United
States Gemini Program
Quarterly
Review
of
GNIRS
Held October
13, 1999
at Tucson,
Arizona
1.
Meeting Background
A
USGP quarterly review of GNIRS was held on October 13, 1999. The meeting
was attended by Todd Boroson and Mark Trueblood (WPM) from the USGP; David
Montgomery of IGPO; and Larry Daggert, Neil Gaughan, Jay Elias, and members
of the GNIRS team from NOAO/ETS.
The
goal of the quarterly reviews is to evaluate each instrument project's
progress in a number of different areas, with emphasis on management and
high level concerns. Specifically, the USGP wishes to have a formal mechanism
to determine whether a project is on track with respect to budget and schedule,
and to identify potential problems before they significantly impact progress.
2.
Major Findings
The
project appears to be somewhat behind schedule for holding the Pre-Fabrication
Review in February 2000 but in the opinion of the WPM and the Project Manager,
it is possible to make up that schedule deficit, which is primarily in
mechanical analysis of the instrument's flexure and thermal properties.
A
major deficiency identified at the Restart Review that had not been corrected
at the time of the review is software. No software design or plan was presented
at the Quarterly Review, and no software plan appeared to be in place at
that time. Since then, NOAO has submitted a very preliminary software plan
indicating a more detailed plan will follow next April.
3.
Project Summary
3.1
Project Overview and Key Accomplishments
The
key accomplishments since the Restart Review have been:
·Concluded
negotiations with IGPO concerning the terms and conditions for restarting
the project
·Developed
a detailed schedule of all tasks needed to complete the design and to fabricate
and test the instrument
·Put
into place a management information system to status the schedule, obtain
financial data in accordance with the WBS, and to produce earned value
and other management reports
·Advanced
the mechanical design of the instrument in several areas
·Began
structural and thermal modeling
·Executed
a comprehensive cold motor testing Project to select cold motors and to
characterize them for use in the instrument
·Built
a large test dewar capable of handling the large mechanisms to be used
in the instrument, to test subassemblies before they are installed in the
instrument
·Explored
various alternatives to obtaining the needed software engineering support
3.2
Project Status and Plans
The
GNIRS project is behind schedule in the area of engineering design of the
main optical bench, and the structural and thermal analysis of this design.
The Project Manager believes the schedule is tight, but that the Pre-Fab
review can still be held as scheduled in February. As the Restart Review
committee discovered, a detailed software design and management plan are
not yet in place, due to lack of NOAO resources. The current schedule is
for these to be put into place in April 2000. All other areas appear to
be on schedule. All effort is focussed on preparing for the Pre-Fabrication
Review scheduled for February 2000.
3.3
Project Problems and Concerns
As
noted above, mechanical design and analysis are somewhat behind schedule.
It is not clear what the software status is, since no schedule yet exists
for software.
3.4
Project Schedule
The
summary-level project schedule is attached to this report. An analysis
of the schedule performance of each major engineering discipline appears
below.
3.5
Project Milestones, Cost, and Manpower Charts
Major
milestones for the next few months include the Pre-Fabrication Review and
developing the detailed software plan. The cost of the project since the
beginning of the instrument redesign in January 1999 is estimated to be
$4.2M, not including the $2.4M spent between the project start in October,
1995 and the discovery of serious design flaws in late 1998. Manpower charts
are not available at this time, as manpower leveling is still being performed
as the schedule is being fine-tuned by the Project Manager. Beginning in
the November 1999 report, the USGP expects to see Earned Value reported
in the monthly report.
3.6
Project Budget and Expenditures to Date
The
Project Manager reports budget and expenditures monthly to the USGP (see
attached report for October). This report shows budgeted and actual expenditures
for the month and cumulative to date. As of this review, expenses are on
track for staying within the budget at completion.
3.7
Organization
The
project appears to be staffed with a sufficient number of competent people,
except in software. A software manager is due to begin full time in January
2000.
4.
Optics Design
The
optics design is complete. All further optical work is in the area of procurement,
installation, alignment, and integration.
5.
Optics Fabrication
All
powered elements and the filters are on order, with the other items not
yet scheduled to be procured.
6.
Mechanical Design
6.1
Mechanical Design Overview and Key Accomplishments
The
mechanical design strategy is to use the two mechanical engineers and AutoDesk
Mechanical Desktop to make a 3-D model of the instrument, then to use the
drafting staff to extract 2-D drawings from the 3-D model, to dimension
and tolerance the drawings, and to prepare them for use in fabrication.
As
of the Restart Review, the 3-D engineering design was almost at a PDR level,
but without any analysis having been done. Between the Restart Review and
the Quarterly Review, work concentrated on fleshing out the design and
getting it ready to perform the structural and thermal analysis. A major
effort was also devoted to designing prototype mechanisms that will be
fabricated and cold tested to ensure that repeatability and other requirements
can be met.
6.2
Mechanical Design Status and Plans
The
prototyping effort is on schedule. The completion of the design, especially
the optical bench, and other tasks that need to be completed before structural
and thermal analysis can begin are behind schedule, and are now on the
Critical Path.
6.3
Mechanical Design Problems and Concerns
WBS
elements 5.3.2.1 and 5.3.2.2 are behind schedule. It appears that this
is due in large part to a miscommunication between the Project Manager
and the engineering staff concerning the ordering and timing of tasks leading
up to the structural and thermal analysis of the instrument. The GNIRS
must meet some very demanding requirements for both flexure and thermal
gradients, so the mechanical engineer performing these analyses is interested
in using a model that accurately represents the instrument design. The
intended process is that the final stages of design and analysis are parallel
efforts each informing the other; when the analysis indicates a stiffer
structure is needed in a particular place, the engineer adds the required
material to the design, regenerates the model, and repeats the analysis.
This cycle is repeated until the design converges on a solution that analysis
indicates will meet the requirement, or the engineer determines the requirement
cannot be met.
The
original schedule had the design of the science and OIWFS optical benches
being completed after the Pre-Fabrication Review in February. This activity
was moved forward to provide the engineer with an adequately realistic
starting point for the analysis. If this work can be completed in time
to hold the Pre-Fabrication Review in February, then the mechanical design
will actually be slightly ahead of schedule, since a task scheduled for
after the review (completing the 3-D design of the two optical benches)
will have been completed before the review.
7.
Mechanical Fabrication
No
mechanical fabrication was scheduled to have begun before the Quarterly
Review.
8.
Electronics Design
8.1
Electronics Design Overview and Key Accomplishments
The
basic electronics design was presented at the Restart Review, and is at
a level somewhere between a PDR and a CDR. All assemblies are identified
and designed, with remaining work being in the area of some detailed design,
such as connector pinouts and wiring lists. The electrical engineer has
spent most of his time since the Restart Review working on cold motor qualification
and characterization tests, which have been completed.
8.2
Electronics Design Status and Plans
Electronics
design is on schedule.
8.3
Electronics Design Problems and Concerns
None
8.4
Electronics Design Schedule
Electronics
design is on schedule.
8.5
Electronics Design Milestones, Cost, and Manpower Charts
The
next major milestone is completion of mechanism prototype testing. Cost
is within budget, and the tasks are adequately staffed with available personnel.
After the QR in early November, Andy Rudeen, the GNIRS electronics engineer,
gave notice of terminating his employment. The Project Manager does not
believe this will have an adverse effect on the project, as electronics
is not on the Critical Path, and he believes he will be able to hire a
replacement in time to avoid schedule slips.
9.
Electronics Fabrication
No
deliverable fabrication tasks are scheduled to begin until February 2000.
The only fabrication that has been done to date is for motor qualification
and characterization, and for mechanism prototype testing. With regard
to the latter, a test rig has been assembled and demonstrated.
10.
Software Design
10.1
Software Design Overview and Key Accomplishments
Due
to major changes in the mechanism control philosophy between the original
instrument design and the current design, most of the prior work on software,
at least at the detailed level, must be discarded. Some top-level design
work concerning the OCS interface may be transferable.
Richard
Wolff has agreed to serve as the GNIRS software group manager beginning
January 2000. He will be responsible for all GNIRS software efforts. The
software requirements are now being documented by the systems engineering
staff, primarily Jay Elias. These requirements will be refined by Richard,
then he will produce a top-level design, a detailed design, and a management
plan by April, 2000. The master project plan will be updated at that time
to reflect his estimates for completing the software.
10.2
Software Design Status and Plans
Software
design will begin in early 2000.
10.3
Software Design Problems and Concerns
In
the experience of the GNIRS Work Package Manager, software usually takes
far longer than anticipated. For example, the NIR InSb array controllers
NOAO built for Gemini were over a year late, due primarily to delays in
software caused by the difficult learning curve for EPICS and underestimating
the effort required. With the instrument now scheduled to be delivered
about 2.5 years late, NOAO cannot afford to let this happen again on GNIRS.
10.4
Software Design Schedule
The
software schedule will be in place in April 2000. Until then, it is impossible
to determine if software is on the Critical Path.
10.5
Software Design Milestones, Cost, and Manpower Charts
These
will not be known until the detailed software plan is delivered in April
2000.
11.
Software Fabrication
No
software fabrication was scheduled to begin before the Quarterly Review.
12.
Subsystem Integration
No
subsystem integration was scheduled to begin before the Quarterly Review.
13.
System Integration
No
system integration was scheduled to begin before the Quarterly Review.
14.
Test and Checkout
No
test and checkout tasks were scheduled to begin before the Quarterly Review.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NOAO Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360