CassIAS_v3


Project Start Date: Mon 4/16/01
Project Finish Date: Wed 5/8/02

Tasks with Assignments

ID
Task Name
Work Duration Start Finish % Work Complete
1
Recharge PSL contract
0 hrs 1 day Mon 4/16/01 Mon 4/16/01 100%
2
Deliver drawings in AutoCad
0 hrs 2 wks? Sat 6/16/01 Fri 6/29/01 100%
3
Backviewing optics
248 hrs 114 days Wed 5/16/01 Mon 10/22/01 84%
4
Check Yale spectrograph vs. focal distance
40 hrs 1 wk Tue 10/16/01 Mon 10/22/01 0%
5
Jeff Snyder
40 hrs   Tue 10/16/01 Mon 10/22/01 0%
5
Check Yale spectrograph need for pellicle
208 hrs 5.2 wks Wed 5/16/01 Wed 6/20/01 100%
5
Jeff Snyder
208 hrs   Wed 5/16/01 Wed 6/20/01 100%
6
Mechanical
5,120 hrs 113 days? Wed 8/1/01 Thu 1/3/02 43%
7
Mechanical procurement and alignment
1,920 hrs 4 mons Wed 8/1/01 Tue 11/20/01 85%
2
Chris Anderson
640 hrs   Wed 8/1/01 Tue 11/20/01 85%
15
Scott Buckley
640 hrs   Wed 8/1/01 Tue 11/20/01 85%
16
Rick Williams
640 hrs   Wed 8/1/01 Tue 11/20/01 85%
8
Anodization
240 hrs 2 wks Wed 11/21/01 Mon 12/3/01 0%
2
Chris Anderson
80 hrs   Wed 11/21/01 Mon 12/3/01 0%
15
Scott Buckley
80 hrs   Wed 11/21/01 Mon 12/3/01 0%
16
Rick Williams
80 hrs   Wed 11/21/01 Mon 12/3/01 0%
9
Access panel to reach ICCD
1,280 hrs 2 mons Mon 9/3/01 Fri 10/26/01 35%
1
Charles Corson
320 hrs   Mon 9/3/01 Fri 10/26/01 35%
2
Chris Anderson
320 hrs   Mon 9/3/01 Fri 10/26/01 35%
8
Shelby Gott
320 hrs   Mon 9/3/01 Fri 10/26/01 35%
15
Scott Buckley
320 hrs   Mon 9/3/01 Fri 10/26/01 35%
10
Outrigger bars
600 hrs 20 days? Mon 10/29/01 Fri 11/23/01 0%
11
Check need to watch for friction
40 hrs 1 wk Mon 10/29/01 Fri 11/2/01 0%
16
Rick Williams
40 hrs   Mon 10/29/01 Fri 11/2/01 0%
12
Check if need to seal bars
160 hrs 2 wks? Mon 10/29/01 Fri 11/9/01 0%
2
Chris Anderson
80 hrs   Mon 10/29/01 Fri 11/9/01 0%
16
Rick Williams
80 hrs   Mon 10/29/01 Fri 11/9/01 0%
13
PM procedure for cleaning and lubrication
320 hrs 4 wks? Mon 10/29/01 Fri 11/23/01 0%
2
Chris Anderson
160 hrs   Mon 10/29/01 Fri 11/23/01 0%
22
Rick Willams
160 hrs   Mon 10/29/01 Fri 11/23/01 0%
14
Check if THK motors are sealed
80 hrs 1 wk? Mon 11/5/01 Fri 11/9/01 0%
2
Chris Anderson
40 hrs   Mon 11/5/01 Fri 11/9/01 0%
16
Rick Williams
40 hrs   Mon 11/5/01 Fri 11/9/01 0%
15
Lab Testing/Verification
1,080 hrs 47 days Thu 11/1/01 Thu 1/3/02 10%
16
Initial Assembly
120 hrs 1 wk Thu 11/1/01 Wed 11/7/01 90%
2
Chris Anderson
40 hrs   Thu 11/1/01 Wed 11/7/01 90%
15
Scott Buckley
40 hrs   Thu 11/1/01 Wed 11/7/01 90%
16
Rick Williams
40 hrs   Thu 11/1/01 Wed 11/7/01 90%
17
Functional tests at UW
360 hrs 3 wks Thu 11/8/01 Wed 11/28/01 0%
2
Chris Anderson
120 hrs   Thu 11/8/01 Wed 11/28/01 0%
15
Scott Buckley
120 hrs   Thu 11/8/01 Wed 11/28/01 0%
16
Rick Williams
120 hrs   Thu 11/8/01 Wed 11/28/01 0%
18
Rework Machining
120 hrs 1 wk Fri 12/7/01 Thu 12/13/01 0%
2
Chris Anderson
40 hrs   Fri 12/7/01 Thu 12/13/01 0%
15
Scott Buckley
40 hrs   Fri 12/7/01 Thu 12/13/01 0%
16
Rick Williams
40 hrs   Fri 12/7/01 Thu 12/13/01 0%
19
Final Mechanical Assembly
480 hrs 1 mon Fri 12/7/01 Thu 1/3/02 0%
2
Chris Anderson
160 hrs   Fri 12/7/01 Thu 1/3/02 0%
15
Scott Buckley
160 hrs   Fri 12/7/01 Thu 1/3/02 0%
16
Rick Williams
160 hrs   Fri 12/7/01 Thu 1/3/02 0%
20
Shipping Crate
188 hrs 24 days? Mon 12/3/01 Thu 1/3/02 0%
21
Acquire basic measurements
4 hrs 0.25 days Mon 12/3/01 Mon 12/3/01 0%
15
Scott Buckley
2 hrs   Mon 12/3/01 Mon 12/3/01 0%
16
Rick Williams
2 hrs   Mon 12/3/01 Mon 12/3/01 0%
22
Create sketch of CassIAS crate
12 hrs 0.75 days Mon 12/3/01 Mon 12/3/01 0%
15
Scott Buckley
6 hrs   Mon 12/3/01 Mon 12/3/01 0%
16
Rick Williams
6 hrs   Mon 12/3/01 Mon 12/3/01 0%
23
Mechanical sketch created
12 hrs 0.75 days Tue 12/4/01 Tue 12/4/01 0%
15
Scott Buckley
6 hrs   Tue 12/4/01 Tue 12/4/01 0%
16
Rick Williams
6 hrs   Tue 12/4/01 Tue 12/4/01 0%
24
Fabrication of crate
160 hrs 2 wks? Tue 12/4/01 Tue 12/18/01 0%
15
Scott Buckley
80 hrs   Tue 12/4/01 Tue 12/18/01 0%
16
Rick Williams
80 hrs   Tue 12/4/01 Tue 12/18/01 0%
25
Delivery of CassIAS to NOAO
0 hrs 0 days Thu 1/3/02 Thu 1/3/02 0%
15
Scott Buckley
0 hrs   Thu 1/3/02 Thu 1/3/02 0%
16
Rick Williams
0 hrs   Thu 1/3/02 Thu 1/3/02 0%
26
Electronics
6,944 hrs 170 days? Mon 9/3/01 Thu 4/25/02 19%
11
Shebly Gott
1,280 hrs   Mon 9/17/01 Thu 4/25/02 19%
27
Limit switches
1,240 hrs 65 days? Mon 9/17/01 Thu 12/13/01 34%
28
Specify limit switches
40 hrs 1 wk? Mon 9/17/01 Fri 9/21/01 100%
11
Shebly Gott
40 hrs   Mon 9/17/01 Fri 9/21/01 100%
29
Define switches functional design
480 hrs 3 mons Mon 9/24/01 Thu 12/13/01 20%
8
Shelby Gott
480 hrs   Mon 9/24/01 Thu 12/13/01 20%
30
Guard against driving past limit
640 hrs 2 mons Mon 9/17/01 Fri 11/9/01 40%
1
Charles Corson
320 hrs   Mon 9/17/01 Fri 11/9/01 40%
2
Chris Anderson
320 hrs   Mon 9/17/01 Fri 11/9/01 40%
31
Test motor torques
80 hrs 2 wks? Fri 10/5/01 Thu 10/18/01 30%
2
Chris Anderson
80 hrs   Fri 10/5/01 Thu 10/18/01 30%
32
Electronics/Motor ventilation
960 hrs 2 mons Mon 9/3/01 Fri 10/26/01 25%
1
Charles Corson
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
2
Chris Anderson
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
8
Shelby Gott
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
33
Electronics Box
3,464 hrs 170 days? Mon 9/3/01 Thu 4/25/02 13%
1
Charles Corson
1,296 hrs   Thu 9/13/01 Thu 4/25/02 9%
34
Mech engineering
1,120 hrs 48 days? Mon 9/3/01 Wed 11/7/01 21%
35
Cable drape tie-off
80 hrs 1 wk Thu 11/1/01 Wed 11/7/01 0%
15
Scott Buckley
40 hrs   Thu 11/1/01 Wed 11/7/01 0%
16
Rick Williams
40 hrs   Thu 11/1/01 Wed 11/7/01 0%
36
Support from housing
80 hrs 1 wk? Thu 11/1/01 Wed 11/7/01 0%
15
Scott Buckley
40 hrs   Thu 11/1/01 Wed 11/7/01 0%
16
Rick Williams
40 hrs   Thu 11/1/01 Wed 11/7/01 0%
37
Electronics/Motor ventilation
960 hrs 2 mons Mon 9/3/01 Fri 10/26/01 25%
1
Charles Corson
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
2
Chris Anderson
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
8
Shelby Gott
320 hrs   Mon 9/3/01 Fri 10/26/01 25%
38
STD bus vs. Linux
80 hrs 1 wk? Thu 9/13/01 Wed 9/19/01 100%
1
Charles Corson
40 hrs   Thu 9/13/01 Wed 9/19/01 100%
8
Shelby Gott
40 hrs   Thu 9/13/01 Wed 9/19/01 100%
39
Procure STD bus/chassis (or Linux)
240 hrs 3 wks? Thu 11/1/01 Wed 11/21/01 0%
1
Charles Corson
120 hrs   Thu 11/1/01 Wed 11/21/01 0%
8
Shelby Gott
120 hrs   Thu 11/1/01 Wed 11/21/01 0%
40
Identify power supplies for box
8 hrs 1 day? Thu 11/22/01 Thu 11/22/01 0%
8
Shelby Gott
8 hrs   Thu 11/22/01 Thu 11/22/01 0%
41
Specify connectors for Rick
40 hrs 1 wk? Thu 11/22/01 Wed 11/28/01 0%
8
Shelby Gott
40 hrs   Thu 11/22/01 Wed 11/28/01 0%
42
Assemble STD bus (or Linux)
40 hrs 1 wk? Thu 11/22/01 Wed 11/28/01 0%
8
Shelby Gott
40 hrs   Thu 11/22/01 Wed 11/28/01 0%
43
Electronics Assembly
320 hrs 2 mons Fri 1/4/02 Thu 2/28/02 0%
8
Shelby Gott
320 hrs   Fri 1/4/02 Thu 2/28/02 0%
44
Electronics testing
320 hrs 2 mons Fri 3/1/02 Thu 4/25/02 0%
8
Shelby Gott
320 hrs   Fri 3/1/02 Thu 4/25/02 0%
45
TV Guider
972 hrs 126 days Mon 6/25/01 Fri 12/14/01 30%
46
Guider camera filter slide
0 hrs 3.4 mons Thu 9/13/01 Fri 12/14/01 0%
47
Evaluation of ICCD's
960 hrs 3.9 mons Mon 6/25/01 Wed 10/10/01 30%
1
Charles Corson
624 hrs   Mon 6/25/01 Wed 10/10/01 46%
17
Rich Reed
336 hrs   Tue 8/14/01 Wed 10/10/01 0%
48
Integrate into Linux Guider
8 hrs 1 day Thu 10/11/01 Thu 10/11/01 0%
1
Charles Corson
8 hrs   Thu 10/11/01 Thu 10/11/01 0%
49
On-sky Test at CASS
4 hrs 0.5 days Fri 10/12/01 Fri 10/12/01 0%
1
Charles Corson
4 hrs   Fri 10/12/01 Fri 10/12/01 0%
50
Re-Imager
2,936 hrs 279 days? Mon 4/16/01 Wed 5/8/02 35%
51
Re-imager drawings from UW to WIYN
640 hrs 2.15 mons Mon 10/1/01 Wed 11/28/01 85%
2
Chris Anderson
320 hrs   Mon 10/1/01 Fri 11/23/01 85%
16
Rick Williams
320 hrs   Mon 10/1/01 Wed 11/28/01 85%
52
Focus/Telescope Surface Study
640 hrs 2 mons Mon 10/8/01 Tue 12/4/01 0%
6
Art Code
320 hrs   Thu 10/11/01 Tue 12/4/01 0%
7
Phil Lamb
320 hrs   Thu 10/11/01 Tue 12/4/01 0%
53
Cass Re-Imager Coating
1,440 hrs 9 mons? Wed 8/1/01 Mon 4/8/02 30%
1
Charles Corson
1,440 hrs   Wed 8/1/01 Mon 4/8/02 30%
54
Collimation Procedure
160 hrs 4 wks? Tue 4/9/02 Mon 5/6/02 0%
1
Charles Corson
160 hrs   Tue 4/9/02 Mon 5/6/02 0%
55
Tests for Opt/Mech Axis Alignment
16 hrs 2 days Tue 5/7/02 Wed 5/8/02 0%
1
Charles Corson
16 hrs   Tue 5/7/02 Wed 5/8/02 0%
56
Understand Spider Mis-alignment
40 hrs 3 days Mon 4/16/01 Wed 4/18/01 100%
57
Obtain drawings
16 hrs 2 days Mon 4/16/01 Tue 4/17/01 100%
1
Charles Corson
16 hrs   Mon 4/16/01 Tue 4/17/01 100%
58
Investigate mountings
24 hrs 3 days Mon 4/16/01 Wed 4/18/01 100%
1
Charles Corson
24 hrs   Mon 4/16/01 Wed 4/18/01 100%
59
Calibration Illumination Assembly (CIA)
2,160 hrs 192 days? Mon 6/4/01 Mon 2/25/02 39%
60
CIA Document
40 hrs 5 days Mon 6/4/01 Fri 6/8/01 100%
1
Charles Corson
40 hrs   Mon 6/4/01 Fri 6/8/01 100%
61
WTTM-based design
80 hrs 2 wks? Thu 8/2/01 Wed 8/15/01 100%
1
Charles Corson
80 hrs   Thu 8/2/01 Wed 8/15/01 100%
62
Conceptual design
480 hrs 3 mons Thu 8/16/01 Wed 11/7/01 95%
2
Chris Anderson
480 hrs   Thu 8/16/01 Wed 11/7/01 95%
63
Mechanical design
160 hrs 1 mon Thu 11/8/01 Tue 12/4/01 0%
15
Scott Buckley
160 hrs   Thu 11/8/01 Tue 12/4/01 0%
64
Calibration lamp overfill study
1,080 hrs 9 wks Fri 9/14/01 Thu 11/15/01 25%
1
Charles Corson
360 hrs   Fri 9/14/01 Thu 11/15/01 25%
5
Jeff Snyder
360 hrs   Fri 9/14/01 Thu 11/15/01 25%
18
Chuck Claver
360 hrs   Fri 9/14/01 Thu 11/15/01 25%
65
Comparison Lamps
320 hrs 2 mons? Tue 1/1/02 Mon 2/25/02 0%
1
Charles Corson
320 hrs   Tue 1/1/02 Mon 2/25/02 0%
66
Cabling and Site Installation
680 hrs 40 days Fri 3/1/02 Thu 4/25/02 0%
67
Cable wraps
40 hrs 1 wk Fri 3/1/02 Thu 3/7/02 0%
19
Rodger McIntyre
40 hrs   Fri 3/1/02 Thu 3/7/02 0%
68
Installation fixtures and equipment
640 hrs 2 mons Fri 3/1/02 Thu 4/25/02 0%
1
Charles Corson
320 hrs   Fri 3/1/02 Thu 4/25/02 0%
8
Shelby Gott
320 hrs   Fri 3/1/02 Thu 4/25/02 0%
69
Rotator encoder and position control
2,104 hrs 120 days Mon 9/17/01 Thu 2/28/02 6%
70
Concept of rotator encoder
184 hrs 1 mon Mon 9/17/01 Fri 10/12/01 74%
13
Jeff Percival
160 hrs   Mon 9/17/01 Fri 10/12/01 85%
20
Don Bucholz
24 hrs   Wed 10/10/01 Fri 10/12/01 0%
71
Define method for rotator control
320 hrs 4 wks Mon 10/15/01 Fri 11/9/01 0%
8
Shelby Gott
160 hrs   Mon 10/15/01 Fri 11/9/01 0%
13
Jeff Percival
160 hrs   Mon 10/15/01 Fri 11/9/01 0%
72
Specification of rotator accuracy
480 hrs 4 wks Mon 11/12/01 Thu 12/6/01 0%
2
Chris Anderson
160 hrs   Mon 11/12/01 Thu 12/6/01 0%
8
Shelby Gott
160 hrs   Mon 11/12/01 Thu 12/6/01 0%
13
Jeff Percival
160 hrs   Mon 11/12/01 Thu 12/6/01 0%
73
Rotator assembly & testing
960 hrs 2 mons Fri 12/7/01 Thu 1/31/02 0%
2
Chris Anderson
320 hrs   Fri 12/7/01 Thu 1/31/02 0%
8
Shelby Gott
320 hrs   Fri 12/7/01 Thu 1/31/02 0%
13
Jeff Percival
320 hrs   Fri 12/7/01 Thu 1/31/02 0%
74
Ship rotator to NOAO
0 hrs 0 wks Thu 1/31/02 Thu 1/31/02 0%
2
Chris Anderson
0 hrs   Thu 1/31/02 Thu 1/31/02 0%
8
Shelby Gott
0 hrs   Thu 1/31/02 Thu 1/31/02 0%
13
Jeff Percival
0 hrs   Thu 1/31/02 Thu 1/31/02 0%
75
Algorithm for setting rotator angle with TCS input
160 hrs 4 wks Fri 2/1/02 Thu 2/28/02 0%
14
Behzad Abareshi
160 hrs   Fri 2/1/02 Thu 2/28/02 0%
76
Outrigger bars
600 hrs 20 days? Mon 10/29/01 Fri 11/23/01 0%
77
Check need to watch for friction
40 hrs 1 wk Mon 10/29/01 Fri 11/2/01 0%
16
Rick Williams
40 hrs   Mon 10/29/01 Fri 11/2/01 0%
78
Check if need to seal bars
160 hrs 2 wks? Mon 10/29/01 Fri 11/9/01 0%
2
Chris Anderson
80 hrs   Mon 10/29/01 Fri 11/9/01 0%
16
Rick Williams
80 hrs   Mon 10/29/01 Fri 11/9/01 0%
79
PM procedure for cleaning and lubrication
320 hrs 4 wks? Mon 10/29/01 Fri 11/23/01 0%
2
Chris Anderson
160 hrs   Mon 10/29/01 Fri 11/23/01 0%
22
Rick Willams
160 hrs   Mon 10/29/01 Fri 11/23/01 0%
80
Check if THK motors are sealed
80 hrs 1 wk? Mon 11/5/01 Fri 11/9/01 0%
2
Chris Anderson
40 hrs   Mon 11/5/01 Fri 11/9/01 0%
16
Rick Williams
40 hrs   Mon 11/5/01 Fri 11/9/01 0%
81
Software
2,981.2 hrs 111 days Mon 10/1/01 Fri 3/1/02 0%
8
Shelby Gott
888 hrs   Mon 10/1/01 Fri 3/1/02 0%
10
Dave Mills
133.2 hrs   Mon 10/1/01 Fri 3/1/02 0%
82
TCS software
160 hrs 1 mon Mon 2/4/02 Fri 3/1/02 0%
14
Behzad Abareshi
160 hrs   Mon 2/4/02 Fri 3/1/02 0%
83
Electronics software
800 hrs 5 mons Mon 10/1/01 Thu 2/14/02 0%
8
Shelby Gott
800 hrs   Mon 10/1/01 Thu 2/14/02 0%
84
Rotator software
1,000 hrs 5 mons Mon 10/1/01 Thu 2/14/02 0%
13
Jeff Percival
800 hrs   Mon 10/1/01 Thu 2/14/02 0%
14
Behzad Abareshi
200 hrs   Mon 10/1/01 Thu 2/14/02 0%
85
Handling Cart
188 hrs 23.5 days? Mon 1/7/02 Thu 2/7/02 0%
86
Acquire basic measurements
4 hrs 0.5 days Mon 1/7/02 Mon 1/7/02 0%
1
Charles Corson
4 hrs   Mon 1/7/02 Mon 1/7/02 0%
87
Create sketch of CassIAS U-cart
12 hrs 1.5 days Mon 1/7/02 Tue 1/8/02 0%
1
Charles Corson
12 hrs   Mon 1/7/02 Tue 1/8/02 0%
88
Mechanical sketch created
12 hrs 1.5 days Wed 1/9/02 Thu 1/10/02 0%
1
Charles Corson
12 hrs   Wed 1/9/02 Thu 1/10/02 0%
89
Fabrication of cart
160 hrs 4 wks? Thu 1/10/02 Thu 2/7/02 0%
3
machinist
160 hrs   Thu 1/10/02 Thu 2/7/02 0%
90
Final Assembly
224 hrs 7 days Fri 4/26/02 Mon 5/6/02 0%
1
Charles Corson
56 hrs   Fri 4/26/02 Mon 5/6/02 0%
6
Art Code
56 hrs   Fri 4/26/02 Mon 5/6/02 0%
91
Alignment of CassIAS
112 hrs 7 days Fri 4/26/02 Mon 5/6/02 0%
1
Charles Corson
56 hrs   Fri 4/26/02 Mon 5/6/02 0%
6
Art Code
56 hrs   Fri 4/26/02 Mon 5/6/02 0%
92
Delivery of CassIAS & rotator to WIYN
0 hrs 0 days Mon 5/6/02 Mon 5/6/02 0%
1
Charles Corson
0 hrs   Mon 5/6/02 Mon 5/6/02 0%
6
Art Code
0 hrs   Mon 5/6/02 Mon 5/6/02 0%
93
Definition of Spares List
960 hrs 2 mons Mon 3/4/02 Fri 4/26/02 0%
1
Charles Corson
320 hrs   Mon 3/4/02 Fri 4/26/02 0%
2
Chris Anderson
320 hrs   Mon 3/4/02 Fri 4/26/02 0%
8
Shelby Gott
320 hrs   Mon 3/4/02 Fri 4/26/02 0%
94
Commissioning of CassIAS
1,344 hrs 155 days Fri 10/5/01 Wed 5/8/02 11%
95
Commission Plan and Definition
1,008 hrs 6.3 mons Fri 10/5/01 Thu 3/28/02 15%
9
George Jacoby
1,008 hrs   Fri 10/5/01 Thu 3/28/02 15%
96
Define Acceptance Criteria
320 hrs 2 mons Mon 11/26/01 Thu 1/17/02 0%
9
George Jacoby
320 hrs   Mon 11/26/01 Thu 1/17/02 0%
97
Build Focus Dependency Map
16 hrs 2 days Tue 5/7/02 Wed 5/8/02 0%
1
Charles Corson
16 hrs   Tue 5/7/02 Wed 5/8/02 0%
98
Commission CassIAS
0 hrs 0 days Wed 5/8/02 Wed 5/8/02 0%