GNIRS
Interim Design Review
An Interim Review of the Opto-Mechanical Design of the GNIRS
May 25, 1999
| TIME | ITEM | PRESENTER |
| 8:30-8:45 | Introductory Remarks | Gaughan |
| 8:45-9:00 | Design Issues | Elias |
| 9:15-1:00 | Configuration Description | Muller/Goble |
|
||
|
||
|
||
|
||
|
||
|
||
|
||
| 12:00-1:00 | Lunch (working) | |
| 1:00-1:30 | Thermal Issues | Elias |
| 1:30-1:45 | Optics Status | Gregory |
| 1:45-2:15 | Electrical Packaging | Rudeen |
| 2:15-2:30 | Schedule and Status | Gaughan |
| 2:30-3:00 | Discussion and Adjourn |
|
|
|
|
|
|
|
|
|
|
|
|
|
|