GNIRS RESTART REVIEW

July 20-21, 1999



 
 
 
AGENDA
COMMITTEE CHARGE
PRESENTATION


AGENDA

Tuesday, July 20
 
 
Time Section Event Presenter(s)
0800 Closed Review Committee Session  James Breckinridge
0830 I Introduction Sidney Wolff
0900 II Summary of Committee Report Items Sidney Wolff
0930 III Current Status of the GNIRS Project Neil Gaughan
1030 Break
1045 IV Project Overview - RR to Completion Neil Gaughan
1130 V Project Management Neil Gaughan
1200 Lunch
1300 Project Management (cont) Neil Gaughan
1400 VI GNIRS Configuration Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen
1430 Break
1445 GNIRS Configuration (cont) Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen
1700 End of First Day

Wednesday, July 21
 
Time Section Event Presenter(s)
0830 Meeting Start-up
0845 GNIRS Configuration (cont) Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen
1000 Break
1015 VII Risk Identification and Mitigation Plan Neil Gaughan
1100 VIII Conclusion Sidney Wolff
1200 Lunch
1300 IX Committee Caucus Chair - James Breckinridge


Restart Review Committee Charge





During October 1998 AURA held a thorough review of the GNIRS project after it was reported by NOAO and the USGP that GNIRS would substantially overrun its budget and delivery schedule. Among the recommendations of that overall project review was one to hold a Restart Review before formally deciding if the instrument should be allowed to proceed. The purpose of this Restart Review is expressed in the Executive Summary of the AURA review committee’s report, which states that,

“GNIRS should be restarted if a successful “restart review” can be completed. This review should be aimed at resolving technical/fabrication issues, cost and schedule issues, and the adequacy of the new GNIRS management and engineering team currently being assembled by NOAO. The Review panel concluded that such a “restart review” must be based upon a proper project technical management structure with well-defined roles and responsibilities. The intent of this review should be to show clearly and rigorously (1) that the GNIRS instrument, completed under NOAO’s project plan as presented to the Panel, will be a world-class device appropriate to the funds and time spent to develop it, and (2) that the GNIRS instrument will have operational capabilities (cool down time, alignment stability, etc.) which will make it an asset rather than a liability to the end user community.”

In this context, the Restart Review committee is charged to investigate the following questions -

1) What is NOAO’s current cost estimate to complete GNIRS and on what schedule?
2) Is this estimate consistent with NOAO’s planned resources over the duration of the GNIRS project?
3) Have the technical issues (AURA report attached for reference) identified by the AURA review committee been addressed adequately to permit continuation of GNIRS?
4) Does NOAO now have in place an appropriate management structure to track, plan, and control resources to ensure that GNIRS will be delivered on time and budget?
5) Are there any approaches to designing and fabricating GNIRS that can significantly accelerate the planned delivery, e.g., through the injection of additional NOAO resources, outsourcing the fabrication of components, etc.?
6) Have all contractual matters involving out of scope work, definition of work, and interfacing requirements been settled with IGPO?

The Restart Review committee, which is defined by Gemini Observatory, will promptly report its findings to Gemini, AURA, and NOAO, so appropriate action can be taken to resolve outstanding issues in the GNIRS project.


Restart Review Presentation - MS PowerPoint file
 

Restart Review Committee Report

Restart Review Posters


Home
Planning
Progress Reports
System Design Notes
Meetings/Reviews
Configuration Images
Requirements
Subsystems
Memoranda
Staff
FTP Site
 


If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.

NOAO Intranet Services
NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360