Previous Article Next Article Table of Contents


Mayall 4-m Back On-line After Shutter Failure (1Mar96) (from KPNO, NOAO Newsletter No. 45, March 1996) In mid-October 1995 the gearbox that drives the dome shutter of the Mayall telescope was found to have damaged gears, and we were forced to suspend observing at the 4-m while we repaired it. Nightly operations resumed on 28 December 1995. We would like to describe the nature of the failure, the repair itself, and how the loss of observing opportunity was addressed. On 18 October, while searching for a noise that the dome shutter was making as it closed, the shutter gearbox was found to have damaged gears. The gears were damaged to such an extent that we judged it unsafe to continue to operate the shutter on a daily basis, as further use could have led to complete breakage of the gearbox and significant damage to the shutter. We decided to keep the 4-m dome open until the manufacturer was ready to repair the gearbox, or until we were forced to close the shutter because of threatening weather. After twelve nights--ten clear--our luck ran out. The night of 29/30 October saw the first storm of fall arrive on the tropical jet stream. After riding out a few drizzles during the night and morning--the Cassegrain cage was wrapped in a tarp and the top-end sheltered under the dome--the storm intensified, with embedded thunderstorms showing up on weather radar. We decided just before noon on 30 October to close. That afternoon the mountain received a strong rainstorm with the promised thunder and lightning; significant water damage would have resulted had the 4-m dome not been closed when it was. [Photo not included] While we were open, arrangements for the repair were made. As soon as we closed the shutter, removal of the gearbox began. Not suprisingly, the gearbox itself defined the critical path of the repair schedule. The manufacturer estimated eight weeks to fabricate new gears, which seemed like a long time until we learned that a complete gearbox would have taken five months to be manufactured. While the gearbox was off for repair, the motors, clutch and brake assemblies in the shutter mechanism were refurbished, and the shutter drive was carefully inspected and lubricated. Despite the usual surprises that come up in undertaking a project of this magnitude--e.g., the gearbox went out weighing 1100 lbs and came back weighing 650 lbs. more, requiring that we re-do our rigging to lift the gearbox into place--we met our goal of opening by year's end. The root cause of the failure appears simply to be due to wear over the nearly thirty years of use. The original gears were cast-iron with a hardened surface. When the hardening wears through, rapid wearing of the gears occurs with the teeth then easily breaking (see figure). All of the gears showed pitting from wear, an indication of surface fatigue failure, but without signs of scoring, which would indicate oil film failure due to excessive loads or aging lubricant. All of the bearings in the gearbox were worn out and were replaced at this time as well. The new gears are made of solid steel with superior wear properties. In addition, the two old motors--one for slow speed and one for fast--have been replaced with a single DC motor that ramps up to the set speed, thus placing less load on the gearbox when starting and stopping. The entire shutter system is under review to ensure that any potential failure modes that we have been unknowingly living with for decades will be corrected. Astronomers scheduled during the time that we expected to be closed were informed of the extraordinary circumstances. All were offered reimbursement of any direct expenses (such as non-refundable air-fare) that they had made in advance of their runs. They were asked if they would be available should we be finished before our projected opening date, and if they would like to be re-scheduled in spring 1996. Ultimately, by shortening the block assigned for DLIRIM proposals to five nights, we were able to fit in two programs from earlier in the semester. Five proposals canceled at the 4-m in fall 1995 have been scheduled in early spring 1996 after due consideration by the TAC when they met in November. Ironically, the noise that was heard that led us to take a careful look at the gearbox was still there when we were able to move the shutter again. The noise turned out to come from a piece of sheet-metal from one of the seals that had started to rub against the dome skin. That has been taken care of as well. A large number of personnel--both Kitt Peak and Tucson based--were involved in this repair. Thanks to their hard work and teamwork the telescope was ready for use by visiting astronomers essentially on the day projected back in October when we shipped the gearbox off for repair. They were also responsible for a significant amount of additional work done to the dome shutter while the gearbox was away to ensure reliable operation for years to come. We sincerely thank them for all of their efforts. Bruce Bohannan, Tony Abraham
Previous Article Next Article Table of Contents