wed 11/7/01 | 90% |
| 2 |
Chris Anderson |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 90% | |
| 15 |
Scott Buckley |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 90% | |
| 16 |
Rick Williams |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 90% | |
| 17 |
Functional tests at UW |
360 hrs | 3 wks | Thu 11/8/01 | Wed 11/28/01 | 0% |
| 2 |
Chris Anderson |
120 hrs | Thu 11/8/01 | Wed 11/28/01 | 0% | |
| 15 |
Scott Buckley |
120 hrs | Thu 11/8/01 | Wed 11/28/01 | 0% | |
| 16 |
Rick Williams |
120 hrs | Thu 11/8/01 | Wed 11/28/01 | 0% | |
| 18 |
Rework Machining |
120 hrs | 1 wk | Fri 12/7/01 | Thu 12/13/01 | 0% |
| 2 |
Chris Anderson |
40 hrs | Fri 12/7/01 | Thu 12/13/01 | 0% | |
| 15 |
Scott Buckley |
40 hrs | Fri 12/7/01 | Thu 12/13/01 | 0% | |
| 16 |
Rick Williams |
40 hrs | Fri 12/7/01 | Thu 12/13/01 | 0% | |
| 19 |
Final Mechanical Assembly |
480 hrs | 1 mon | Fri 12/7/01 | Thu 1/3/02 | 0% |
| 2 |
Chris Anderson |
160 hrs | Fri 12/7/01 | Thu 1/3/02 | 0% | |
| 15 |
Scott Buckley |
160 hrs | Fri 12/7/01 | Thu 1/3/02 | 0% | |
| 16 |
Rick Williams |
160 hrs | Fri 12/7/01 | Thu 1/3/02 | 0% | |
| 20 |
Shipping Crate |
188 hrs | 24 days? | Mon 12/3/01 | Thu 1/3/02 | 0% |
| 21 |
Acquire basic measurements |
4 hrs | 0.25 days | Mon 12/3/01 | Mon 12/3/01 | 0% |
| 15 |
Scott Buckley |
2 hrs | Mon 12/3/01 | Mon 12/3/01 | 0% | |
| 16 |
Rick Williams |
2 hrs | Mon 12/3/01 | Mon 12/3/01 | 0% | |
| 22 |
Create sketch of CassIAS crate |
12 hrs | 0.75 days | Mon 12/3/01 | Mon 12/3/01 | 0% |
| 15 |
Scott Buckley |
6 hrs | Mon 12/3/01 | Mon 12/3/01 | 0% | |
| 16 |
Rick Williams |
6 hrs | Mon 12/3/01 | Mon 12/3/01 | 0% | |
| 23 |
Mechanical sketch created |
12 hrs | 0.75 days | Tue 12/4/01 | Tue 12/4/01 | 0% |
| 15 |
Scott Buckley |
6 hrs | Tue 12/4/01 | Tue 12/4/01 | 0% | |
| 16 |
Rick Williams |
6 hrs | Tue 12/4/01 | Tue 12/4/01 | 0% | |
| 24 |
Fabrication of crate |
160 hrs | 2 wks? | Tue 12/4/01 | Tue 12/18/01 | 0% |
| 15 |
Scott Buckley |
80 hrs | Tue 12/4/01 | Tue 12/18/01 | 0% | |
| 16 |
Rick Williams |
80 hrs | Tue 12/4/01 | Tue 12/18/01 | 0% | |
| 25 |
Delivery of CassIAS to NOAO |
0 hrs | 0 days | Thu 1/3/02 | Thu 1/3/02 | 0% |
| 15 |
Scott Buckley |
0 hrs | Thu 1/3/02 | Thu 1/3/02 | 0% | |
| 16 |
Rick Williams |
0 hrs | Thu 1/3/02 | Thu 1/3/02 | 0% | |
| 26 |
Electronics |
6,944 hrs | 170 days? | Mon 9/3/01 | Thu 4/25/02 | 19% |
| 11 |
Shebly Gott |
1,280 hrs | Mon 9/17/01 | Thu 4/25/02 | 19% | |
| 27 |
Limit switches |
1,240 hrs | 65 days? | Mon 9/17/01 | Thu 12/13/01 | 34% |
| 28 |
Specify limit switches |
40 hrs | 1 wk? | Mon 9/17/01 | Fri 9/21/01 | 100% |
| 11 |
Shebly Gott |
40 hrs | Mon 9/17/01 | Fri 9/21/01 | 100% | |
| 29 |
Define switches functional design |
480 hrs | 3 mons | Mon 9/24/01 | Thu 12/13/01 | 20% |
| 8 |
Shelby Gott |
480 hrs | Mon 9/24/01 | Thu 12/13/01 | 20% | |
| 30 |
Guard against driving past limit |
640 hrs | 2 mons | Mon 9/17/01 | Fri 11/9/01 | 40% |
| 1 |
Charles Corson |
320 hrs | Mon 9/17/01 | Fri 11/9/01 | 40% | |
| 2 |
Chris Anderson |
320 hrs | Mon 9/17/01 | Fri 11/9/01 | 40% | |
| 31 |
Test motor torques |
80 hrs | 2 wks? | Fri 10/5/01 | Thu 10/18/01 | 30% |
| 2 |
Chris Anderson |
80 hrs | Fri 10/5/01 | Thu 10/18/01 | 30% | |
| 32 |
Electronics/Motor ventilation |
960 hrs | 2 mons | Mon 9/3/01 | Fri 10/26/01 | 25% |
| 1 |
Charles Corson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 2 |
Chris Anderson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 8 |
Shelby Gott |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 33 |
Electronics Box |
3,464 hrs | 170 days? | Mon 9/3/01 | Thu 4/25/02 | 13% |
| 1 |
Charles Corson |
1,296 hrs | Thu 9/13/01 | Thu 4/25/02 | 9% | |
| 34 |
Mech engineering |
1,120 hrs | 48 days? | Mon 9/3/01 | Wed 11/7/01 | 21% |
| 35 |
Cable drape tie-off |
80 hrs | 1 wk | Thu 11/1/01 | Wed 11/7/01 | 0% |
| 15 |
Scott Buckley |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 0% | |
| 16 |
Rick Williams |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 0% | |
| 36 |
Support from housing |
80 hrs | 1 wk? | Thu 11/1/01 | Wed 11/7/01 | 0% |
| 15 |
Scott Buckley |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 0% | |
| 16 |
Rick Williams |
40 hrs | Thu 11/1/01 | Wed 11/7/01 | 0% | |
| 37 |
Electronics/Motor ventilation |
960 hrs | 2 mons | Mon 9/3/01 | Fri 10/26/01 | 25% |
| 1 |
Charles Corson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 2 |
Chris Anderson |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 8 |
Shelby Gott |
320 hrs | Mon 9/3/01 | Fri 10/26/01 | 25% | |
| 38 |
STD bus vs. Linux |
80 hrs | 1 wk? | Thu 9/13/01 | Wed 9/19/01 | 100% |
| 1 |
Charles Corson |
40 hrs | Thu 9/13/01 | Wed 9/19/01 | 100% | |
| 8 |
Shelby Gott |
40 hrs | Thu 9/13/01 | Wed 9/19/01 | 100% | |
| 39 |
Procure STD bus/chassis (or Linux) |
240 hrs | 3 wks? | Thu 11/1/01 | Wed 11/21/01 | 0% |
| 1 |
Charles Corson |
120 hrs | Thu 11/1/01 | Wed 11/21/01 | 0% | |
| 8 |
Shelby Gott |
120 hrs | Thu 11/1/01 | Wed 11/21/01 | 0% | |
| 40 |
Identify power supplies for box |
8 hrs | 1 day? | Thu 11/22/01 | Thu 11/22/01 | 0% |
| 8 |
Shelby Gott |
8 hrs | Thu 11/22/01 | Thu 11/22/01 | 0% | |
| 41 |
Specify connectors for Rick |
40 hrs | 1 wk? | Thu 11/22/01 | Wed 11/28/01 | 0% |
| 8 |
Shelby Gott |
40 hrs | Thu 11/22/01 | Wed 11/28/01 | 0% | |
| 42 |
Assemble STD bus (or Linux) |
40 hrs | 1 wk? | Thu 11/22/01 | Wed 11/28/01 | 0% |
| 8 |
Shelby Gott |
40 hrs | Thu 11/22/01 | Wed 11/28/01 | 0% | |
| 43 |
Electronics Assembly |
320 hrs | 2 mons | Fri 1/4/02 | Thu 2/28/02 | 0% |
| 8 |
Shelby Gott |
320 hrs | Fri 1/4/02 | Thu 2/28/02 | 0% | |
| 44 |
Electronics testing |
320 hrs | 2 mons | Fri 3/1/02 | Thu 4/25/02 | 0% |
| 8 |
Shelby Gott |
320 hrs | Fri 3/1/02 | Thu 4/25/02 | 0% | |
| 45 |
TV Guider |
972 hrs | 126 days | Mon 6/25/01 | Fri 12/14/01 | 30% |
| 46 |
Guider camera filter slide |
0 hrs | 3.4 mons | Thu 9/13/01 | Fri 12/14/01 | 0% |
| 47 |
Evaluation of ICCD's |
960 hrs | 3.9 mons | Mon 6/25/01 | Wed 10/10/01 | 30% |
| 1 |
Charles Corson |
624 hrs | Mon 6/25/01 | Wed 10/10/01 | 46% | |
| 17 |
Rich Reed |
336 hrs | Tue 8/14/01 | Wed 10/10/01 | 0% | |
| 48 |
Integrate into Linux Guider |
8 hrs | 1 day | Thu 10/11/01 | Thu 10/11/01 | 0% |
| 1 |
Charles Corson |
8 hrs | Thu 10/11/01 | Thu 10/11/01 | 0% | |
| 49 |
On-sky Test at CASS |
4 hrs | 0.5 days | Fri 10/12/01 | Fri 10/12/01 | 0% |
| 1 |
Charles Corson |
4 hrs | Fri 10/12/01 | Fri 10/12/01 | 0% | |
| 50 |
Re-Imager |
2,936 hrs | 279 days? | Mon 4/16/01 | Wed 5/8/02 | 35% |
| 51 |
Re-imager drawings from UW to WIYN |
640 hrs | 2.15 mons | Mon 10/1/01 | Wed 11/28/01 | 85% |
| 2 |
Chris Anderson |
320 hrs | Mon 10/1/01 | Fri 11/23/01 | 85% | |
| 16 |
Rick Williams |
320 hrs | Mon 10/1/01 | Wed 11/28/01 | 85% | |
| 52 |
Focus/Telescope Surface Study |
640 hrs | 2 mons | Mon 10/8/01 | Tue 12/4/01 | 0% |
| 6 |
Art Code |
320 hrs | Thu 10/11/01 | Tue 12/4/01 | 0% | |
| 7 |
Phil Lamb |
320 hrs | Thu 10/11/01 | Tue 12/4/01 | 0% | |
| 53 |
Cass Re-Imager Coating |
1,440 hrs | 9 mons? | Wed 8/1/01 | Mon 4/8/02 | 30% |
| 1 |
Charles Corson |
1,440 hrs | Wed 8/1/01 | Mon 4/8/02 | 30% | |
| 54 |
Collimation Procedure |
160 hrs | 4 wks? | Tue 4/9/02 | Mon 5/6/02 | 0% |
| 1 |
Charles Corson |
160 hrs | Tue 4/9/02 | Mon 5/6/02 | 0% | |
| 55 |
Tests for Opt/Mech Axis Alignment |
16 hrs | 2 days | Tue 5/7/02 | Wed 5/8/02 | 0% |
| 1 |
Charles Corson |
16 hrs | Tue 5/7/02 | Wed 5/8/02 | 0% | |
| 56 |
Understand Spider
Mis-alignment |
40 hrs | 3 days | Mon 4/16/01 | Wed 4/18/01 | 100% |
| 57 |
Obtain drawings |
16 hrs | 2 days | Mon 4/16/01 | Tue 4/17/01 | 100% |
| 1 |
Charles Corson |
16 hrs | Mon 4/16/01 | Tue 4/17/01 | 100% | |
| 58 |
Investigate mountings |
24 hrs | 3 days | Mon 4/16/01 | Wed 4/18/01 | 100% |
| 1 |
Charles Corson |
24 hrs | Mon 4/16/01 | Wed 4/18/01 | 100% | |
| 59 |
Calibration Illumination Assembly
(CIA) |
2,160 hrs | 192 days? | Mon 6/4/01 | Mon 2/25/02 | 39% |
| 60 |
CIA Document |
40 hrs | 5 days | Mon 6/4/01 | Fri 6/8/01 | 100% |
| 1 |
Charles Corson |
40 hrs | Mon 6/4/01 | Fri 6/8/01 | 100% | |
| 61 |
WTTM-based design |
80 hrs | 2 wks? | Thu 8/2/01 | Wed 8/15/01 | 100% |
| 1 |
Charles Corson |
80 hrs | Thu 8/2/01 | Wed 8/15/01 | 100% | |
| 62 |
Conceptual design |
480 hrs | 3 mons | Thu 8/16/01 | Wed 11/7/01 | 95% |
| 2 |
Chris Anderson |
480 hrs | Thu 8/16/01 | Wed 11/7/01 | 95% | |
| 63 |
Mechanical design |
160 hrs | 1 mon | Thu 11/8/01 | Tue 12/4/01 | 0% |
| 15 |
Scott Buckley |
160 hrs | Thu 11/8/01 | Tue 12/4/01 | 0% | |
| 64 |
Calibration lamp overfill study |
1,080 hrs | 9 wks | Fri 9/14/01 | Thu 11/15/01 | 25% |
| 1 |
Charles Corson |
360 hrs | Fri 9/14/01 | Thu 11/15/01 | 25% | |
| 5 |
Jeff Snyder |
360 hrs | Fri 9/14/01 | Thu 11/15/01 | 25% | |
| 18 |
Chuck Claver |
360 hrs | Fri 9/14/01 | Thu 11/15/01 | 25% | |
| 65 |
Comparison Lamps |
320 hrs | 2 mons? | Tue 1/1/02 | Mon 2/25/02 | 0% |
| 1 |
Charles Corson |
320 hrs | Tue 1/1/02 | Mon 2/25/02 | 0% | |
| 66 |
Cabling and Site
Installation |
680 hrs | 40 days | Fri 3/1/02 | Thu 4/25/02 | 0% |
| 67 |
Cable wraps |
40 hrs | 1 wk | Fri 3/1/02 | Thu 3/7/02 | 0% |
| 19 |
Rodger McIntyre |
40 hrs | Fri 3/1/02 | Thu 3/7/02 | 0% | |
| 68 |
Installation fixtures and
equipment |
640 hrs | 2 mons | Fri 3/1/02 | Thu 4/25/02 | 0% |
| 1 |
Charles Corson |
320 hrs | Fri 3/1/02 | Thu 4/25/02 | 0% | |
| 8 |
Shelby Gott |
320 hrs | Fri 3/1/02 | Thu 4/25/02 | 0% | |
| 69 |
Rotator encoder and position
control |
2,104 hrs | 120 days | Mon 9/17/01 | Thu 2/28/02 | 6% |
| 70 |
Concept of rotator encoder |
184 hrs | 1 mon | Mon 9/17/01 | Fri 10/12/01 | 74% |
| 13 |
Jeff Percival |
160 hrs | Mon 9/17/01 | Fri 10/12/01 | 85% | |
| 20 |
Don Bucholz |
24 hrs | Wed 10/10/01 | Fri 10/12/01 | 0% | |
| 71 |
Define method for rotator control |
320 hrs | 4 wks | Mon 10/15/01 | Fri 11/9/01 | 0% |
| 8 |
Shelby Gott |
160 hrs | Mon 10/15/01 | Fri 11/9/01 | 0% | |
| 13 |
Jeff Percival |
160 hrs | Mon 10/15/01 | Fri 11/9/01 | 0% | |
| 72 |
Specification of rotator accuracy |
480 hrs | 4 wks | Mon 11/12/01 | Thu 12/6/01 | 0% |
| 2 |
Chris Anderson |
160 hrs | Mon 11/12/01 | Thu 12/6/01 | 0% | |
| 8 |
Shelby Gott |
160 hrs | Mon 11/12/01 | Thu 12/6/01 | 0% | |
| 13 |
Jeff Percival |
160 hrs | Mon 11/12/01 | Thu 12/6/01 | 0% | |
| 73 |
Rotator assembly & testing |
960 hrs | 2 mons | Fri 12/7/01 | Thu 1/31/02 | 0% |
| 2 |
Chris Anderson |
320 hrs | Fri 12/7/01 | Thu 1/31/02 | 0% | |
| 8 |
Shelby Gott |
320 hrs | Fri 12/7/01 | Thu 1/31/02 | 0% | |
| 13 |
Jeff Percival |
320 hrs | Fri 12/7/01 | Thu 1/31/02 | 0% | |
| 74 |
Ship rotator to NOAO |
0 hrs | 0 wks | Thu 1/31/02 | Thu 1/31/02 | 0% |
| 2 |
Chris Anderson |
0 hrs | Thu 1/31/02 | Thu 1/31/02 | 0% | |
| 8 |
Shelby Gott |
0 hrs | Thu 1/31/02 | Thu 1/31/02 | 0% | |
| 13 |
Jeff Percival |
0 hrs | Thu 1/31/02 | Thu 1/31/02 | 0% | |
| 75 |
Algorithm for setting rotator angle with
TCS input |
160 hrs | 4 wks | Fri 2/1/02 | Thu 2/28/02 | 0% |
| 14 |
Behzad Abareshi |
160 hrs | Fri 2/1/02 | Thu 2/28/02 | 0% | |
| 76 |
Outrigger bars |
600 hrs | 20 days? | Mon 10/29/01 | Fri 11/23/01 | 0% |
| 77 |
Check need to watch for friction |
40 hrs | 1 wk | Mon 10/29/01 | Fri 11/2/01 | 0% |
| 16 |
Rick Williams |
40 hrs | Mon 10/29/01 | Fri 11/2/01 | 0% | |
| 78 |
Check if need to seal bars |
160 hrs | 2 wks? | Mon 10/29/01 | Fri 11/9/01 | 0% |
| 2 |
Chris Anderson |
80 hrs | Mon 10/29/01 | Fri 11/9/01 | 0% | |
| 16 |
Rick Williams |
80 hrs | Mon 10/29/01 | Fri 11/9/01 | 0% | |
| 79 |
PM procedure for cleaning and
lubrication |
320 hrs | 4 wks? | Mon 10/29/01 | Fri 11/23/01 | 0% |
| 2 |
Chris Anderson |
160 hrs | Mon 10/29/01 | Fri 11/23/01 | 0% | |
| 22 |
Rick Willams |
160 hrs | Mon 10/29/01 | Fri 11/23/01 | 0% | |
| 80 |
Check if THK motors are sealed |
80 hrs | 1 wk? | Mon 11/5/01 | Fri 11/9/01 | 0% |
| 2 |
Chris Anderson |
40 hrs | Mon 11/5/01 | Fri 11/9/01 | 0% | |
| 16 |
Rick Williams |
40 hrs | Mon 11/5/01 | Fri 11/9/01 | 0% | |
| 81 |
Software |
2,981.2 hrs | 111 days | Mon 10/1/01 | Fri 3/1/02 | 0% |
| 8 |
Shelby Gott |
888 hrs | Mon 10/1/01 | Fri 3/1/02 | 0% | |
| 10 |
Dave Mills |
133.2 hrs | Mon 10/1/01 | Fri 3/1/02 | 0% | |
| 82 |
TCS software |
160 hrs | 1 mon | Mon 2/4/02 | Fri 3/1/02 | 0% |
| 14 |
Behzad Abareshi |
160 hrs | Mon 2/4/02 | Fri 3/1/02 | 0% | |
| 83 |
Electronics software |
800 hrs | 5 mons | Mon 10/1/01 | Thu 2/14/02 | 0% |
| 8 |
Shelby Gott |
800 hrs | Mon 10/1/01 | Thu 2/14/02 | 0% | |
| 84 |
Rotator software |
1,000 hrs | 5 mons | Mon 10/1/01 | Thu 2/14/02 | 0% |
| 13 |
Jeff Percival |
800 hrs | Mon 10/1/01 | Thu 2/14/02 | 0% | |
| 14 |
Behzad Abareshi |
200 hrs | Mon 10/1/01 | Thu 2/14/02 | 0% | |
| 85 |
Handling Cart |
188 hrs | 23.5 days? | Mon 1/7/02 | Thu 2/7/02 | 0% |
| 86 |
Acquire basic measurements |
4 hrs | 0.5 days | Mon 1/7/02 | Mon 1/7/02 | 0% |
| 1 |
Charles Corson |
4 hrs | Mon 1/7/02 | Mon 1/7/02 | 0% | |
| 87 |
Create sketch of CassIAS U-cart |
12 hrs | 1.5 days | Mon 1/7/02 | Tue 1/8/02 | 0% |
| 1 |
Charles Corson |
12 hrs | Mon 1/7/02 | Tue 1/8/02 | 0% | |
| 88 |
Mechanical sketch created |
12 hrs | 1.5 days | Wed 1/9/02 | Thu 1/10/02 | 0% |
| 1 |
Charles Corson |
12 hrs | Wed 1/9/02 | Thu 1/10/02 | 0% | |
| 89 |
Fabrication of cart |
160 hrs | 4 wks? | Thu 1/10/02 | Thu 2/7/02 | 0% |
| 3 |
machinist |
160 hrs | Thu 1/10/02 | Thu 2/7/02 | 0% | |
| 90 |
Final Assembly |
224 hrs | 7 days | Fri 4/26/02 | Mon 5/6/02 | 0% |
| 1 |
Charles Corson |
56 hrs | Fri 4/26/02 | Mon 5/6/02 | 0% | |
| 6 |
Art Code |
56 hrs | Fri 4/26/02 | Mon 5/6/02 | 0% | |
| 91 |
Alignment of CassIAS |
112 hrs | 7 days | Fri 4/26/02 | Mon 5/6/02 | 0% |
| 1 |
Charles Corson |
56 hrs | Fri 4/26/02 | Mon 5/6/02 | 0% | |
| 6 |
Art Code |
56 hrs | Fri 4/26/02 | Mon 5/6/02 | 0% | |
| 92 |
Delivery of CassIAS & rotator to
WIYN |
0 hrs | 0 days | Mon 5/6/02 | Mon 5/6/02 | 0% |
| 1 |
Charles Corson |
0 hrs | Mon 5/6/02 | Mon 5/6/02 | 0% | |
| 6 |
Art Code |
0 hrs | Mon 5/6/02 | Mon 5/6/02 | 0% | |
| 93 |
Definition of Spares List |
960 hrs | 2 mons | Mon 3/4/02 | Fri 4/26/02 | 0% |
| 1 |
Charles Corson |
320 hrs | Mon 3/4/02 | Fri 4/26/02 | 0% | |
| 2 |
Chris Anderson |
320 hrs | Mon 3/4/02 | Fri 4/26/02 | 0% | |
| 8 |
Shelby Gott |
320 hrs | Mon 3/4/02 | Fri 4/26/02 | 0% | |
| 94 |
Commissioning of CassIAS |
1,344 hrs | 155 days | Fri 10/5/01 | Wed 5/8/02 | 11% |
| 95 |
Commission Plan and Definition |
1,008 hrs | 6.3 mons | Fri 10/5/01 | Thu 3/28/02 | 15% |
| 9 |
George Jacoby |
1,008 hrs | Fri 10/5/01 | Thu 3/28/02 | 15% | |
| 96 |
Define Acceptance Criteria |
320 hrs | 2 mons | Mon 11/26/01 | Thu 1/17/02 | 0% |
| 9 |
George Jacoby |
320 hrs | Mon 11/26/01 | Thu 1/17/02 | 0% | |
| 97 |
Build Focus Dependency Map |
16 hrs | 2 days | Tue 5/7/02 | Wed 5/8/02 | 0% |
| 1 |
Charles Corson |
16 hrs | Tue 5/7/02 | Wed 5/8/02 | 0% | |
| 98 |
Commission CassIAS |
0 hrs | 0 days | Wed 5/8/02 | Wed 5/8/02 | 0% |