Previous Article Next Article Table of Contents


WIYN Project Review: October 1994 (1Dec94) (from KPNO, NOAO Newsletter No. 40, 1 December 1994) Commissioning of the WIYN Observatory continues to unfold smoothly, as the Project begins the transition from telescope commissioning to instrument commissioning. The main optics systems continue to function quite well and routinely produce the best images on Kitt Peak. Whenever the telescope is operated at night, delivered image quality measurements are made at approximately 80^o elevation in the R band. For short (10 sec and less) exposures, image sizes are typically in the 0.6"-0.7" FWHM range. About 10% of the time, image sizes of 0.5" FWHM or less are measured. The image quality of longer exposures is still limited by open-loop tracking accuracy, but image sizes of 0.8" FWHM or smaller are often achieved over 60-120 s exposures. At present, the number of measurements is insufficient to assess the statistical significance of these image sizes. However, image quality measurements are being made 3-4 days per week, so a statistically meaningful determination should be available for publication in the next NOAO Newsletter. Image quality degradation at lower elevation appears to be consistent with known atmospheric effects, such as differential atmospheric refraction, and errors in the current open loop telescope focus lookup tables. These latter errors are not unexpected, since these lookup tables do not yet reflect the nightly thermal contraction of the telescope. Very simple closed loop lookup tables that are tied to telescope temperature will be implemented shortly. A more sophisticated closed loop focus adjustment based on measuring the actual focus in real time will be implemented in the Instrument Adaptor Subsystem next spring. As mentioned above, long exposure image quality continues to be limited by telescope tracking. Although telescope pointing has been improved to approximately 5" RMS over the whole sky, non-random errors in the current pointing model lead to position dependent open loop tracking errors which can be as high as 1"/min in some parts of the sky. However, by 15 November, an improved pointing model as well as closed loop guiding should be implemented. The MOS Nasymth port Wide Field Corrector (WFC) lenses were finally accepted in September. The lenses slightly exceed their original polishing specification. They are currently being AR coated by Continental Optical and are due back in Tucson in late November. The lenses will then be assembled into their cell and installed at the Observatory. Once the WFC is installed, the 1^o diameter field-of-view will be characterized photographically to assess the magnitude of residual optical aberrations and field distortions. The latter measurement is crucial for achieving accurate fiber positioning by MOS/Hydra. Unfortunately, since final MOS/Hydra installation and commissioning cannot begin until these measurements are made and WFC installation is now several months behind schedule, it now appears that MOS/Hydra will not be available for science operations until at least mid-May 1995. The WIYN Imager is making steady progress and should be available for shared-risk science operations by mid-March 1995. Deploying the Imager requires completing and commissioning three components: the Instrument Adaptor Subsystem (IAS), the Filter/Shutter Assembly (FSA), and the CCD detector system. The permanent IAS, which encompasses all the hardware for guiding, wavefront curvature sensing, and closed loop focusing on the WIYN Imager Nasymth port, is now scheduled for telescope installation in late February 1995 and commissioning completion by mid-March 1995. In August, Indiana University delivered a substitute IAS, which consists of a duplicate of the IAS outer shell and a single axis stage. A ICCD borrowed from KPNO has been mounted on this stage. This substitute IAS will allow the Project to start commissioning the FSA and the CCD detector system immediately. It will also be used as a closed loop guiding testbed. In September, the FSA was delivered to Indiana University. The FSA is currently being commissioned and interfaced to the Harcon CCD control software. As discussed elsewhere in this Newsletter, the initial WIYN Imager CCD detector will not be a KPNO Mini-Mosaic with 15 um pixels as originally planned but a thinned STIS 2048 X 2048 pixel device with 21 um (0.197") pixels. The University of Wisconsin Controls Group (UWCG) continues to work towards completing delivery of the control system and to support WIYN commissioning activities. Closed loop guiding remains the most significant undelivered capability at this writing but should be implemented by December 1994. Commissioning activities being supported include tuning main axis servo performance, diagnosing control system bugs revealed during commissioning operations, finishing documentation delivery, and transitioning the day-to-day maintenance of the control system to the KPNO based operations staff. This is expected to be completed by the end of 1994. Work continues on the WIYN control system graphical user interfaces (GUIs). UWCG supplied several engineering GUIs which are being used routinely by the WIYN and UWCG staff to diagnose control system problems. Several of the operations GUIs being implemented by the KPNO Mountain Programming Group are now in use during normal night-time operations. This GUI effort is scheduled to be completed in early 1995. The WIYN Observatory was officially dedicated on 15 October under memorable weather conditions. In the weeks leading up to this event, the WIYN Project staff spent many days cleaning up and organizing the Observatory, an effort which has already had great benefit for the Project beyond the Dedication event itself. The telescope is now routinely used 3-4 nights a week and it is anticipated that this will increase to 5-6 nights per week by the end of the year. To support this increase in night-time activities, the WIYN Project has trained a second Observing Technician, Bridget Watts. In recognition of the complex nature of this new facility, the WIYN Board approved the allocation of one week per month during the first year of science operations for engineering activities. This extended engineering time will be used for normal facility maintenance as well as to resolve problems that arise during the rest of the month. These nights will be allocated to specific consortium members and returned to the designated institution if no engineering is required or engineering tasks are completed early. The current major project scheduling milestones are: (1) complete closed loop guiding implementation by 15 November; (2) install WFC and begin photographic assessment of the wide-field by 1 December; (3) complete Imager commissioning, including IAS, FSA, and CCD detector commissioning by 15 March; (4) begin shared risk Imager operations by 1 April; (5) finish MOS/Hydra commissioning and begin shared risk MOS/Hydra operations by 15 May. Dave Silva
Previous Article Next Article Table of Contents