
Functional and Performance Requirements
for the
Gemini Near Infrared Spectrograph
Prepared by the
National Optical Astronomy Observatories
Instrument Projects Group
for the
United States Gemini Program
(DRAFT REVISION: Not fully updated for all Gemini ICD updates)
November, 1997
Document Acceptance and Concurrence
This document represents the current understanding of
the capabilities and performance of the Gemini Near Infrared Spectrograph
to be designed, fabricated, tested, delivered, and commissioned by the
National Optical Astronomy Observatories Instrument Projects Group to the
United States Gemini Program for use on the Gemini North 8-m telescope.
NOAO/USGP NOAO/ETS
____________________________________ ___________________________________
Mark Trueblood, Work Package Manager
Neil Gaughan, IPG Manager
____________________________________ ___________________________________
Todd Boroson, USGP Project Scientist Larry Daggert, ETS
Manager
IGPO Concurrence:
____________________________________ ___________________________________
Table of Contents
Purpose of This Document
Applicable Documents
Acronym List
100 Cassegrain Rotator Interfaces
110 Instrument Support Structure Interface
120 Helium Interface
130 Electric Power Interface
140 Cooling Water Interface
150 Signal, Control, and Data Interfaces
160 Liquid Nitrogen Interface
170 Vacuum
Interface
200 Control Systems Interfaces
210 Observatory Control System Interface
220 Telescope Control System Interface
230 Engineering Interface
240 Interlock Bus Interface
250 Events Bus Interface
260 Synchro Bus Interface
270 Time LAN Interface
280 reserved
290 General
Control System Requirements
300 Array and Array Controller Interfaces
310 Science Detector Array Interface
320 Science Array Controller Interface
330 Data Handling System Interface
340 OIWFS Detector Array Interface
350 OIWFS Array Controller Interface
360 Telescope
Control System Interface
400 Environmental Requirements
410 Altitude Environment
420 Temperature Environment
430 Humidity Environment
440 Vacuum Environment
450 Mechanical
Environment
500 Optical Requirements
510 Science Requirements
520 Science Options
530 Image Quality and Optical Tolerances
540 OIWFS Feed
550 Target Acquisition
560 Baffling
570 Internal Instrument Background
580 Throughput
590 General
Optical Requirements
600 Mechanical Requirements
610 Rigidity
620 Tolerances
630 Thermal Performance
640 Space Requirements
650 Mass and Center of Gravity Requirements
660 Cooling System
670 Vacuum System
680 Mechanisms
690 Instrument Handling
6A0 Metric
Dimensioning
700 Electrical and Electronic Requirements
710 Electronic Design Requirements
720 Cassegrain Cable Wrap Interfaces
730 Temperature Monitoring
740 Heat Dissipation
800 Software Requirements
810 Software Design Requirements
820 EPICS Compatibility
830 Gemini
Furnished Software
900 Other Requirements
910 Documentation
920 Training
930 Reliability
940 Maintainability and Serviceability
950 Lifetime
960 Safety
Purpose of This Document
The purpose of the Functional and Performance Requirements (document) for the Gemini Near Infrared Spectrograph ("GNIRS FPRD") is to provide the Gemini scientific community with an understanding of what the GNIRS will do and how quickly or how well it will do it, and engineers with the requirements to use to design the GNIRS. This document answers the question "What?", but not the question "How?". The "How" is the design that is derived from, and traceable to, this document. That is, this document takes precedence over the design and fabrication documents.
The design must serve the requirements in this document completely. This means every feature of the GNIRS should be traceable to a requirement in this document, and there should be no features of the GNIRS that are not required by this document. The GNIRS will be designed in stages, with a review after each stage is complete. Comments from the review committee will be folded into the design, so the requirements will change as the design changes. Therefore, this document will be updated as needed after each major design review to maintain the correspondence between requirements and design.
This document was written using the Design Requirements
(document) for the Gemini Near Infrared Spectrograph ("GNIRS
DRD") as a guide. The GNIRS DRD contains more than engineering requirements,
including a brief description of the science goals driving the requirements,
suggestions of good design practice, and other information useful to the
engineering team designing the GNIRS. The authors of the FPRD attempted
to capture this information in the DRD and to cast it into engineering
requirements that could be used to design the GNIRS. Upon approval by all
parties named on the signature page, this document supersedes the DRD and
defines the GNIRS capabilities and performance.
Applicable Documents
Controlling Documents. The following documents control the GNIRS design:
1. GNIRS Statement of Work
2. GNIRS Quality Assurance Plan, to be written
3. Critical Design for the Cassegrain Assembly, RPT-I-G0044,
6 June 94
Reference Documents. The following documents will be useful in the GNIRS design:
1. Gemini Software Design Description, SPE-C-G0037, 7 March 95
2. Gemini Instrumentation Control Document, ICD-G-0009, [Very Rough Draft], 20 July 94
3. Gemini System Error Budget Plan, SPE-S-G0041, Version 2.1, 1 February 94
4. Mountain, M., A Scientific Perspective on the Requirements for the 1- 5 m m Spectrograph, TN-PS-G0020, 1 July 94
5. Gemini Electronic Design Specification, SPE-ASA-G0008, 23 February 94
6. Gemini IR Array Controller Performance Requirements, 7 August 95
7. Fowler, et al., "Next Generation In InSb Arrays: ALADDIN 1024 x 1024 InSb Focal Plane Array Development Project Status Report", SPIE Volume 2198, pp. 623- 629, 13-14 March, 1994
8. Ott, Henry W., Noise Reduction Techniques in Electronic Systems, Second Edition, AT&T Bell Laboratories, 1988
9. Gemini ICD 07a, ICS Subsystem Interfaces, 22 February 95
Acronym List
AO Adaptive Optics
CICS Core Instrument Control System
DHS Data Handling System
EPICS Experimental Physics and Industrial Control System
GNIRS Gemini Near Infrared Spectrograph
ICD Interface Control Document
ICS Instrument Control System
IGPO International Gemini Project Office ("Gemini" or "the Project")
IOC Input/Output Controller
ISS Instrument Support Structure (the "cube")
OIWFS On Instrument Wavefront Sensor
OCS Observatory Control System
TCS Telescope Control System
USGP United States Gemini
Program
100 Cassegrain Rotator Interfaces
110 Instrument Support Structure Interface
The GNIRS shall interface mechanically to the Gemini Instrument Support Structure (ISS).
111 Ports
The GNIRS shall be capable of being mounted on and used at any side-looking science instrument ISS port or the upward-looking port at the bottom of the ISS.
112 Instrument Mounting Plate Flatness
The GNIRS mounting interface shall be repeatable within the optical tolerances of the alignment between GNIRS and ISS when removed and replaced.
113 Instrument Mounting Plate Material
The GNIRS mounting interface shall take into account the material of which the ISS is made and shall hold differential temperature effects to a level that permits the GNIRS to meet all optical alignment requirements over the entire operating temperature range.
114 Fasteners
The fasteners that are engaged for load transfer from the Cassegrain handling rig shall be sized for a safe working load that includes a static and dynamic factor of safety to accommodate predicted loads on the Gemini telescope.
115 Optical Feed
The GNIRS shall accept and use the Gemini telescope optical feed, which is approximately f/16 with a focal length of 128 meters. The beam comes to a focus 300 mm from the ISS mounting surface inside the GNIRS.
Notes and Comments
1. The ISS to Science Instrument ICD is 1.5.3/1.9. The 1.5.3 ISS Introductory ICD is also relevant.
2. Fastener design must accommodate the changing direction of the gravity vector due to rotation of the ISS and positioning of the telescope.
3. The largest field of view of the GNIRS is 3 arc-min. in diameter. Due to the weak power of the entrance window, the effective f-number of the telescope inside the dewar is stronger than specified above.
4. Telescope focal length is given in Gemini Telescopes
f/16 Design Summary, RPT-0-G0047, 6 July 1994.
120 Helium Interface
The GNIRS shall obtain helium for its cryocoolers and return low-pressure helium through the connectors provided in the Cassegrain Rotator Utility Box appropriate to each instrument port. The helium interface is described in ICD 1.9/3.7.
121 Number of Helium Connections
The GNIRS shall have one high pressure connection for the entire instrument, and one low pressure return for the entire instrument. Each of these lines shall have appropriate tees on the instrument to service the cryocooler heads.
122 Length of Helium Line Runs
The high and low pressure lines to the Cassegrain Rotator Utility Box shall be of a length that permits the GNIRS to meet Requirement 111. If good design practice dictates, coupling hoses of different lengths shall be supplied for mounting the GNIRS on different ISS ports.
123 Helium Line Flexibility
The high and low pressure lines to the Cassegrain Rotator Utility Box shall be flexible enough to permit easy routing, connection, disconnection, and dressing for operation.
124 Type of Helium Connectors
The high pressure line shall connect to the Cassegrain
Rotator Utility Box using a connector described in ICD 1.9/3.7.
Notes and Comments
1. It is expected that Gemini will provide a helium supply of (TBD) liters/minute at a pressure of (TBD) units. The low pressure return line is expected to carry (TBD) liters/minute at a pressure of (TBD) units. All helium delivered to the GNIRS is expected to be 99.999% pure. It is expected that details of the helium supply will be added to ICD 1.9/3.7.
2. Details of the helium interface are expected to be obtained from the Quantum Study, due 29 February 1996.
130 Electric Power Interface
The GNIRS shall derive its electric power through the
connectors provided on the Cassegrain Rotator Utility Box appropriate to
each instrument port. The power interface is part of ICD 1.9/3.8, Science
Instruments to System Cables.
131 Number of Electrical Connections
The GNIRS shall have two electric power connections for the entire instrument. One connection will provide "clean" power for the computer and electronics, while the other will provide "dirty" power for the cryo coolers and fans. The "dirty" connection should provide optional 220 V./3 phase power for the cryo coolers. The GNIRS shall have appropriate runs from a junction box to serve all instrument power needs. The ICD 1.5.2/1.9 describes cable wrap connector plates.
132 Length of Electrical Line Runs
The power line to the Cassegrain Rotator Utility Box shall be of a length that permits the GNIRS to meet Requirement 111. If good design practice dictates, a means of dressing the power cable to a length appropriate for different ports shall be provided.
133 Electric Power Line Flexibility
The electric power line to the Cassegrain Rotator Utility Box shall be flexible enough to permit easy routing, connection, disconnection, and dressing for operation.
134 Type of Electrical Connectors
AC power is provided to the science instrument via two, dual 3-prong, 120 VAC outlets (NEMA 5-15) mounted on the cable wrap interface plate. One outlet pair is UPS conditioned power and the other is building mains power. The cable connector at the interface to the instrument is a circular MIL-style connector, MS3106R16-10S. The corresponding instrument connector must be an MS3100R16-10P. AC voltage at both observatories will be 120 VAC. Line frequency for Cerro Pachon is 50 Hz, while the Mauna Kea frequency is the US standard 60 Hz.
Notes and Comments
1. Gemini will provide an electric power supply as given in ICD 1.9/3.8.
2. The GNIRS may require 220 to 260 volts AC, 60 Hz, 3
phase power for cryocooler operation. This type of power is not currently
provided by the ISS.
140 Cooling Water Interface
The GNIRS shall derive cooling water supply (and return) for electronic enclosures and any other use through the connectors provided on the Cassegrain Rotator Utility Box appropriate to each instrument port.
141 Number of Plumbing Connections
The GNIRS shall have one cooling water supply connection and one return line connection for the entire instrument. The GNIRS shall have appropriate tees from these lines to serve all instrument cooling water needs.
142 Length of Cooling Water Runs
The cooling water lines to the Cassegrain Rotator Utility Box shall be of a length that permits the GNIRS to meet Requirement 111. If good design practice dictates, a means of dressing the cooling water lines to a length appropriate for different ports, or lines of different lengths for different ports, shall be provided.
143 Cooling Water Line Flexibility
The supply and return lines to the Cassegrain Rotator Utility Box shall be flexible enough to permit easy routing, connection, disconnection, and dressing for operation.
144 Type of Plumbing Connectors
The cooling water lines shall connect to the Cassegrain Rotator Utility Box using a connector of type (TBD) and of gender (TBD), compatible with (TBD) vendor model number (TBD). The connector shall not permit more than a drop or two of coolant to escape the system when connecting or disconnecting the supply and return lines, and shall not leak during normal operation.
145 Resistance to Glycol
The cooling water lines and connectors shall not be damaged in any way when used with a cooling solution containing glycol.
Notes and Comments
1. It is expected that Gemini will provide a cooling water supply of (TBD) liters/minute at a pressure of (TBD) units and a temperature of (TBD)C. The low pressure return line is expected to carry (TBD) liters/minute at a pressure of (TBD) units and a temperature of (TBD)C.
2. Plumbing connection standards may already exist within the Gemini project.
3. Coolant mixture is expected to be 50/50 water/glycol.
4. The cooling water interface is covered in ICD 1.9/3.6.
150 Signal, Control, and Data Interfaces
The GNIRS shall receive and provide all signal, control,
and data paths through the connectors provided on the Cassegrain Rotator
Utility Box appropriate to each instrument port.
151 Number of Signal, Control, and Data Connections
The GNIRS shall
have one connection for the entire instrument to the appropriate Cassegrain
Rotator Utility Box for each of the following, if needed:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The GNIRS shall have appropriate tees from these lines to serve all instrument needs. In/out signals marked with * must be bridged at the cable wrap connector plate when not connected to instruments. In the case of the Synchro Bus, the two connectors of the pair must be bridged.
152 Length of Signal, Control, and Data Runs
The signal, control, and data lines to the Cassegrain Rotator Utility Box shall be of a length that permits the GNIRS to meet Requirement 111. If good design practice dictates, a means of dressing these lines to a length appropriate for different ports, or lines of different lengths for different ports, shall be provided.
153 Signal, Control, and Data Line Flexibility
The signal, control, and data lines to the Cassegrain Rotator Utility Box shall be flexible enough to permit easy routing, connection, disconnection, and dressing for operation.
Notes and Comments
1. The ICD 1.9/3.8 contains references to all but the video LAN and Interlock System.
2. There is also an auxiliary boot RS-2332 to each instrument IOC control. Control, Time, Synchro and Event LANs are in/out connector pairs.
160 Liquid Nitrogen Interface
The GNIRS shall be provided with interfaces for adding
liquid nitrogen for cool down when the instrument is on the ISS at the
telescope.
Notes and Comments
1. It is not anticipated that LN2 will be added through the ISS. This requirement is intended to provide for cool down of the instrument via a separate set of connections when the GNIRS is on the telescope.
2. Addition of LN2 is likely to be by hand carried dewars.
3. No LN2 interface currently exists.
170 Vacuum Interfaces
The GNIRS shall be provided with interfaces for the connection
of vacuum lines when the instrument is attached to the ISS at the telescope.
Notes and Comments
1. It is not intended to provide vacuum lines in the ISS. This requirement is to provide for the ability to evacuate the GNIRS when the instrument is attached to the ISS at the telescope.
2. Under normal conditions the instrument will be evacuated in the pump room. If necessary, portable equipment will be used to evacuate the GNIRS at the telescope.
3. No vacuum interface currently exists.
200 Control Systems Interfaces
210 Observatory Control System Interface
1. The Observatory Control System Interface is covered
by ICD 1.1.11/1.9.
220 Telescope Control System Interface
The only required connection between GNIRS and the TCS
shall be provided by the OIWFS components controller software package.
Notes and Comments
1. Although Gemini provides both the OIWFS components controller and the Telescope Control System, and must demonstrate that these items work together, the GNIRS team must integrate the OIWFS array controller into the GNIRS and make it work in the instrument environment at the ISS.
2. The Telescope Control System must provide a coordinate position for the OIWFS pick-off with respect to the GNIRS coordinates.
3. Currently there are three ICDs shown for the OIWFS: Intro, 1.10; Cooling, 1.10/3.6 and Cables 1.10/3.8.
230 Engineering Interface
The GNIRS shall provide a means for command and control
of GNIRS mechanisms and science array controller, and data capture from
the science array without the need for having Gemini control systems (i.e.,
the Observatory Control System and the Telescope Control System) present
or connected.
231 Physical Interface
The Engineering Interface shall run on a Sun/Solaris workstation
that is compatible with Gemini workstations.
232 User Interface
To the extent practicable, the user interface in the Engineering
Interface should appear to a user to be very similar to the user interface
in the CICS.
233 Command and Control
The Engineering Interface shall:
The Gemini-furnished detector controller software is responsible
for capturing science data from the GNIRS and transferring it to the DHS.
The Engineering Interface shall be provide the necessary connections to
the detector control software.
Notes and Comments
1. The intent of this requirement is to permit the GNIRS to be operated in the laboratory for Pre-Ship Acceptance testing.
2. There is no need to provide an Engineering Interface to command or control, or capture data from, the OIWFS. Some means of testing set-up routines for the OIWFS/slit viewer combination is required.
3. It is expected (but not required) that the Engineering Interface would use at least a part of EPICS in its implementation.
4. Not all data readout modes need be supported. The data
that is captured may require extensive processing normally done by the
GNIRS Instrument Control System or the Gemini Data Handling System to be
intelligible. There is no requirement for the Engineering Interface to
perform this data processing, which may be done off-line on another system
to analyze results.
240 Interlock System Interface
(TBD)
Notes and Comments
1. No GNIRS interlocks require a complete stop of the telescope.
2. Some local interlocks should immediately notify the operator that the GNIRS has shut down. For example: a helium failure or overheating of the electronics.
3. The physical interface is described in ICD 1.9/3.8.
250 Events Bus Interface
At this time there is no requirement for the GNIRS too
connect to the Events Bus.
Notes and Comments
1. The physical interface is included in ICD 1.9/3.8.
260 Synchro Bus Interface
At this time there is no requirement for the GNIRS to
connect to the Synchro Bus.
Notes and Comments
1. The physical interface is included in ICD 1.9/3.8.
2. The Synchro Bus In/Out Connector is dual SC fiber.
270 Time LAN Interface
At this time there is no requirement for the GNIRS to
connect to the Time LAN.
Notes and Comments
1. The physical interface is included in ICD 1.9/3.8.
2. The Time LAN to IOC thermal enclosure is BNC in and
BNC out.
280 reserved
290 General Control System Requirements
The GNIRS shall meet all general control system requirements
given below.
291 Operability
All mechanisms and other controllable features of the
GNIRS shall be managed by computer through the standard EPICS control paths
from the GNIRS Engineering Interface, or from the Instrument Console developed
as part of the OCS by Gemini.
292 Configuration Time
The goal for configuration of the GNIRS for an observation
from any previous observation configuration is 3 minutes or less.
Notes and Comments
1. Besides being controllable from the ICS, the dark slide
can be moved by hand, to permit closing it manually in the event of a loss
of power to the instrument.
300 Array and Array Controller Interfaces
310 Science Detector Array Interface
The GNIRS design shall make provision for the Gemini-furnished
InSb science detector array.
311 Characteristics
The GNIRS shall be designed to take the fullest possible advantage of an InSb detector with the following characteristics:
Number of pixels 1024 (H) x 1024 (V)
Architecture 4 independent 512 x 512 quadrants
Pixel size 27 m m, square
Effective fill factor 100%
Number of outputs 32 (8 per quadrant)
Maximum frame rate 20 frames/second
IR material Thinned InSb
Full well 300,000 electrons at 0.8 V bias
Wavelength range 0.9-5.5 m m
Nominal operating temperature 35 K
Dark current <0.1 electron/second
Read noise <25 electrons (rms)
Quantum efficiency
80% (0.9-5 m m)
312 Mechanical Interface
(TBD)
313 Thermal Interface
(TBD)
314 Optical Interface
(TBD)
Notes and Comments
1. Both the array and array controller are furnished by Gemini. Therefore, the interface between the array and its controller is not described in this document, as that interface is not the responsibility of the GNIRS team. Size, weight, and mechanical connection information concerning the array are required.
2. The GNIRS requires information on the number of electronics boards and racks required for the array and array controller. Information is required on the length of cable runs and the maximum distance between the array and the preamp.
3. An estimate of heat dissipation and power requirements for the array electronics is required.
4. The detector ICD is 1.9.2
5. The detector controller ICD is 1.9.3.
6. The Instrument Components Controller ICD is 1.9.4.
7. The Instrument Sequencer ICD is 1.9.5.
320 Science Array Controller Interface
The GNIRS design shall make provision for the Gemini-furnished
science array controller.
321 Mechanical Interface
(TBD)
322 Thermal Interface
(TBD)
323 Optical Interface
(TBD)
324 Software Interface
(TBD)
Notes and Comments
1. Both the array and array controller are furnished by Gemini. Therefore, the interface between the array and its controller is not described in this document, as that interface is not the responsibility of the GNIRS team.
330 Data Handling System Interface
The GNIRS will provide the software necessary to log data.
Data logging shall be used when the instrument is operating in the Gemini-prescribed
debug modes. Data logging may also occur during normal operation for the
purpose of reflecting instrument health over time.
Notes and Comments
1. The software for transfer of science data is part of the Gemini-furnished array controller software.
2. The physical interface is included in ICD 1.9/3.8.
340 OIWFS Detector Array Interface
(TBD)
Notes and Comments
1. The interface between the OIWFS and GNIRS is very critical in defining the overall configuration of the instrument. Early release of this interface requirement is essential for maintaining the GNIRS schedule.
2. The OIWFS ICDs are:
Components - 1.10.1
Controller - 1.10.4
Sequencer - 1.10.5
(TBD)
Notes and Comments
1. The interface between the OIWFS and GNIRS is very critical in defining the overall configuration of the instrument. Early release of this interface requirement is essential for maintaining the GNIRS schedule.
2. The OIWFS ICDs are:
Components - 1.10.1
Controller - 1.10.4
Sequencer - 1.10.5
360 Telescope Control System Interface
400 Environmental Requirements
410 Altitude Environment
The GNIRS shall be capable of being transported, stored, and operated in a wide range of altitude environments.
411 Transportation Altitudes
The GNIRS shall be capable of being transported at any altitude between -200 feet and 14,000 feet by any transportation mode. The GNIRS shall be capable of being transported by commercial jet with pressurized cargo compartments at altitudes up to 50,000 feet.
412 Storage Altitudes
The GNIRS shall be capable of being stored in or out of its shipping container at any altitude between -200 feet and 14,000 feet.
413 Operation Altitudes
The GNIRS shall be capable of being operated at any altitude
between -200 feet and 14,000 feet.
Notes and Comments
1. The GNIRS must work at the Hilo Base Facility, at an altitude of approximately sea level, and at the telescope on Mauna Kea, at an altitude of approximately 13,900 feet.
2. The pre-ship acceptance test may be run in Tucson at an altitude of approximately 2,200 feet and on Kitt Peak at an altitude of approximately 7,000 feet.
3. After the GNIRS is commissioned on Mauna Kea, it might be shipped to Cerro Pachon. The base facility at La Serena has an altitude of a few hundred feet, and the telescope site on Cerro Pachon has an altitude of almost 9,000 feet.
420 Temperature Environment
421 Operational Environment
The GNIRS operational environment shall be limited to -15 to +25 oC.
422 Survival Environment
The GNIRS shall be capable of surviving a temperature range of -20 to +50 oC without damage.
423 Transport Environment
The GNIRS shall be capable of withstanding without damage
a temperature range of -20 to +50 oC during transport without
damage.
Notes and Comments
1. Storage and shipping temperature environments should be limited to those given in MIL-STD-810E, (222 to 344 K, or -51 to 71 oC).
2. During operation any temperature below -7 oC may affect the operation of external motors and ferro-fluidic feed throughs.
430 Humidity Environment
The GNIRS shall be capable of being transported and stored,
in a wide range of altitude environments in the range 0 to 100% relative
humidity, with condensing moisture.
Notes and Comments
1. Operation of the GNIRS at high relative humidity levels
will cause condensation on the dewar window. Using heaters on the window
or a hot air system are incompatible with the thermal management of the
telescope.
440 Vacuum Environment
If required by good design practice, the GNIRS shall maintain
a vacuum inside the dewar.
441 Creating the Vacuum
The GNIRS shall provide a means to evacuate its dewar
while the instrument is on its handling rig in the instrument support area,
and while it is attached to the ISS.
442 Vacuum Quality and Duration
The GNIRS shall be capable of being kept cold and operated
without measurable degradation of performance for 3 months. If needed the
instrument shall be capable of being kept at room temperature without measurable
contamination of the detector or internal optics for at least 3 months
without pumping.
Notes and Comments
1. Early Gemini documentation mentions a vacuum line in the ISS utility services box. This is no longer being provided. Instead, instruments will be pumped down in the instrument support facility, then transported to the telescope.
2. Operating vacuum may only be obtained with a cold instrument. The facility requires that the cryogenic cooldown system be disconnected during operation on the telescope.
450 Mechanical Environment
The GNIRS shall be capable of operating in the mechanical environment of the Gemini telescopes and their base facilities, and shall be capable of withstanding shipment among Tucson, Mauna Kea, and Cerro Pachon.
451 Telescope Slew Rates
The GNIRS shall be capable of withstanding slew rates
of 2° per second in azimuth and 0.75°
per second in elevation, or any combination of these, along with rotation
of the Cassegrain rotator to maintain alignment with the parallactic angle
as it changes at these slew rates. All optics and mechanisms shall meet
their flexure and alignment specifications at these rates.
Notes and Comments
1. The rotator requires faster slew rates than specified for maintaining parallactic angle.
500 Optical Requirements
510 Science Requirements
The GNIRS shall meet all science requirements listed below.
511 Wavelength Range
The GNIRS shall operate as a spectrograph in the wavelength
range 0.9 m m through 5.0 m
m.
512 Detector Format
The GNIRS shall use an InSb science detector array with
a format of 1024 x 1024, with 27 m m square
pixels.
513 Spectral Resolution
The GNIRS shall provide a low dispersion mode with R ~
1800 that permits most atmospheric windows to be covered by the detector
array. The GNIRS shall also provide an intermediate dispersion mode with
R 5000.
514 Pixel Scale
The GNIRS shall be capable of using 0.1-0.2 arcsecond
slits with sampling of approximately 0.05 arcsecond/pixel.
515 Slit Length
The GNIRS shall provide an entrance slit with a length
= 50 arcseconds. For the cross dispersion module the entrance slit length
will be less than 50 arc-seconds.
516 Polarizing Prism
The GNIRS design shall incorporate a polarization analyzer prism. The prism will not be included in the instrument as delivered.
Notes and Comments
1. There is no need for an on-instrument calibration source. Gemini will provide a calibration source on the ISS that can be fed to the GNIRS.
2. There is no need to provide a focus adjustment controllable from the ICS within the instrument. The OIWFS will be used to provide final focus provided focus meets 300 mm standoff specification at any orientation.
3. The post-slit viewer may use refractive optics.
4. Image parity is not a concern, so a fold mirror may be introduced anywhere in the optical path.
5. IGPO will provide the detector arrays and array controllers.
6. The 3-micron window cannot be covered at R=1800 due
to its width, R=1300 is required.
520 Science Options
The GNIRS shall include the science options or upgrade
paths listed below.
521 Cross Dispersion
The GNIRS should have a cross dispersion mechanism with
positions for 3 dispersive elements plus a mirror. The cross dispersion
mechanism shall provide the use of full slit length or work cross dispersed
with minimum JHK coverage for any camera. The dispersive elements will
be two cross dispersion prisms (one for each camera) and one Wollaston
prism. The Wollaston prism will not be included in the instrument as delivered.
522 Multi-slit Capability
The GNIRS will not have a multi-slit capability.
523 Long Slit
The GNIRS will have a slit length of 100 arcseconds for
the short camera.
524 Short Camera
The GNIRS should provide a second plate scale of 0.15
arcsecond/pixel. The camera required to provide this capability for wavelengths
greater than 2.5 m m will be designed but will
not be included in the instrument as delivered.
525 Higher Spectral Resolution
The GNIRS should have higher spectral resolution of approximately
18,000 accessible with the long-focus (0.05 arcsec pixel) camera.
526 Integral Field Mode
The GNIRS should have the capability to add an integral
field mode image slicer or its functional equivalent.
Notes and Comments
1. The integral field mode has the highest scientific
priority with the IRISWG, but has the lowest implementation priority due
to perceived technical problems of implementation.
530 Image Quality and Optical Tolerances
This section lists both "Goals" and "Requirements"; if a "Goal" is met then the corresponding "Requirement" does not need to be met.
531 Pre-Slit Image Quality at Telescope Focus
The image quality at the edge of a 30 arc-second field of view at the telescope focus shall be such that 50 % of the energy of a spot is within less than 0.1 arc-second and 85% of the energy of a spot is within less than 0.4 arc-second.
The image quality goals at the slit, following the fore-optics within the GNIRS, is evaluated for three case: on-axis, off-axis, and with adaptive optics. The specific science cases should be used to determine which goals should drive (or not drive) the design .
531a On-Axis
Goal: The increase in 50% encircled energy diameter (including
diffraction) of the 10th percentile best seeing, perfectly tip/tilt-corrected
image as delivered to the slit within GNIRS shall be less than or equal
to the following:
| Wavelength | 1.2 m m | 1.6 m m | 2.2 m m | 3.7 m m | 4.8 m m |
| 50% eed increase, arcsec | 0.096 | 0.097 | 0.104 | 0.124 | 0.162 |
531b Off-Axis by 25 arcsec
Goal: The increase in 50% encircled energy diameter (including
diffraction) of the 10th percentile best seeing, perfectly tip/tilt-corrected
image as delivered to the slit within GNIRS shall be less than or equal
to the following:
| Wavelength | 1.2 m m | 1.6 m m | 2.2 m m | 3.7 m m | 4.8 m m |
| 50% eed increase, arcsec | 0.101 | 0.102 | 0.108 | 0.132 | 0.167 |
532b Adaptive Optics
Goal: The increase in 50% encircled energy diameter (including
diffraction) of the 10th percentile best seeing, perfectly tip/tilt-corrected
image as delivered to the slit within GNIRS shall be less than or equal
to the following:
| Wavelength | 1.2 m m | 1.6 m m | 2.2 m m | 3.7 m m | 4.8 m m |
| Strehl degradation | 0.66 | 0.79 | 0.88 | 0.96 | 0.97 |
532 Image Quality at Spectrograph Focus
532a Post-Slit Image Quality - without AO
Requirement: At the spectrograph focus 85% of the light should be within a 27 micron diameter, at 25 arc-seconds from the center of the field, neglecting diffraction effects.
The "Goal" image quality at spectrograph focus is specified in both the spatial and spectral directions. The specific science cases should be used to determine which goals should drive (or not drive) the design.
The goal specification is expressed in terms of the diameter that encloses 50% of the encircled energy (50% eed). The image quality is assessed at the detector surface, which is assumed to be a 1024 x 1024 array with 27 m m square pixels. The overall wavelength range for the baseline system is 0.9-5.5 microns.
532a-1 Spectral Direction, without AO
Goal: The degradation in image quality in the spectral direction shall produce less than a 10% change in the resolution. In the dispersion direction, the image quality should be assessed with telescope aberrations excluded but including diffraction. The specifications must be maintained for the image of a long slit which extends over the full width of the field (as specified in 515 or 523) for all wavelengths which fall on the array detector up to a maximum of 0.4 x central wavelength or 0.8 x central wavelength, depending on science case.
532a-2 Spatial Direction, without AO
Goal-1 is more important than Goal-2
Goal-1: On the optical axis the degradation in image quality in the spatial direction shall produce an increase in the 50% eed of less than 10% of the 50% eed of the 10th percentile seeing image. In the spatial direction, along the slit, the image quality should be assessed with telescope aberrations and diffraction included. The specification must be maintained for the image of a long slit which extends over the full width of the field (as specified in 515 or 523) for all wavelengths which fall on the detector up to a maximum of 0.4 x central wavelength or 0.8 x central wavelength, depending on science case.
Goal-2: Within 10 arcseconds of the optical axis, the degradation in image quality in the spatial direction shall produce an increase in the 50% eed of less than 10% of the 50% eed of the 10th percentile seeing image.
532b Post-Slit Image Quality - with AO
Requirement: The use of GNIRS with Adaptive Optics is not part of the baseline requirements.
The goal image quality should be assessed with telescope aberrations included. The image quality at spectrograph focus is evaluated for two cases: with the long camera, with the slit narrowed to take advantage of the smaller AO image, and with an IFU. In each case image quality at the spectrograph focus is specified in both the spatial and spectral direction.
532b-1 Spectral Direction with Narrow Slit
Goal: The degradation in image quality in the spectral direction shall produce less than a 10% change in the resolution given by the narrow slit. In the dispersion direction, the image quality should be assessed with telescope aberrations excluded but including diffraction. The specification must be maintained for the image of a long slit which extends over the full width of the isoplanatic field or the field specified in 515, whichever is less.
532b-2 Spatial Direction with Narrow Slit
Goal-1 is more important than Goal-2
Goal-1: On the optical axis the degradation in image quality in the spatial direction shall produce an increase in the 50% eed of less than 10% of the 50% eed of the AO-corrected image. In the spatial direction, along the slit, the image quality should be assessed with telescope aberrations and diffraction included.
Goal-2: The specification must be maintained for the image of a long slit which extends over the full width of the isoplanatic field or the field specified in 515, whichever is less.
532c-1 Spectral Direction with Integral Field Unit
Requirements/Goals: TBD
532c-2 Spatial Direction with Integral Field Unit
Requirements/Goals: TBD
540 OIWFS Feed
The GNIRS shall provide an optical feed compatible with
the operation of the On-Instrument Wavefront Sensor module supplied by
Gemini.
541 Beam Characteristics
(TBD) with a plate scale corresponding to 0.2" pixels.
The optics inside the GNIRS in the path to the OIWFS shall distort the
beam fed to the GNIRS by the Gemini telescope no more than 60 nm rms.
542 Field Curvature
The beam feed optics shall be designed assuming the telescope
is providing the GNIRS its normal curved field uncorrected by adaptive
optics.
543 Wavelength Sensitivity
The OIWFS beam shall contain as much of the energy from
the telescope beam in the wavelength range of 1 m
m to 2.5 m m as it is practical to provide.
Notes and Comments
1. The purpose of the OIWFS is to provide feedback to the fast tip/tilt and focus correction control loops. The OIWFS will always provide telescope flexure correction. It may provide a fast tilt source for adaptive optics.
550 Target Acquisition
The GNIRS shall provide a means for simple target acquisition.
551 Target Complexity
The GNIRS shall provide a means for locating the slit
on single stars, specific features, and complex fields.
552 Target Wavelength
The GNIRS shall provide a means for locating the slit
on targets not detectable in the visible band of the electromagnetic spectrum,
but detectable in the wavelength range of the science detector.
Notes and Comments
1. Examples of complex targets include crowded star fields,
the core of a galaxy, and an emission region in a nebula. This may require
an imaging mode for locating the slit on targets, but other designs may
be acceptable.
560 Baffling
The GNIRS shall be properly baffled to minimize stray
radiation.
561 Thermal Baffling
The GNIRS shall contain sufficient thermal baffling to
minimize heat loading on the cryogenic systems.
562 Optical Baffling
The GNIRS shall contain proper optical baffling to reduce
stray radiation to levels below that detectable by the science detector.
570 Internal Instrument Background
The GNIRS shall have an internal instrument background
less than either the natural background from the observed science field
or the dark current of the detector, whichever is greater.
580 Throughput
The GNIRS shall be designed to maximize throughput to
take maximum advantage of the Gemini telescope performance.
581 Vignetting
The GNIRS design shall minimize vignetting, including
diffraction effects.
582 Signal-to-Noise Ratio
The GNIRS shall be designed to maximize throughput and
signal-to-noise ratio.
590 General Optical Requirements
The GNIRS shall meet the general optical requirements
listed below.
591 Lyot Stop
The GNIRS shall provide a cold Lyot stop at an image of
the telescope pupil (the secondary mirror). Any field stop before this
cold Lyot stop shall be at least 100 arcseconds in diameter. The Lyot stop
shall be capable of being changed when the instrument is off the telescope
and warmed up.
592 Coatings
The following characteristics of all optical coatings shall be specified in design documentation:
Transmission (for transmissive coatings) or reflection (for reflective coatings) over the
entire wavelength range
Transmission (for transmissive coatings) or reflection (for reflective coatings) within
each atmospheric window
Maximum allowed reflection (for transmissive coatings) or transmission (for reflective
coatings)
Environmental testing
Hardness or equivalent ISO standard
Adherence or equivalent ISO standard
Abrasion or equivalent ISO standard
Humidity
Cleanability
Water solubility
Surface appearance (flaking, peeling, finger prints, etc.)
All coatings shall be unaffected by repeated thermal cycling
over the operating, storage, and transportation temperature ranges.
593 Vacuum Environment
All optical components and coatings shall meet all performance
requirements when operated in a vacuum of less than 10-5 Torr
at operational temperatures.
594 Thermal Cycling
All optical components and coatings shall meet all performance requirements when thermally cycled at a maximum rate of temperature change of 0.25 K/minute.
Notes and Comments
1. Durability of coatings will be given by ISO or Mil-Spec.
600 Mechanical Requirements
610 Rigidity and Repeatability
The GNIRS shall be designed to be rigid, and to meet all
the requirements listed below.
611 Alignment of the Instrument to the Telescope Optics
The alignment of the GNIRS cold stop with the secondary
mirror shall be set and maintained to better than 1% of the apparent secondary
mirror diameter.
611 Tracking with the OIWFS
Tracking performance when using the GNIRS OIWFS shall
hold motion of the image on the slit to at most 10 microns in one hour
of observation.
612 Tracking with the Peripheral Wavefront Sensor
Tracking performance when using the peripheral wavefront sensor is (TBD - flexure to be with respect to ISS).
613 Motion of Slit Image on Detector
The maximum image motion of the slit on the detector in one hour of observation shall be no more than 0.1 pixel (2.7 m m).
614 Mechanism repeatability
All mechanisms shall return to a normal position with repeatability that limit motion of the slit image on the detector to 0.1 pixel and of the object image on the slit to 10 microns. This is a goal and not a requirement for the camera turret.
620 Mechanical and Thermal Tolerances
Notes and Comments
1. Mechanical stability of all mechanical components is dependent on the optical tolerance analysis given in section 530. The translation from section 530 to the mechanical tolerances is given in the table below.
Mechanical Tolerances in Alignment
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
630 Thermal Performance
Notes and Comments
1. Thermal effects due to temperature gradients (TBD) outside the dewar, inside the dewar, and near the detector shall be considered in the design of the GNIRS.
2. Thermal transient effects during cool-down or warm-up shall be considered in the design of the GNIRS.
640 Space Requirements
644 Electronic Enclosures
All GNIRS electronic enclosures mounted on the ISS shall be counted in the space requirements given above.
645 Access to Electronic Enclosures
The electronic enclosures shall be accessible without removing the GNIRS from the ISS.
646 Access to Vacuum Ports
Vacuum ports on the GNIRS shall be accessible without removing the instrument from the ISS.
646 Access to Liquid Nitrogen Ports
The GNIRS does not use liquid nitrogen.
647 Access to Helium Ports
Helium ports on the GNIRS shall be accessible without removing the instrument from the ISS.
648 Mechanical Connections
All mechanical connections on the GNIRS shall be accessible
without removing the instrument from the ISS and while mounted with other
instruments.
Notes and Comments
1. Space requirements are specified in ICD 1.1.1/1.9 and the ICD for the ISS (/1.9).
650 Mass and Center of Gravity Requirements
The GNIRS shall meet all mass and center of gravity requirements
listed below.
651 Total Mass
The GNIRS shall have a mass of 2100 kg or less.
652 Center of Gravity
The GNIRS shall have a center of gravity on the port axis
1000 mm mm from the mechanical interface on the ISS. The tolerance is as
specified in ICD XXXX
653 Balance Tolerance
The out-of-balance during operation due to moving elements,
fixtures, (including LN2 boiloff) etc. within the GNIRS shall
be less than 400 N-m.
654 Ballast Weight
A ballast weight and its supporting structure shall be
supplied as required to meet the above requirements.
655 Electronic Enclosures
All GNIRS electronic enclosures mounted on the ISS shall
count in the mass and center of gravity requirements given above.
660 Cooling System
The GNIRS shall meet all cooling system requirements listed
below.
661 Cooldown Time
The GNIRS cooling system shall have the capability to
cool the instrument from room temperature to operating conditions, with
a goal of 72 hours. Cryogenic closed cycle coolers shall be used to maintain
the operating temperature once it has been achieved.
662 Warmup Time
The GNIRS shall not require more than 24 hours to warm
up the entire instrument from operating conditions to room temperature.
663 Thermal Stability
The GNIRS detector assembly shall have an active temperature control system providing a variable accuracy to be set at the optimum temperature for the detector between 30 K and 40 K, and a stability of +/- 0.1 K.
664 Vibration
Adequate measures shall be taken to ensure that the use
of cryogenic closed cycle coolers shall not introduce sufficient vibrations
into the mechanical structure to prevent meeting all rigidity, alignment,
tracking, and other performance requirements.
Notes and Comments
670 Vacuum System
671 Staging and Holding Areas
(TBD)
672 Vacuum Pump Capacity and Selection
(TBD)
673 Operating Procedure and Set-Up
(TBD)
674 Test Set-Up
(TBD)
680 Operational Requirements for Mechanisms
GNIRS mechanisms shall meet the requirements listed below.
681 Safety
No mechanism shall be back-driveable in the event of loss
of electrical power.
682 Time to Function
The goal for all individual mechanisms is to take no more
than 60 seconds to operate from any position to any other position. The
maximum allowable time is 180 seconds. The time to re-zero or "home" any
mechanism from an unknown position shall not exceed 210 seconds.
690 Instrument Handling
The GNIRS shall be delivered with an instrument handling
rig that can hold the GNIRS during installation on the ISS. The instrument
handling rig shall also hold the GNIRS during storage and will provide
assistance during assembly and disassembly.
Notes and Comments
1. The handling rig is intended to be used for instrument storage, safe movement around the instrument preparation and assembly areas, and for assembly and disassembly assistance. Consult the Instrumentation Control Document, Section 3.2.
2. Instruments are mounted on the ISS using the Cassegrain handling rig (supplied by Gemini). An instrument will be moved from the storage/preparation area in the facility to the observing floor via the service lift of the large lifting platform. Once on the observing floor, the instrument will be transferred from its handling rig to the Cassegrain handling rig. Depending upon the ISS port that the GNIRS is to occupy (side- or up-looking port), the GNIRS handling rig will orient the instrument in the proper configuration before transfer to the Cassegrain rig, which is a maneuverable lifting platform. The GNIRS will then be maneuvered to the intended port by the Cassegrain handling rig, positioned, and the GNIRS load bearing fasteners will be engaged (dowels or expanding bolts), followed by the load bearing clamping fasteners (clearance bolts). The position of location and load bearing fasteners is outlined in the Critical Design for the Cassegrain Assembly. Each consists of a circular raised boss with an annular flat surface. At the center of the surface is a locating counterbore with a tapped hole further in. More guidance regarding the Cassegrain handling rig and the general scheme for mounting instruments can be found in the Instrumentation Control Document, Section 8.1.
3. A handling
rig usable in all telescope orientations is likely to be very large, complex
and extremely expensive. It is anticipated that the GNIRS will be installed
in the zenith pointing position of the telescope.
6A0 Metric Dimensioning
Metric dimensions shall be used in the GNIRS.
6A1 Metric Dimensions on Drawings
Metric dimensions in millimeters shall be used in all
as-built drawings, with dimensions called out to 0.01 mm.
6A2 Metric Fasteners
All screws, bolts, nuts, tapped holes, and fasteners shall
be of standard metric sizes, and called out as such on the as-built drawings.
Notes and Comments
1. This requirement permits the use of "soft metric" design,
in which, e.g., two holes are spaced 4 inches apart by the designer. The
fabrication drawings may show dimensions in inches to reduce confusion
and retooling costs, but the as-built drawings will be converted before
delivery to metric dimensions, e.g., 4 inches will be shown as 101.60 mm.
700 Electrical and Electronic Requirements
710 Electronic Design Requirements
The GNIRS shall be designed in accordance with modern
electronics engineering practice for astronomical instruments.
711 Grounding and Shielding
Separate ground returns shall be provided for low level
signals, noisy components such as relays and motors, and hardware components
such as mechanical enclosures, chassis, and racks.
712 Electrostatic Discharge
The GNIRS design shall protect sensitive components from
electrostatic discharge.
Notes and Comments
1. Good grounding practice is discussed in Ott, Henry W., Noise Reduction Techniques in Electronic Systems, Second Edition, AT&T Bell Laboratories, 1988, Chapter 3.
2. Ott (above) discusses electrostatic discharge on page
332.
720 Cassegrain Cable Wrap Interfaces
Notes and Comments
1. Cassegrain cable wrap interfaces are provided by the break out panels on the ISS, and should be defined by the ICD 1.5.2/1.9.
730 Temperature Monitoring
Thermocouples (or gas thermometers) are required to monitor the cryo environment within the dewar and the detectors
731 Temperature Sensor Locations
(TBD)
732 Sensor Interfaces
The temperature sensor read-out interface shall be part
of the Engineering Interface as described in section 234.
Notes and Comments
1. The GNIRS will have a variety of temperature sensors inside the dewar and between the radiation shields. Normal NOAO practice is to provide a total of 24 such sensors.
2. The GNIRS detector will be provided with temperature sensors, at least 2 for the mount and 2 for the detector.
3. The GNIRS electronics temperature is monitored by the Gemini thermal enclosure system.
800 Software Requirements
810 Software Design Requirements
The GNIRS shall be a "conforming" instrument, in that
it shall use EPICS and conform to Gemini software and control system standards
and the requirements listed below.
811 Use of EPICS
The GNIRS shall use a standard Gemini configuration of a workstation for the operator interface, connected to an EPICS based system used for controlling motors, coolers, and heaters and for receiving status information from sensors.
812 EPICS System
The EPICS system shall be a standard Gemini unit (VME crate, 68040 CPU, VxWorks operating system.
813 Use of the Core Instrument Control System Software Package
The GNIRS software engineers shall use the Gemini-furnished
Core Instrument Control System Software Package to develop the Instrument
Control System (ICS).
Notes and Comments
1. The Gemini Software Design Description contains guidelines for developing Gemini-compatible software.
2. Gemini will provide the GNIRS team with a Core Instrument Controller Software Package to aid in the development of an ICS that conforms to Gemini requirements and standards.
814 Functionality
The following capabilities shall be provided by the GNIRS software:
The GNIRS must meet the following objectives:
The GNIRS software will not:
1. Refer to section 230 for additional software requirements regarding the Engineering Interface.
820 EPICS Compatibility
The GNIRS software shall be based on and use an EPICS system as required
by 810.
821 Interfaces to the Gemini System
Interfaces to the Gemini system shall conform to the descriptions
presented in the Core ICS documentation. In particular, all OCS
commands to, and responses from, the GNIRS shall be by CAD, CAR and SIR
EPICS records as described in the Core ICS documentation. Interfaces
to other Gemini subsystems shall conform to the relevant Interface
Control Documents.
Notes and Comments
1. Low level software in the GNIRS will be a mixture of
EPICS code and C-coded tasks, both running directly on VxWorks.
830 Gemini Furnished Software
Gemini shall furnish a complete and final set of all Interface Control Documents not later than the GNIRS PDR.
Gemini shall furnish to the GNIRS software engineers a functional CICS (see 813) as soon as practical, and shall provide updates as they become available. The first release of the CICS should be by GNIRS PDR with general information available before then.
Gemini shall furnish a complete interface description of the detector sub-system as soon as practical.
Gemini shall furnish a complete interface description of the OIWFS sub-system as soon as practical.
Gemini shall furnish a DHS (or a simulation thereof) when the detector subsystem is delivered.
Gemini shall furnish a prototype of the OIWFS components controller software as soon as practical. This software must simulate operation of the OIWFS in a stand-alone mode.
Gemini shall furnish software for obtaining accurate time information when the detector sub-system is delivered.
900 Other Requirements
910 Documentation
The GNIRS shall be delivered with adequate documentation
to facilitate the operation, maintenance, and repair of the instrument.
911 User’s Manual
The User’s Manual shall be written to enable a new user
of the GNIRS to easily get acquainted with the operation of the instrument.
912 Service and Calibration Manual
913 Software Maintenance Manual
This document described the software at a level of detail sufficient for a competent programmer not initially familiar with the software can maintain it properly. It includes detailed verbal descriptions of all software systems and subsystems written by NOAO at a high level, including purpose, organization, and interaction with any other software systems and subsystems. Included are any systems analyses, data flow diagrams, data dictionaries, structure charts, and mini-specs developed during the software design process, updated to reflect as-built conditions. Also included are listings of all software delivered as part of the GNIRS, including firmware in ROM’s, PROM’s and DSP’s. All software source code modules shall include a standard header documenting the module contents, and each module shall contain a sufficient number of comments explaining the purpose and function of each section of code that a programmer unfamiliar with the software can understand it. Any systems engineering analyses that led to the allocation of functions between hardware and software or the software design used are included.
914 As-Built Drawings
The as-built drawings shall show all dimensions in millimeters, down to 0.01 mm. All fasteners specified in these drawings shall be standard metric sizes. All drawings shall otherwise be to NOAO standards used in instruments of similar size, function, and complexity.
915 Drawing Standards
(TBD)
916 Drawing Numbering System
(TBD)
917 Drawing Filing System
(TBD)
Notes and Comments
1. It is anticipated that ANSI specifications will be used for final drawings.
2. Final released drawings will be maintained by IGPO.
920 Training
The GNIRS development team shall provide training documentation and a training course to Gemini operations personnel on the operation, maintenance, and repair of the GNIRS.
930 Reliability
The GNIRS shall be designed and built to be reliable.
931 Downtime
The GNIRS shall have a total downtime of 2%, with 1% as
a goal. Where possible, component failure shall result in gradual performance
degradation. Single point failures that may result in significant downtime
shall be determined and, where necessary, critical spares shall be identified.
932 Continuous Duty
The GNIRS shall be designed and built for continuous operation. Modules containing moving parts, e.g., cryocooler cold heads, shall be designed or selected to meet Requirement 931 assuming continuous operation.
940 Maintainability and Serviceability
The GNIRS shall meet the requirements for maintainability
in the Instrumentation Control Document, Section 2.2.
941 Standard Components
Wherever possible, the GNIRS shall use unmodified commercially
available standard components.
942 Modularity
To the extent possible, the GNIRS shall be designed to
be modular.
943 Access
Access to components and subassemblies shall be considered
in the GNIRS design, particularly for those elements that are accessed
frequently. Tool and hand clearances shall be considered, as well as space
required to remove modules, visual access to components (or a means to
feel their correct position and alignment, e.g., for electronic connectors).
944 Alignment
Alignment of optical components shall be achieved to the
extent possible by accurate machining of locating fixtures.
945 Relative Equipment Arrangements
Equipment shall be located with due consideration of the
sequence of operations involved in maintenance procedures. To the extent
possible, the most accessible locations shall be reserved for the items
requiring most frequent access.
946 Subassemblies
Subassemblies of the equipment that require more frequent
service (inspection, adjustment, repair, or replacement) shall be configured
as plug-in modules or, if in racks, as drawers that can be withdrawn easily.
947 Handling
Modules greater than 20 kg in mass shall have suitable
handles for use in removing, replacing, and carrying them. Handles shall
be located such that the vector sum of resultant handling forces shall
pass close to the center of gravity of the unit.
948 Revisability
Multilayer electronic boards shall not be used unless
they are replaceable as a module. Backplane interconnections between custom
boards is discouraged.
Notes and Comments
1. Requirement 944 can be achieved by machining captive
thick shims to achieve the assembled tolerances, but the intention is to
avoid an involved re-alignment procedure on assembly or re-assembly.
950 Lifetime
The GNIRS shall be designed for an operational lifetime
of 10 years without a major overhaul. Components likely to affect the lifetime
requirement shall be identified.
Notes and Comments
1. Battery back-up systems will require replacement at
intervals of less than 10 years.
960 Safety
Home
Planning
Progress Reports
System Design Notes
Meetings/Reviews
Subsystems
Configuration Images
Requirements
Memoranda
Staff
FTP Site
NOAO Intranet Services |
![]() |
|
Statement |
National Optical Astronomy Observatories, 950 North Cherry Avenue, P.O.
Box 26732, Tucson, Arizona 85726,
Phone: (520) 318-8000, Fax: (520) 318-8360