PROJECTED COSTS as of 1/99
To be revised before Restart Review 7/99



 
 

Summary of Projected GNIRS Capital and Labor Costs
Skill Type
FY 99
FY 00
FY 01
FY 02
Total mm
Labor($K)
Capital ($K)
MD
24
36
23
9
92
510
ED
2
2
11
ET
1
9
12
9
31
172
ME
18
24
15
9
66
366
EE
9
12
12
9
42
233
OE
4.5
2
7.4
3
16.9
94
IM
9
39
39
3
90
499
P
6
12
12
10
40
222
OMT
0.5
6
3
9.5
53
PS
13.5
18
18
14.5
64
355
PM
9
12
12
9
42
233
AA
9
12
12
9
42
233
Total mm
103.5
178
168.4
87.5
537.4
Labor cost ($K)
574.218
987.54
934.28
485.45
2,981
Capital ($K)
175
645
20
20
860

 


Home | Management | System Design Notes | Requirements | Configuration Images | Subsystems | Archives | Staff | FTP Site | Internal Information |



If you have any questions or suggestions regarding this website, please contact Melissa Bowersock.


NOAO Intranet Services
NOAO Copyright
 Statement

National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O. Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360