GNIRS RESTART REVIEW
July 20-21, 1999
|
|
|
|
Tuesday, July 20
| Time | Section | Event | Presenter(s) |
| 0800 | Closed Review Committee Session | James Breckinridge | |
| 0830 | I | Introduction | Sidney Wolff |
| 0900 | II | Summary of Committee Report Items | Sidney Wolff |
| 0930 | III | Current Status of the GNIRS Project | Neil Gaughan |
| 1030 | Break | ||
| 1045 | IV | Project Overview - RR to Completion | Neil Gaughan |
| 1130 | V | Project Management | Neil Gaughan |
| 1200 | Lunch | ||
| 1300 | Project Management (cont) | Neil Gaughan | |
| 1400 | VI | GNIRS Configuration | Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen |
| 1430 | Break | ||
| 1445 | GNIRS Configuration (cont) | Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen | |
| 1700 | End of First Day |
Wednesday, July 21
| Time | Section | Event | Presenter(s) |
| 0830 | Meeting Start-up | ||
| 0845 | GNIRS Configuration (cont) | Jay Elias/Brooke Gregory/Larry Goble/Gary Muller/Andy Rudeen | |
| 1000 | Break | ||
| 1015 | VII | Risk Identification and Mitigation Plan | Neil Gaughan |
| 1100 | VIII | Conclusion | Sidney Wolff |
| 1200 | Lunch | ||
| 1300 | IX | Committee Caucus | Chair - James Breckinridge |
During October 1998 AURA held a thorough review of the GNIRS project after it was reported by NOAO and the USGP that GNIRS would substantially overrun its budget and delivery schedule. Among the recommendations of that overall project review was one to hold a Restart Review before formally deciding if the instrument should be allowed to proceed. The purpose of this Restart Review is expressed in the Executive Summary of the AURA review committee’s report, which states that,
“GNIRS should be restarted if a successful “restart review” can be completed. This review should be aimed at resolving technical/fabrication issues, cost and schedule issues, and the adequacy of the new GNIRS management and engineering team currently being assembled by NOAO. The Review panel concluded that such a “restart review” must be based upon a proper project technical management structure with well-defined roles and responsibilities. The intent of this review should be to show clearly and rigorously (1) that the GNIRS instrument, completed under NOAO’s project plan as presented to the Panel, will be a world-class device appropriate to the funds and time spent to develop it, and (2) that the GNIRS instrument will have operational capabilities (cool down time, alignment stability, etc.) which will make it an asset rather than a liability to the end user community.”
In this context, the Restart Review committee is charged to investigate the following questions -
1) What is NOAO’s current cost estimate to complete GNIRS and on what
schedule?
2) Is this estimate consistent with NOAO’s planned resources over the
duration of the GNIRS project?
3) Have the technical issues (AURA report attached for reference) identified
by the AURA review committee been addressed adequately to permit continuation
of GNIRS?
4) Does NOAO now have in place an appropriate management structure
to track, plan, and control resources to ensure that GNIRS will be delivered
on time and budget?
5) Are there any approaches to designing and fabricating GNIRS that
can significantly accelerate the planned delivery, e.g., through the injection
of additional NOAO resources, outsourcing the fabrication of components,
etc.?
6) Have all contractual matters involving out of scope work, definition
of work, and interfacing requirements been settled with IGPO?
The Restart Review committee, which is defined by Gemini Observatory, will promptly report its findings to Gemini, AURA, and NOAO, so appropriate action can be taken to resolve outstanding issues in the GNIRS project.
Restart
Review Presentation - MS PowerPoint file
Restart Review Committee Report
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360